PL CV 082306 Killion Crossing
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
Pre-Application Meeting
August 23, 2006
These comments are preliminary in nature and are not intended to represent final comments and or requirements for the City of Yelm. Until a complete application is made, the Community
Development Department can only attempt to inform the applicant of general requirements as they appear in the form presented by the applicant at the time of pre-submission.
Proponent: Killion Crossing, Nicole Sullivan
Project Proposal: Large Commercial Development
Project Location: Yelm Avenue West (SR 510) & Killion Road
Tax parcel number 21724130100
Zoning and Setbacks
The property is zoned Commercial (C-1) which is codified at Chapter 17.26 YMC. The C-1 district is intended to provide for the location of business centers to serve the needs of the
community for convenience goods and services such as food, drugs, household supplies, automobile servicing, recreation, entertainment and other uses related to, but lesser in scope,
than downtown core area uses.
The C-1 district allows retail/ food service as a permitted use subject to site plan review approval in accordance with Chapter 17.84 YMC.
Building setbacks are 15 feet from the front, 20 feet from the rear and 10 feet from the side property lines.
The maximum building height is forty (40) feet.
Critical Areas
All of Yelm is considered a critical aquifer recharge area. Existing development
regulations address the potential impacts to this critical area.
The City wetland maps indicate that the property is located outside of wetlands, flood zones, and high ground water areas buffer areas.
Landscaping and Design Review
Street Fronts (SR 510 & Killion Street)
The design guidelines require that development must define the street edge with building, landscaping, or other features, must provide direct access to the building from the frontage,
and provide treatment to spatially define the street edge when parking is adjacent to street frontages.
Type II landscaping is intended to provide visual separation of uses from streets, and visual separation of compatible uses so as to soften the appearance of streets, parking areas,
and building elevation. This landscaping is used around the perimeter of a site, and adjacent to buildings.
Type II landscaping is characterized by an 8 foot landscape strip between uses and a 5 foot strip around buildings of any combination of evergreen and deciduous trees (with no more than
50 percent being deciduous), shrubs, earthen berms and related plant materials or design features may be selected; provided, that the resultant effect is to provide partial screening
and buffering between uses and of softening the appearance of streets, parking and structures.
Side and Rear Yards
The design guidelines indicate that service areas, and outdoor storage be located away from neighboring properties to reduce conflicts and requires screening of refuse containers located
behind the building. No refuse container shall be permitted between a street and the front of a building.
The refuse area must be large enough to accommodate a dumpster and recycle bin. Refuse areas must be screened with an enclosure of a material and design compatible with the overall
architectural theme. A six foot wall or fence shall enclose any outdoor refuse collection point. The fence shall be a solid material such as wood or masonry.
Street Corners
Developments on corner lots must enhance the property’s visual qualities by installing substantial landscaping, a decorative screen wall, providing pedestrian access, and architectural
cover treatments.
Pedestrian Circulation
The following elements must be provided as part of the site plan for new developments:
All pedestrian paths must comply with the ADA.
Adequate lighting must be provided for pedestrian access.
Walkways should be integrated with the required parking lot landscaping.
Provide pathways through parking lots
Integrate transit stops into the planning of site improvements
Provide weather protection such as a canopy to create a covered pedestrian open space.
Provide at least 200 square feet of landscaping at or near the entry.
Provide pedestrian facilities such as benches, kiosks, or bicycle racks.
Provide pedestrian scaled lighting
Adjacent window displays
Provide artwork or special pedestrian scaled signs
Building Design and Details
To encourage buildings that are comfortable at a human scale, at least three of the following features must be incorporated into the building design:
Balconies in upper stories
Bay windows
Pedestrian oriented space
Individual windows
Gable or hipped roof
Porch or covered entry
Spatially defining building elements that define an occupied space
Upper story setbacks
Composing smaller building elements near the entry or pedestrian oriented street fronts
To ensure new development is compatible with Yelm’s architectural size and character, at least two of the following features must be incorporated into the building design:
Upper story setback
Horizontal building modulation
Modulated roof line
Building articulation
To encourage unique, identifiable architectural features at intersections, at least one of the following features must be included on a façade facing a public street:
Decorated roofline
Decorative treatment of windows and doors
Decorative railings, grill work, or landscape guards
Landscape trellises
Decorative light fixtures
Decorative building materials (masonry, wood details or patterns)
Concrete block walls must use textured blocks, colored mortar or a mix of other masonry types.
Metal roofing must be of high quality with a standing seam and can not be brightly colored.
Concrete must be architecturally treated.
Blank walls must be treated through trellis and plantings, landscaping beds or other methods.
Parking Lot Landscaping
Type IV landscaping is intended to provide visual relief and shade in parking areas.
At least 24 square feet of landscaping is required for each parking stall proposed. Each area of landscaping must contain at least 100 square feet of area and must be at least six feet
in any direction. Each planting area must contain at least one tree. Live groundcover shall be provided throughout each landscaping area. No parking stall shall be located more than
50 feet from a tree.
Transportation
Ingress and egress at the site shall be consistent with the Yelm Development Guidelines, Section 4B.140. A traffic impact analysis should review the required access points into the
site, storage for left turns onto Killion Street from Yelm Avenue West (SR 510) and the possible need for acceleration or deceleration lanes.
The City of Yelm has formed a Local Improvement District (LID) for the realignment of Killion Road, and installation of a traffic signal, as well as reconstruction of SR 510 (Yelm Avenue
W) from Cullens Road to Burnett Road. This site is part of the LID improvement area, and required frontage improvements will be completed as part of the LID.
The Traffic Impact Analysis required as part of the environmental review will indicate the impacts that the development will have on the transportation system and suggest mitigation
measures that may be required.
The City of Yelm has adopted a Transportation Facility Charge (TFC) of $750.00 per PM peak trip generated by new development. The code provides a default table that the applicant can
use to determine the number of new PM trips generated by a proposal.
The TFC charges are based on the type of use proposed. Each use may be significantly different. For example, the traffic generated from a fast food restaurant is much greater than
a “sit-down” restaurant. Retail sales are also determined by different factors.
Traffic Facilities Charges may be applied to off-site improvements required to mitigate potential significant impacts attributed to the proposed development if the required improvements
are capacity related.
Parking
The requirements for off-street parking and their design shall be regarded as the minimum; however, the owner, developer, or operator of the premises for which the parking facilities
are intended shall be responsible for providing adequate amounts and arrangement of space for the particular premises even though such space is in excess of the minimum set forth.
Chapter 17.72 YMC requires retail establishments to provide one parking space for every 250 feet of gross floor area. A restaurant requires one parking space for every 200 square feet
of gross floor area. Twenty five percent (25%) of the parking spaces may be compact.
A standard stall is 9 feet by 20 feet while a compact stall is 8 by 16. A loading space must accommodate a truck 45 feet in length, 12 feet in width, and 14 feet tall.
All parking areas must be surfaced with asphalt or concrete, and shall be striped and landscaped to the standards of the development guidelines.
The design details for parking lot construction can be found in the Yelm Development Guidelines.
Water
The site is currently not connected to the City of Yelm water system. The water mains are installed along SR 510 and Killion Road. It would be expected that this project will
connect to the existing water mains and extend the water system on your site as needed to support your intended uses.
Commercial water connections are based on a consumption rate of 900 cubic feet a month and are charged at a rate of $1,500 per connection (fee subject to change) inside the city limits.
An engineers estimate for water usage will be required as part of the civil plan submission. Water connection fees are payable at building permit issuance.
An irrigation meter shall be installed, provided an approved backflow prevention device is provided. As sewer use fees are calculated based on water usage, an irrigation meter will
lower monthly sewer bills.
All commercial buildings and irrigation systems are required to provide for cross-connection control through the provisions of a back flow prevention device installed on the water services.
A list of approved devices can be found at Chapter 246-290-490 WAC.
Sewer
The proposed site is currently not connected to the City of Yelm’s STEP sewer system.
The sewer force mains are installed along SR 510 and Killion Road. It would be expected that this project will connect to the existing sewer main located on Killion Road and extend
the step sewer system on your site as needed to support your intended uses.
This project will be required to install a City of Yelm STEP sewer tank(s) assembly. Also a grease interceptor will be required before the STEP tank in uses the City deems necessary.
The size of both the STEP tank and grease interceptor will be based on peak flows as calculated by the developer’s engineer, which must be submitted as part of the civil plan review.
Commercial sewer connections are based on a consumption rate of 900 cubic feet a month and are charged at a rate of $5,569.00 per a connection (fee subject to change) inside city limits.
An inspection fee of $145.00 per a connection will also be required.
Fire Protection
All projects need to have fire protection for the buildings. It is likely that fire flow may be an issue at this location, which will be addressed through building official review of
the proposed building uses and construction material used for the buildings.
Stormwater
Developments with additional impervious surface are required to provide stormwater facilities pursuant to the 1992 DOE Stormwater Manual. The size and design would be reviewed as part
of the site plan review and further review at civil plan submittal. An operations and maintenance agreement will be required.
ADA Requirements
The American Disabilities Act required that facilities are ADA accessible. Facility improvements will have to meet current code. Review of these improvements will be determined upon
further review of the civil and architectural plans.
State Environmental Policy Act Process
A SEPA threshold determination will be required before action is taken on the Site Plan Review application. Because of the size of the project, an expanded environmental checklist will
be required initially. The expanded checklist should include the following environmental documents:
Traffic Impact Analysis.
Preliminary Stormwater Plan.
The SEPA threshold determination is appealable to the Hearings Examiner, who would hold an open record hearing on the issue. The Examiner’s decision may be appealed to City Council,
which would conduct a closed record hearing and determine if the Examiner’s decision was contrary to law and supported by substantial evidence.
Site Plan Review Process
A Site Plan Review application as established by Chapter 17.84 YMC is an administrative review process. The minimum application requirements can be found at Section 17.84.060 YMC and
are listed on the application form. A notice of application is mailed to all property owners within 300 feet of the site.
The site plan review committee’s decision on a site plan review application may be appealed to the Hearing Examiner, who would hold an open record hearing on the issue. The Examiner’s
decision can be appealed to the City Council, which would hold a closed record hearing and determine if the decision was supported by substantial evidence or contrary to law. If a SEPA
appeal is filed, the site plan review would be combined with that appeal and the Hearing Examiner would become the decision maker with a recommendation from the SPR Committee. An open
record hearing would be
held by the examiner on the site plan review application, if combined with a SEPA appeal.
A conceptual landscaping plan is required with the application for site plan review. The final landscaping and irrigation plan is required as an element of civil plans, with installation
and approval prior to occupancy of the business.
Land use approval typically contains conditions of approval that the applicant must complete prior to receiving a building permit. Upon satisfactory completion of all conditions of
land use approval, the applicant can submit building plans for approval.
Civil Plan Review Process
Civil Plan review generally takes place after a land use approval. The Yelm Development Guidelines contain standard details for all infrastructure requirements, including parking lot
layout, sewer and water lines, STEP tank design, and stormwater control.
Building Permit Process
Building Plan review, permitting and inspections will be based on Title 15 Yelm Municipal Code, adopting the 2003 IBC, IMC, UPC, IFC and the 2001 Washington State Energy Code. By resolution,
the City of Yelm re-adopted the 1997 UBC, UMC and UPC Fee schedules.
Building Plans may be submitted after Site Plan Review approval. Five(5) sets of plans, one of which may be half scale, two (2) sets of engineering calculations, energy calculations
and specifications will be required. Due to the size of the occupancy, an integrated sprinkler and fire alarm system will be required. These plans may be submitted at a later date
along with any required kitchen suppression systems. All fire related items 5’ outside the building will be subject to civil review along with domestic water, waste, and storm water.
Concurrently with Site Plan Review two sets of building and accessory building elevations must be submitted for review of the building for consistency with the Design Guidelines.
Allow at least 4 to 6 weeks for Building Plan Review and 2 weeks for design guideline review.