proposed changes to contract 3-5-04 001
I
City Hall Proposed Changes to Contract
Phase I Verbally changed and completed, not invoiced
1) Paint old back door
2) Paint restrooms
3) All new doors andjambs, except 121B
4) Remove and store shelving from 117
Phase I Verbally changed and not completed, not invoiced
1) Fix floor around outlet box in hallway
Phase I Proposed changes
1) Additional bookcase east of door 126 in Rm.126-
2) CDD Reception Desk
a) Add quad outlet at center
b) Add 2 duplex outlets below desk, spaced evenly
c) Add 4 data and 2 phone jacks at center
3) Exterior J Box for RPB hotbox
4) New matching VCT in restrooms
Phase If Proposed Changes -sr/r r Ir
1) Additional bookcases in 122 (Shelly)
2) Additional work centers in 109, SE comer- Air
3) Additional counter space in 108 - N"'
4) Restroom Remodel
5) Problem Solving
a) Column fix
b) Plumbing wall at old break room
c) Where to put hot water tank. Negotiated with on demand deletion.
Alternated bid (Council Chambers) Proposed Changes
1) Reoriented and build new Council Bench, expand for 7 council and one mayor
seating, el. +14" above ff
2) Add work table and seating for 2 at each side of bench, el. +7" above ff
3) Sheet rock and insulate exterior walls
4) Add acoustical ceiling, minimum of 10'-2" above If
5) Add windows to council doors (fire type, non rated)
Additional Items?
1) Water filter
2)
3)
4)
5)
6)
7)
I j-Lt t