City of Yelm Daily Inspection Form 3 Yelm Creek Storm Vault
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 9/26/06
Day: Tuesday
Time: 3:30 p.m.
Project Name:
Yelm Creek
Project Number
SUB-05-0239-YL
Project Description:
Subdivision
Contractor's Name:
RGD Rainier General Development
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Cool, cloudy, Soil conditions are Dirt and Rock
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.)
Contratractor placed 48” ADS Wet Vault in Place. Connected to C.B # 1, with 12” ADS.
Wet vault was put in place and back filled with native material and not washed rock. Roger said this was per the approval of Jim Gibson, prior to my being on this project.
Contractor placed an Catch Basin in between Wet Vault and Catch Basin # 1. I believe this was to make the angle or bend with out using a 45 or 22 ½ Degree Bend?
Tony and Roger said this was put in per Jim Gibson approval before I was employed with the City of Yelm. (This is not speced on plans this way)
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material)
Contractor Placed 48 “ ADS Wet Vault.
5. Sketch or Paste Pictures Below:
Date
9/26/06
Typed or Printed Name and Title
Steve Harrington
Signature