STAFF REPORT
To: Mayor Adam Rivas Yelm City Council
From: Tami Merriman, Assistant Planner
Date: October 18, 2005 (for October 26, 2005 City Council Meeting)
Subj: Mountain Sunrise Final Plat
Recommendation
Approval of Phase I of the final plat for Mountain Sunrise, SUB-02-8329-YL.
Background
The Yelm Hearing Examiner approved, with conditions, a preliminary plat for the above referenced project on August 23, 2003. The project has finished construction of Phase I, and the
applicant has filed a complete application for final plat.
Current Situation
Staff has reviewed the plat for compliance with the conditions of approval placed on the preliminary plat. Staff is satisfied that phase I of the final plat meets all conditions of
the preliminary approval.