Loading...
lasco planning City of Yelm Community Development Department 105 Yelm Avenue West P.O. Box 479 Yelm, WA 98597  Pre-Application Meeting December 8, 2004 These comments are preliminary in nature and are not intended to represent final comments and or requirements for the City of Yelm. Until a complete application is made, the Community Development Department can only attempt to inform the applicant of general requirements as they appear in the form presented by the applicant at the time of pre-submission. Proponent: Lasco Bathware Project Proposal: Addition of 42,484 sq. ft. Project Location: N.P. Road. Zoning and Setbacks The property is zoned Industrial District (I), Chapter 17.40 YMC. This district allows the manufacture of goods or products as a permitted use subject to site plan review. Applications to develop, remodel or improve properties and structures within this zone shall require review and approval of a site plan in accordance with Chapter 17.84 YMC. Site plan review and approval shall be required prior to the use of land or building for the location of any commercial, industrial or public building. Exemptions from site plan review shall be granted if there is no addition of square feet, nor additional tenant, or the expansion is for storage only. Parking The requirements for off-street parking and their design shall be regarded as the minimum; however, the owner, developer, or operator of the premises for which the parking facilities are intended shall be responsible for providing adequate amounts and arrangement of space for the particular premises even though such space is in excess of the minimum set forth. Chapter 17.72 Industrial uses require one space per employee based on the greatest number of employees on a single shift, plus one square foot parking per square foot of display or retail area, plus one space for each vehicle owned, leased or operated by the company. Yelm Development Guidelines 4G.110 states; “in all commercial and industrial developments, parking areas shall be so arranged as to make it unnecessary for a vehicle to back out into any street or public right-of-way. A parking plan shall be submitted to the Community Development Department for review and approval a the time of application for site plan review. All required parking areas must be paved, striped and landscaped. Ingress/Egress Ingress and egress at the site shall be consistent with the Yelm Development Guidelines, section 4B.140. Existing vehicular access to the site is by N.P. Road, and by Rhoton Road. Access placement shall be reviewed at the time of application. Landscaping: Chapter 17.80, Type I, II, III, IV & V Type I landscaping is intended to provide a very dense sight barrier and physical buffer to separate conflicting uses, and land use districts. Type I landscaping is required between this site and the residential use ro the northeast. Existing vegetation may be retained, and could meet this requirement. Type I landscaping is characterized by a 15 foot landscape strip in which any combination of trees, shrubs, fences, walls, earthen berms, and design features provides an effect which is sight-obscuring from adjoining properties. Type II landscaping is intended to provide visual separation of uses from streets, and visual separation of compatible uses so as to soften the appearance of streets, parking areas, and building elevation. This landscaping is used around the perimeter of a site, and adjacent to buildings. Type II landscaping would be required along the remaining perimeter property lines. Type II landscaping is charactorized by an 8 foot landscape strip between uses and a 5 foot strip around buildings of any combination of evergreen and deciduous trees (with no more than 50 percent being deciduous), shrubs, earthen berms and related plant materials or design features may be selected; provided, that the resultant effect is to provide partial screening and buffering between uses and of softening the appearance of streets, parking and structures. Type III landscaping is intended to provide visual relief where clear sight is desired. This landscaping is utilized along pedestrian corridors and walks for separation of pedestrians from streets and parking areas. Type III landscaping would be required as part of frontage improvements along Rhoton Road, and N.P. Road. Type III landscaping is typified by a six foot landscaping strip with street trees for a large overstory canopy along streets and pedestrian corridors and grass or other approved vegetation for groundcover. Earthen berms with grass or other vegetative groundcover and other design features may be worked into landscaping provided the resultant effect of providing a pedestrian-friendly environment and visual relief where clear site is required can be achieved. Type IV landscaping is intended to provide visual relief and shade in parking areas. At least 24 square feet of landscape development for each parking stall proposed. Each area of landscaping must contain at least 100 square feet of area and must be at least six feet in any direction. Each planting area must contain at least one tree. Live groundcover shall be provided throughout each landscaping area. No parking stall shall be located more than 50 feet from a tree. Type V landscaping is required in storm water retention areas, if required. The floor and slopes of any stormwater retention/detention area shall be planted in vegetation that is suitable and will thrive in hydric soils. The landscaping of the stormwater facility shall be incorporated with all on-site landscaping. A conceptual landscaping plan is required with the application for site plan review. Final landscaping and irrigation plan is required as element of civil construction drawings, with installation prior to occupancy. The refuse area must be large enough to accommodate a dumpster and recycle bin. Refuse areas must be screened with an enclosure of a material and design compatible with the overall architectural theme. A six foot wall or fence shall enclose any outdoor refuse collection point. The fence shall be a solid material such as wood or masonry. Traffic The City has adopted a Transportation Facility Charge (TFC) of $750.00 per PM peak trip. The Code provides a default table that the applicant can use to determine new PM trips generated. For industrial/manufacturing, the trip generation rate is .98 per 1,000 square feet. To determine the projects impact and fee, use the following formula for the use proposed: ((Peak PM Trip Rate * Gross Floor Area)/1,000) * $750.00 = TFC Example: .98 x 42,484 = 41,634.32 ÷ 1,000 = 41.63 x $750.00 = $31,226.25 If the applicant feels the proposed use would not generate the default number of trips as designated in the TFC Ordinance, and analysis prepared by a Washington State Licensed Engineer can be submitted to the City for review and consideration. SEPA An environmental checklist and Traffic Impact Analysis is required. Application and Process Site Plan Review, Chapter 17.84, is an administrative process. Minimum application requirements are located in Section 17.84.060 and are listed on the application form. A project of this size can expect completed review in approximately 14 to 18 weeks. Land use approval typically contains conditions of approval that the applicant must complete prior to receiving a building permit. Upon satisfactory completion of all conditions of land use approval, the applicant can submit building plans for approval.