8313-Final Punchlist-120302December 3, 2002
Dick Wetzel
Emanuel Lutheran Church
206 3rd St SE
Yelm, Washington 98597
RE: Emanuel Lutheran Church Final Punch list and Project Closeout
City of Yelm Project No. CIV-02-8313-YL
Dear Dick:
Your contractor requested a final punch list to complete the above referenced project. The following numbered items are required to complete and grant final approval for your project.
You are required to submit Final Construction Drawings or “Asbuilts” to the city for approval. These AutoCAD drawings should show the changes that were made during the construction
process. If there were no changes made, resubmit the approved drawings with the asbuilt approval block shown.
A bill of sale is required for the water mains and water meters. See the City of Yelm Development Guidelines for the format.
A water main easement needs to be recorded for the water main and water meters. See the City of Yelm Development Guidelines for the format.
A bill of sale is required for the STEP sewer system. See the City of Yelm Development Guidelines for the format.
A STEP sewer easement needs to be recorded for the sewer system. See the City of Yelm Development Guidelines for the format.
The construction punch list needs to be completed. This list has been forwarded to Brody Stohr by Gary Carlson.
If you have any questions or concerns please call me at (360) 458-8438 or email me at jimgibson@ywave.com.
Respectfully
Community Development Department
James Gibson
Development Review Engineer
Cc: Gary Carlson/Tim Peterson, City of Yelm
Brody Stohr, Shinstine and Assoc.