Loading...
Proj Rev Date MemoCity of Yelm Community Development Department P.O. Box 479 Yelm, WA 98597 (360) 458-3835 (360) 458-3144 FAX Memorandum To: SPRC From: Roberta Allen, Administrative Assistant Date: September 26, 2005 Re: SUB-05-0304-YL – Project Review Schedule for Tahoma Terra Division 2 Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please let me know as soon as possible. The following is the tentative review schedule for the project. September 26, 2005 – Notice of Application distributed – begin 15 day comment period. October 19 and October 26 – SPRC project review. Department comments/conditions of approval for staff report. Complete Staff report for public hearing. Public Hearing Notice to Paper/Mailing/Post site. (publish 10 days prior to hearing) Public Hearing in front of Hearing Examiner (try to schedule first Monday of the month) Hearing Examiner approval completed