propsed changes 4-1-04 001
City Hall Proposed Changes to Contract
Revised April 1, 2004
Phase I Verbally changed and completed, not invoiced
Material Labor Total
Paint old back door $35.00 $90.00 $125.00
Paint restrooms $77.00 390.00 $467.00
New door and jamb $750.00 $750.00
Remove and store shelving $85.00 $850.00
from 117
Repair Outlet box in floor $130.00 $130.00
Total $862.00 $695.00 $1557.00
Phase I Proposed changes Materials and Labor
1) New matching VCT in restrooms -$1788.00
2) Exterior I-box for RPB 386.00
3) CDD Reception elect. & Comm. 682.50
Total-52856.50
Phase 11 Proposed Changes
1) Additional bookcases
Room # Description Cost Estimate
126 Shelving over file cabinets $477.00
122 L shaped bookcase $2016.00
123 20" Shelving over file cabinets See 122
123 12" book case "
109 Work Center (note 5) $1080.00
109 Take arc out of counter (note
109 xv~.ite 2
108 Counter Space (note 3) $1475.00
106 Shelves (note 4) $1389.00
105 Relocate court shelves $ 160.00
Total $7677
2) Restroom Remodel -$4943.00
3) Plumbing wall at old break room 600.00
4) Water filter + access panel in new plumbing wall. 225.00
5) Standardize egg crate light fixtures (24 new) -$4800.00
6) Replace 9 new lights w/egg crates -S ?
7) New 7' doors -$3060.00
8) Electrical Change Order 41240.00
Total -526959.1
Committed Total 7525.5