Proj Rev Date MemoCity of Yelm
Community Development Department
P.O. Box 479
Yelm, WA 98597
(360) 458-3835
(360) 458-3144 FAX
Memorandum
To: Site Plan Review Committee
From: Grant Beck, Community Development Director
Date: January 30, 2003
Re: SUB-02-8329-YL – Project Review Schedule for Benum|Coyne
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
February 5 – SPRC TIA and Project Review. Department comments.
February 7 – Notice of Application distributed – begin 15 day comment period.
February 7 – Environmental Determination issued by Planning Department. Begin 14 day comment period followed by 7 day appeal period.
February 28 – Environmental Determination appeal time expired.
March 21 – Public Hearing notice to paper, mailing and post site.
March 24 – Complete Staff report for public hearing.
April 7 – Public Hearing
April 17 – Hearing Examiner Decision