Proj Rev Date MemoCity of Yelm
Community Development Department
P.O. Box 479
Yelm, WA 98597
(360) 458-3835
(360) 458-3144 FAX
Memorandum
To: SPRC
From: Roberta Allen, Administrative Assistant
Date: April 11, 2005
Re: SUB-05-0096-YL – Project Review Schedule for Country Vista
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
April 11, 2005 – Notice of Application distributed – begin 15 day comment period.
April 27, 2005 – SPRC Environmental Review. Department comments/mitigation requirements for Environmental Review.
Environmental Determination issued by Planning Department. Begin 14 day comment period followed by 7 day appeal period.
Environmental Determination appeal time expired.
SPRC project review (probably 2 meetings). Department comments/conditions of approval for staff report.
Complete Staff report for public hearing.
Public Hearing Notice to Paper/Mailing/Post site. (publish 10 days prior to hearing)
Public Hearing in front of Hearing Examiner (try to schedule first Monday of the month)
Hearing Examiner approval completed