04-0180 Punchlist 051707CITY OF YELM SEWER DEPARTMENT
2e: Punch list Ridgelice School
May 17, 2007
Please note that this list of 8 items is the same Punch list Yhat was submitted in December
of 2006. None, have been completed.
L The breakers that operate our system within the building are not labeled to allow
service personnel to disconnect power.
2. 1 manhole remains to be vacuum tested.
3. Ground water wells (pyzometers) have not been installed.
4. Both ] 10 volt wiring and low voltage wiring (control wires) were installed in the
same conduit. These must be separated in individual conduits.
5. These pumps have now ran continuously for months and will need to be replaced
with new pumps prior to our acceptance.
6. The floats are not operating correctly and must operate according to
specifications.
7. There is a problem with the alternating relay within the pump control panel or it is
not wired correctly
8. Next to the tank riser, both 110 volt and conhol wires aze protruding out of the
conduits and exposed. This is not except able.
Item #4 above appears to have been corrected. However, there is no sign
(asphalt/concrete patches) that another conduit was in fact installed. The contractor
will have to prove to the sewer Department that another conduit was in fact installed.
Yelm SgweroDepartment to havela mtg atoogo lover thesehtemst(This has already
occurred once, but apparently another mtg is needed).