Date: December 24, 2001
Re: CUP-01-8301-YL – Project Review Schedule for Medic I
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
December 24 – Notice of Application distributed – begin 15 day comment period.
January 9 – SPRC Environmental Review. Department comments/mitigation requirements for Environmental Review.
January 14 – Environmental Determination issued by Planning Department. Begin 14 day comment period followed by 7 day appeal period.
January 30 & February 6 – SPRC project review. Department comments/conditions of approval for staff report.
February 1 – Public Hearing Notice to Paper/Mailing/Post site.
February 4 – Environmental Determination appeal time expired.
February 12 – Complete Staff report for public hearing.
February 19 – Public Hearing
March 13 – City Council Action