8246reviewscheduleMEMORANDUM
To: SPRC
From: Cathie Carlson
Date: February 2, 2000
Subject: PDD-00-8246-YL -Project review schedule
Attached is the application packet for the above referenced project. The Traffic
Impact Analysis, preliminary grading plan and tree and vegetation preservation plan
were not included in the original packet, but have been requested. They should be
available within the next 7 - 10 days. After you initial review of the information
submitted, if you need additional information from the applicant, please let me know
as soon as possible. The following is the tentative review schedule for Prairie Park
Village.
February 2 -Notice of Application distributed -begin 15 day comment period.
February 16 - In house SPRC review.
February 23 -Staff meeting with project manager, if needed to discuss issues
or additional information required by the City.
February 25 -Department comments/mitigation requirements for
Environmental Review.
February 28 -Environmental Determination issued by Planning Department
March 1 - In house SPRC review.
March 8 - In house SPRC review (if needed.)
March 10 -Department comments/conditions of approval for staff report.
March 20 -Public Hearing
March 22 -City Council review and decision.