CC STaff Report
City of Yelm
STAFF REPORT
To: Mayor Ron Harding Yelm City Council
From: Tami Merriman, Associate Planner
Date: November 6, 2006 (for November 14, 2006 City Council Meeting)
Subj: Mountain Sunrise Phase II Final Plat
Recommendation
Approval of Phase II of the final plat for Mountain Sunrise, SUB-02-8329-YL.
Background
The Yelm Hearing Examiner approved, with conditions, a preliminary plat for the above referenced project on August 23, 2003. The project has finished construction of Phase II, and the
applicant has filed a complete application for final plat.
Current Situation
Staff has reviewed the plat for compliance with the conditions of approval placed on the preliminary plat. All standard improvements are complete.
The plat falls into the area of the SR 510 Yelm Loop, and provisions have been made to protect the future right-of-way by not allowing any permits to be issued in the right of way area
until such time as permits have been issued for all other lots within the plat. In light of this, an agreement with the developer has been made to defer certain improvements in the
right-of-way area, to be completed prior to any building permit issued for lots located within the right of way.
Staff is satisfied that phase II of the final plat meets all conditions of the preliminary approval.