RE: Revised Final Project Approval for Mill Pond Middle School STEP Connection
City of Yelm Project No. CIV-03-8335-YL
Dear Mr. Birkland:
This letter is to supersede the letter dated March 4, 2003. The connection fees have been amended utilizing the revised calculations submitted by your civil engineer, as requested.
The revised calculations are based on an amended ERU number of 2 connections. At this time you will need to pay the amended civil engineering review fees, water connection fees and
sewer connection fees. The engineering review fees are $1,134.00; the water connection fees are $3,000.00 and the sewer connection fees are $10,250.00. The total amended fee required
to be paid is $14,384.00.
After the required fees have been paid, the mylars will be signed and returned to either JWM and A or Yelm School District to begin construction.
If you have any concerns or questions, please call me at (360) 458-8438 and I will be happy to further assist you.
Respectfully
Community Development Department
Jim Gibson
Development Review Engineer
C: Grant Beck
Tim Peterson
Jon Yanasak