Loading...
Proj Rev Date MemoCity of Yelm Community Development Department P.O. Box 479 Yelm, WA 98597 (360) 458-3835 (360) 458-3144 FAX Memorandum To: SPRC From: Roberta Allen, Administrative Assistant Date: April 18, 2002 Re: BLA-02-8312-YL – Project Review Schedule for Kitchen Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please let me know as soon as possible. The following is the tentative review schedule for the project. May 1 – SPRC project review. Department comments/conditions of approval for staff report. May 9 – Letter of Approval completed.