Req for release of fundsWashington State Department of Community, Trade, and Economic Development
COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM
REQUEST FOR RELEASE OF FUNDS AND CERTIFICATION
(Pursuant to Section 104(g) of Title I of the Housing and
Community Development Act of 1974 as amended.
1.
City of Yelm
2.
00-64020-004
3.
P.O. Box 479, Yelm, WA 98597
4.
January 25, 2002
5. REQUEST FOR RELEASE OF FUNDS. Release of approved grant funds for the following project is requested:
Yelm Community Services: Remodel and addition of 1600 sq. ft. to the Yelm Community Services Childcare Center. Remodel and addition of 2,500 sq. ft. to the Yelm Community Services
Thrift Shop. Remodel and addition of 900 sq. ft. to the Yelm Community Services Food Bank. Remodel of existing buildings, and addition of 7,600 sq. ft. gymnasium.
CERTIFICATION. Withy reference to the above project, I, the undersigned chief administrative official of the applicant certify:
That the applicant has at least seven (7) days prior to submitting this request for release of funds and certification, published and disseminated in the manner prescribed by 24 CFR
58.43, a notice to the public (a copy of which is attached) in accordance with 24 CFR 58.70;
That the applicant has fully carried out its responsibilities for environmental review, decision making and action pertaining to the project named above that the applicant has complied
with the National Environmental Policy Act of 1969; that the applicant has complied with the environmental procedures, permit requirements, and the statutory obligations of the laws
cited in 24 CFR 58.5; and that the applicant has taken into account the environmental criteria, standards, permit requirements, and other obligations applicable to the project under
other related laws; and that the level of environmental clearance carried out by the applicant in connection with this said project did not require the preparation and dissemination
of an environmental impact statement.
That the dates upon which all statutory and regulatory time periods for review, comment, or other response or action in regard to this clearance began and ended as indicated below; that
all such dates which are applicable to this aforesaid clearance are indicated below; and that with the expiration of each of the time periods indicated below, the applicant is in compliance
with the requirements of 24 CFR Part 58;
ITEM
COMMENCE
MO/DAY/YR
EXPIRE
MO/DAY/YR
Notice of Finding of No Significant Impact: Publication
Same: Comment Period
Notice of Intent to Prepare EIS: Publication
Draft EIS: Comment Period
Same: 90-Day Period (NEPA Regulations)
7-Day Notice of Intent to Request Release of Funds: Publication
15-Day CTED Decision Period
Other: