propsed change in contract 3-15-04 001 City Hall Proposed Changes to Contract Revised 3/15/04 Phase I Verbally changed and completed, not invoiced 1) Paint old back door 2) Paint restrooms 3) All new doors andjambs, except 121B 4) Remove and store shelving from 117 Phase I Verbally changed and not completed, not invoiced 1) Fix floor around outlet box in hallway Phase I Proposed changes 1) Additional bookcase east of door 126 in Rm. 126. File cabinet height +6" 2) CDD Reception Desk (Requested Electrical Change Order) a) Add quad outlet at center b) Add 2 duplex outlets below desk, spaced evenly c) Add 4 data and 2 phone jacks at center 3) Exterior J Box for RPB hotbox (Requested Electrical Change Order) 4) New matching VCT in restrooms Phase II Proposed Changes 1) Additional bookcases in 122x'123 See floor plan a) L shaped book case 12" deep shelves, 8' high b) Over file cabinet 20" deep shelves c) Book case 12" deep shelves 21 Room 109 a) Additional work centers at SE corner (note 5) b) Take curve out of reception counter (note 1) c) Not sure on note 2, may already be in contract. 3) Additional counter space in 108 (note 3) 4) Restroom Remodel (see attached change order proposal) 5) Additional shelves in room 106 (note 4) 6) Relocate court shelves to room 105 7) Problem Solving a) Column fix (approved change order) b) Plumbing wall at old break room c) Where to put hot water tank. Negotiated with on demand deletion. 8) Water filter + access panel in new plumbing wall. 5) Standardize egg crate light fixtures throughout the building (Requested Electrical Change Order) Alternated bid (Council Chambers) Proposed Changes (Change Order Request After Chamber Plan Approved)