Re: Final Occupancy at the NAPA site.
Dear Mike:
The Community Development Department inspected the NAPA site for final occupancy on June 15, 2006. The following items must be completed prior to issuing a Certificate of Occupancy
for Walts Tire, and the final Certificate of Occupancy for the NAPA building.
The sidewalks must be backfilled to sidewalk level for pedestrian safety.
Please coordinate with the City of Yelm Water Department (360) 458-8410 for final approval requirements.
Please coordinate with the City of Yelm Sewer Department (360) 458-8411 for final approval requirements.
A blanket easement is required for utilities, and a bill of sale for the STEP system.
Required landscaping must be complete.
The refuse container must be complete.
The Walts tire building was originally permitted as an auto repair facility. The change to a tire store creates more traffic than an auto repair facility. The TFC charges for a tire
store of 3,240 sq. ft. are $12,472.50. The balance of $5,505.00 is due.
If you have any questions, please feel free to call me at (360) 458-8496.
Sincerely,
Tami Merriman
Department of Community Development