Proj Rev Date MemoCity of Yelm
Community Development Department
P.O. Box 479
Yelm, WA 98597
(360) 458-3835
(360) 458-3144 FAX
Memorandum
To: SPRC
From: Tami Merriman, Planning Technician
Date: April 8, 2004
Re: CUP-04-0043-YL – Project Review Schedule for YCOM Video Project.
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
April 8, 2004 – Notice of Application distributed – begin 15 day comment period.
April 28 & May 5 – SPRC project review. Department comments/conditions of approval for staff report.
May 21, 2004 – Public Hearing Notice to Paper/Mailing/Post site.
May 28, 2004 – Complete Staff report for public hearing.
June 7, 2004 – Public Hearing in front of Hearing Examiner
June 21, 2004 – Hearing Examiner Decision Complete