8340 Punchlist 2nd time 092606
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
September 26, 2006
Steve Martin
Les Russell Construction
P.O. Box 73156
Puyallup, Washington 98373
RE: Cherry Meadows – Final Construction Punchlist - Second Walk Through
City of Yelm Project No. SUB-03-8340-YL
Dear Mr. Martin:
The Community Development Department and Public Works has completed a second walk-through of the above referenced plat. The following items and comments need to be addressed to prior
to submitting for final plat application.
Items are listed by the street in which they are located.
Community Development Department Misc. Comments:
Cullens Road:
Clean sidewalk
Utilities need to be buried. Cullens Rd. & 92nd Ave.
Finish Grade behind and front of sidewalk.
Chad Drive:
1. Clean off sidewalk.
2. Grade front and back of sidewalk
91st. Avenue:
1. Grade front and back of sidewalk.
2. Clean sidewalks.
Carrisa Avenue:
Grade in front and behind sidewalks.
Clean sidewalks.
Callie Avenue:
Grade front and back of sidewalk.
Clean sidewalks.
92nd Avenue:
Clean off sidewalks.
Grade in front and back of sidewalk.
Kayla Street:
Grade in front of and behind Sidewalk.
Clean sidewalks.
Community Development Department Landscape Comments:
Missing trees at the following lots; 37, 41, 60, 68, 75, 115, 118, 119, 155, 161, 182, 191
Tree on lot 157 is too close to sewer box.
Cullens Road and Killion Rd > Hydroseeding Required
Perimeter landscaping on Cullens and Killion required.
Pressure treated 4x6’s and Hydroseeding required throughout the plot
Dead Alders at storm pond on 92nd.
Hydroseeding required adjacent to pathway and open space
Picnic table not complete near play area.
Water Department Comments – September 5, 2006
Check all meter setters for clearance between meter nuts. Many of these are bent so a meter cannot be installed. Please contact water dept for an older meter body to check clearance
with if you do not have one already.
Check all meter box heights; make sure they are at final grade.
Finish cleaning out gate valve housings at Killion Rd and Kayla St. There are rocks around the operating nuts.
Gate valve at Killion Rd to Kayla St is hard to turn, please find out why.
Sewer Department Comments – September 26, 2006
Toning Wire could not be found in Carson Boxes for Lots: 127, 128, 173 and 174.
The Carson Box for Lot 140 has a rock lodged against the outside of the Carson Box and Pressure Line, which must be removed.
Need to clean out blow off box, at Cullen Road, the north side of the project.
Public Works Department Comments (Sidewalks and approaches) – September 26, 2006
1. 23 Driveway Approaches cracked. Marked with red paint
2. 6 Sidewalk Panels cracked. Marked with red paint
Please review these items. If you have any questions or comments, please call me at (360) 458-8423 and I will be happy to further assist you.
Community Development Department
Respectfully
Steve Harrington
Civil Engineering Inspector