Memorandum
To: SPRC
From: Roberta Allen, Administrative Assistant
Date: May 27, 2003
Re: SUB-03-8340-YL – Project Review Schedule for Rosewood
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
May 27, 2003 – Notice of Application distributed – begin 15 day comment period.
June 18, 2003 – SPRC Environmental Review. Department comments/mitigation requirements for Environmental Review.
June 23, 2003 – Environmental Determination issued by Planning Department. Begin 14 day comment period followed by 7 day appeal period.
July 16 and July 23, 2003 – SPRC project review. Department comments/conditions of approval for staff report.
July 16, 2003 – Environmental Determination appeal time expired.
July 21, 2003 – Public Hearing Notice to Paper/Mailing/Post site (July 25, 2003).
July 25, 2003 – Complete Staff report for public hearing.
August 4, 2003 – Public Hearing in front of Hearing Examiner
August 18, 2003 – Final letter of approval completed