cr-041603 105th 97 lot Subdivision
Pre-Application Meeting
Civil Comments
Date April 16, 2003
***These comments are preliminary in nature and are not intended to represent final comments and or requirements for the City of Yelm. Until a complete application is made, the Community
Development Department can only attempt to inform the applicant of general requirements as they appear in the form presented by the applicant at the time of pre-submission.
Proponent: SCA Consulting Group / John Loutzenhiser
Project: 97 lot Subdivision
Project Loc: Clark/105th/3rd, Yelm WA 98597
Tax Parcel: 2273021-0600, 0700 and 0800
Water:
The proposed site would be required to connect to the City's water system. There is an existing 8” watermain located in 105th Ave SE. This watermain will need to be extended to the
west edge of your property line and/or the end of the frontage improvements. A second watermain will have to be extended from the end of 3rd St into the project and connect with the
105th Ave SE new waterline.
The development’s internal roadways will be required to have 8” watermain installed to serve fire hydrants and home services.
The proposed site plan shows new lots located over existing waterlines. This will not be allowed.
Residential water connections are based on a consumption rate of 240 gallons per day and are charged at a rate of $1,500 per a residential connection (fee subject to change) inside city
limits. Each residential unit would be charged for one connection. This is a one-time connection fee and is payable a building permit issuance. Also there is a water meter fee of
$300.00 per a meter. (5/8” residential meter size only)
Irrigation Meter:
An irrigation meter may be installed for the purpose of irrigation. A backflow prevention device will be required for all landscape irrigation connections.
Sewer:
The proposed site would be required to connect to the City's STEP sewer system. This development is located in two separate sewer basins. By being located in two different basins, the
sewer mains in either basin have not been sized to accommodate all 97 lots that are being proposed. The City of Yelm will have to review this information further.
Note: The sewer main located in Parkview Subdivision is located in a third sewer basin.
The development’s internal roadways will be required to have sewermain installed to serve all home services. This sewer main will be sized accordingly to serve the proposed lots and
provide system continuity.
Residential sewer connections are based on a consumption rate of 240 gallons per day and are charged at a rate of $5,125.00 per a residential connection (fee subject to change) inside
city limits. Each residential unit would be charged for one connection. An inspection fee of $145.00/lot will be charged for STEP sewer system. These fees are payable a building permit
issuance and are one-time connection fees.
Fire:
Fire protection must be provided per the Uniform Fire Code. There will be requirements for installation of fire hydrants, fire truck access and fire truck turn-around. These will be
determined upon further review of the preliminary plans.
Stormwater:
This project will require storm drainage treatment and disposal of all stormwater. The stormwater manual currently used is the 1992 Department of Ecology Stormwater Manual. The project
area and all frontage improvements must have stormwater controls designed and installed. All of the stormwater facilities are required to be located outside of the right-of-way. At
the time of Preliminary Plat application, you are required to submit a Preliminary Stormwater Plan and report.
Street Improvements:
Frontage improvements shall be consistent with Yelm’s Development Guidelines. Your project will be required to improve the frontage along 105th Ave SE. These improvements are classified
as “half street” improvements where the roadway already exists. If the roadway is not constructed in the center of right of way, the project will be required in complete the half street
improvements on the project side and 12’ drive aisle on the opposite side. 105th Ave SE is classified as a Neighborhood Collector roadway.
All internal roadways will be classified as Local Access Residential streets. These streets shall connect the existing 3rd St and 105th ST. See attached roadway sections for specific
details about these requirements.
Street Lighting:
Street lighting shall be designed and installed as required per the City of Yelm’s Development Guidelines. The street lighting plan will be reviewed and approved at the time of civil
engineering plan review.
ADA Requirements:
The American Disabilities Act requires the improvements to be ADA accessible. Facility improvements will have to meet current code. Review of these improvements will be determined
upon further review of the civil plans.