05-0067 Single Family Sewer 062105
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
June 21, 2005
Tahoma Terra LLC
4200 6th Ave SE
Suite 301
Lacey, WA 98503
Re: Tahoma Terra Sewer Design East of the Thompson Creek
City of Yelm Project MPC-05-0067-YL
Dear Mr. Bloom,
The City of Yelm, after careful consideration and review of the proposed gravity flow sewer system to a major pumping station, has decided to require that Tahoma Terra use the current
adopted sewer system design for that portion of the project located east of Thompson Creek. You will need to modify your design to meet our current Development Guidelines STEP System.
This shall include a force main in the street and a tank and pump on each lot.
After many meetings and discussions, with our consultants and maintenance personal, we have concluded that we are not yet ready to commit to a new system design along with the requirements
it would require. We feel that we need more time to work out the details of this system and to arrive at a design that would not only meet our current need but the needs of the future.
Thank you for your effort on the designs you submitted. We will take them into consideration as we move forward during the next year to arrive at a standard design that can be used on
the remainder of Tahoma Terra. If you have any questions or concerns please feel free to contact me.
Community Development Department
Respectfully,
James Gibson
Development Review Engineer
C: Tim Peterson, Public Works Director
Grant Beck, Community Development Director