cc-081004 Change Fitness at McGowen Prop
M E M O R A N D U M
City of Yelm
Community Development Department
Engineering Division
Pre-Application Meeting
August 11, 2004
These comments are preliminary in nature and are not intended to represent final comments and or requirements for the City of Yelm. Until a complete application is made, the Community
Development Department can only attempt to inform the applicant of general requirements as they appear in the form presented by the applicant at the time of pre-submission.
Proponent: Jim Coran
Project: Change Fitness at McGowen Property
Project Location: Grove Road
Yelm, WA 98597
Water
The proposed site is currently connected to the City of Yelm’s water system.
This proposal will continue to be served by the City of Yelm’s Public water system.
The City of Yelm’s water system is located along Grove Road. This water system is 10” in size.
An additional water connection fees are based on a consumption rate of an ERU (240 gallons per day) and are charged at a rate of $1,500/ERU (fee subject to change) inside city limits.
At the time of application submittal you will be required to submit water usage calculations provided by a licensed civil engineer for the proposed commercial use of the property.
Connection fees will be calculated using the information provided by your engineer.
Sewer TC \l1 "
The proposed site is currently not connected to the City of Yelm’s S.T.E.P. sewer system. This proposal has two options for service. Extend the City of Yelm’s public sewer system to
the proposed project or apply for a Thurston County Approved onsite septic disposal system.
The City of Yelm’s public sewer system is located at approx. the intersection of Bald Hills Road and SR 507. This sewer line would have to be extended to the proposed project. After
extending the sewer main, you will be required to install the standard
STEP tank system to serve your use. Sewer connection fees are based on the same ERU as water and are charged at a rate of $5,269/ERU (fee subject to change) inside city limits. At
the time of application submittal you will be required to submit water usage calculations provided by a licensed civil engineer. The sewer fees will be calculated using the information
provided by the engineer.
Fire
Fire protection to the buildings must be provided per the International Fire Code. The water system may have to be extended on to the properly to provide fire hydrant coverage. I suggest
the applicant meet with the Building Official to determine the fire protection requirements.
Stormwater TC \l1 "
If the project creates over 5,000 square feet of impervious surface, a preliminary stormwater plan will be required at the time of land use application and a final plan at the time of
civil plan review. The City has adopted the 1992 Department of Ecology Stormwater Manual. If a stormwater plan is not required, stormwater runoff still may not be concentrated and
discharged to the ground or to adjacent properties, including public rights-of-way. Required landscaping areas may not be used for stormwater treatment.
Street Improvements TC \l1 "
Frontage improvements will be required for this project. Grove Road is identified as a neighborhood collector roadway. The required improvements would be a 16’ travel lane, concrete
curb and gutter, a 6’ planter strip with street trees, and a 5' sidewalk. Half street improvements will be required to be constructed along the frontage of this property before occupancy.
Street Lighting TC \l1 "
Street lighting may be required for this project and will be reviewed upon civil engineering application.
ADA Requirements
The American Disabilities Act required that facilities are ADA accessible. Facility improvements will have to meet current code. Review of these improvements will be determined upon
further review of the civil and architectural plans.