8340 Eng Review No 3 052505
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
May 25, 2005
Grant Middleton
Larson and Associates
4401 So 66th
Tacoma, WA 98409
RE: Cherry Meadows - Civil Engineering Review No. 3 – Onsite Plans
City of Yelm Project No. SUB-03-8340-YL
Dear Grant:
I have reviewed the onsite construction documents submitted for Cherry Meadows. The following list of comments will need to be addressed.
Roadway and Storm Drainage:
All walls over 4 feet in height need to have a structural engineer stamp sealing the design. The City has not received the structural design for the walls as of the letters date.
The City has changed the mailbox requirements for new subdivisions. The detail you have on the plans is not longer used. The City has changed over to Cluster Box Units (CBU’s) or lock
boxes for all subdivisions. You have shown 4 locations for mail delivery. These appear to meet the city requirements.
Please forward the structural calculations for review and approval. Until then please do not submit additional plan sets. After the structural review is completed we will request the
final submittal for signature. If you have any questions please do not hesitate to contact me at (360) 458-8438 or by email at jimg@ci.yelm.wa.us.
Respectfully,
Community Development Department
Jim Gibson
Development Review Engineer