Memorandum
To: SPRC
From: Roberta Allen, Administrative Assistant
Date: January 18, 2005
Re: SUB-05-0003YL – Project Review Schedule for Cullens Road Preliminary Plat
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
January 18 – Notice of Application distributed – begin 15 day comment period.
February 9 – SPRC Environmental Review. Department comments/mitigation requirements for Environmental Review.
February 16 – Environmental Determination issued by Planning Department. Begin 14 day comment period followed by 7 day appeal period.
March 9 – Environmental Determination appeal time expired.
March 9 & March 16 – SPRC project review. Department comments/conditions of approval for staff report.
March 18 – Complete Staff report for public hearing.
March 21 – Public Hearing Notice to Paper/Mailing/Post site.
April 4 - Public Hearing in front of Hearing Examiner.
April 14 – Final approval letter completed.