City of Yelm Daily Inspection Form 6 Yelm Creek Sidewalk Prep and Pour City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 9/29/06 Day: Friday Time: 9:30 p.m.  Project Name: Yelm Creek Project Number SUB-05-0239-YL  Project Description: Subdivision Contractor's Name: RGD Rainier General Development  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Cool, cloudy, Soil conditions are Dirt and Rock  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Part of sidewalk poured on Friday September 29, 2006. The rest of sidewalk will be poured on Monday October 2, 2006  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) 5/8 Crushed Rock placed and compacted for sidewalk.  5. Sketch or Paste Pictures Below:    Date 9/29/06 Typed or Printed Name and Title Steve Harrington Signature