Re: SPR-04-0022-YL - Ft. Stevens Elementary School, Portable Classroom -Notice of
Final Decision
Dear Mr. Birkland:
The Site Plan Review Committee has considered your application for the above referenced
project and finds that as conditioned below, the proposed project is consistent with the Yelm
Comprehensive Plan and all applicable City policy's and development standards.
Pursuant to Chapter 15.49, Integrated Project Review Process, a project which is subject to
Site Plan Approval is a Type II Permit and can be appealed to the City of Yelm Hearing
Examiner. An appeal must be filed within 14 days of the date of this notice. Site Plan
Approval is valid for 18 months from the date of this letter.
The affected property owners may request a change in property tax valuation from the
Thurston County Tax Assessor's C1ffice.
The project is approved subject to the following conditions of approval:
Transportation
Findin
Yelm is a small compact community most directly affected by two state highways,
which bisect the community. The two state highways are used by local residents for
transportation throughout the City and for access to commercial and residential
areas throughout the community. In lieu of widening existing streets, the City has
elected to create certain alternatives, Y-1, Y-2, and Y-3, which will avoid the need to
significantly widen existing streets, and particularly Yelm Avenue. New
developments do in fact burden the City's central streets, and unless the bypass
alternatives are accomplished, the City would have to require developers to pay the
cost of the internal street widening.
(360) d:i8-383.5
(360) ~ i 8-31 ~14 FAX
mirrn.~~.yelm.ua.u~
r
City plans show, and the City finds, that adequate facilities will be accomplished
better and in a timely fashion by bypass facilities as a substitute for the widening of
existing facilities. As a result, the City finds that the regional plans in fact benefit
projects in all areas of the City, and will accomplish the goal of providing adequate
facilities to City standards within a reasonable time to serve the demands created by
the proposed project.
Findin
The City of Yelm 2001 Comprehensive Transportation Plan Update lists Goals and
Policies relating to transportation impacts. #30, Funding Sources Policy provides
methods for financing transportation projects, and includes a policy that "requires
impact mitigation payments, or seek voluntary contributions #rom developers".
Findin
The City of Yelm Concurrency Management ordinance a{so describes mitigation
measures far impacts to the City's transportation system by requiring the project to
make a contribution to the facilities identified in off-site comprehensive transportation
plan, in the form of a transportation facility charge. The ordinance lists the number of
new pm peak trips generated by an Elementary/Jr. High School to be 0.02 trips per
student. The Transportation Facility Charge is currently $750.00 per new pm peak trip.
Conditions of Approval:
1. The applicant shall mitigate transportation impacts based on the new p.m. peak hour
trips generated by the project. The project is classified as Institutional -
Elernentary/Jr. High School. The Transportation Facility Charge (TFC) shall be
based on 0.02 new peak hour trips per new student, with an average of 60 students
in a portable. The applicant will be responsible for a TFC ofi $900.00, which is
payable at time of building permit.
Parking:
Findin
Yelm Municipal Code Chapter 17.72 -requires one parking stall far each ten students
enrolled.
Conclusion:
The City finds. that existing parking meets the minimum requirements of Chapter 17.72.
Water
Findin
The site is currently connected to the City's Water system.
Conclusion:
The additional buildings will not be connected to the City water system. No further
connections are required.
April 15, 2004 page 2 of 2
Sewer
Findin
The site is not connected to the City sewer system. The City has not approved
additions! sewer capacity or usage. Thurston County is responsible for approval of the
on site septic system.
Conclusion:
The additional buildings will not be connected to the City sewer system.
Conditions of Approval:
1. Applicant shall provide to the City, Thurston County approval for additional student
capacity in regards to the septic system.
Storrnwater:
Findi~~
The proposed structures do not create mare than 5,000 sq. ft. of impervious surface.
Stormwater runoff from these structures will be captured and distributed by gutter
drywells.
Conclusion:
No additional stormwater facilities will be required.
Fire
Findin
-ire protection is provided by Thurston County Fire District #2. As development occurs
there will be additional demands for fire service. The applicant is required to provide
adequate hydrant placement, and/or fire truck access.
Conditions of Approval:
1. The applicant shall submit a fire hydrant and fire truck access plan to the Community
Development Department for review and approval at building permit review.
Landscaping and Setbacks
Findin
Landscaping and screening are necessary to promote safety, to provide screening
between compatible land uses, to safeguard privacy and to protect the aesthetic assets
of the City. Chapter 17.80, Landscaping, requires the applicant to provide on-site
landscaping for all development proposals.
Findin Chapter 17.80, Landscaping states that whenever anon-residential activity is
proposed adjacent to a residential zone or use, a minimum fifteen-foot buffer area of
Type I landscaping shall be provided along the property boundary between the uses.
Findin Chapter 17.48, Open Spacellnstitutional District states that "If adjacent
properties are in any residential district, the side yard minimum setback shall be twenty-
five feet, and rear yard setback shall be a minimum of twenty-five feet.
April 15, 2Q04 Page 3 of 3
Findin
The applicant has provided a conceptual landscape plan that is acceptable to the City.
Conditions of Aparovai:
1. The setback of the portable classrooms shall be twenty-five feet.
2. The landscape buffer between the portable classrooms and the residentially zoned
properties to the South, shall be 25 feet, and landscaped with a Type I buffer.
Other Conditions of Auprovai:
1. Applicant sha{I assure that all access to, in, and around the structures is ADA
compliant.
2. A building permit from City of Yelm Community Development Department is
required.
3. Applicant must provide a lighting plan showing adequate lighting, and any proposed
additional lighting for the site.
If you have any questions or if I can be of further assistance please contact me at {36~)
458-8496.
Sincerely,
~yfZc ~',~ ~~~~ ~i ~CC~~ ~
Tami Merriman
Assistant Planner
cc: Grant Beck, Community Development Director
Jim Gibson, Development Services Engineer
Gary Carlson, Building Official