04-0180 CIVIL Misc (2)~~ .. ~. .. Y.. ..
Expanded Features
~~ p~F Unlimited Pages ,
Complete ~ ~,
0
coMM vrvi rY~
360 958 6128
FrX 360 958 6434
9 a i cGATES five n w
ERLING BxRIa.AIm PC Box 5 7 6
F.yCILLTIES fi CAPITAL PROJECTS YELM, WP 98597-0-7 6
DIRECTOR ebi rkland@ycs wedne: edu
August 6, 2007
Mr Grant Beck
Community vefopment Director
Gty of Yelm
PO B 79
Yeim 9859
Ridge a Mid and Yelm High Schools
Punch li dated May 31, 2007 ~ O
r
Ridgelme Jurnor High School '
Water Systems
1 The water valve cover at the Carter Ste once has been replaced with the ccrrect cover
2 The valve box at 5+82 89 is 1o be cleaned this week,
3 The valve box at 7+17 05 has been cleaned
4 The hydrant at 3 00 to be raised, The hydrant nearest the domestic water meter has been raised,
5 The bol rds at 13+12 45 have been installed,
6 The bol shave been msta{led around the air release,
7 A retamm all andl~ omplete at Millpond Fenang will be installed w~fhm the ne ks
8 The Reduc Press ow Assembly has been installed at Mill Pond Eleme
9 The electr al nnec n to backllow assembly hot box will be mst ed in n h e
lectncal ne n to the adjacent portable classroom
S~~S em
1 The STE sewer system electrical breaker has been I le~aitinc
2 The grawty manhole has been vacuum tested (waits lion fr
3 Ground Water wells {pyzometers) hav of been insla ed a are un~
regwnng these dewces We did howeve a letter fr the Crty
2005 rejecting the use of the pyrometers,
4 The electrical installation has be inspe a nd approved by the State Electrical inspector The use of
common raceway for low voltage d I~ne voltage is prohibited by NEC I believe Ihat the system was
installed wdh separate raceway a he rssue of combined use of the raceway was at the electrn;al and
control panels only,
5 The pumps m the TEP ave been replaced (Wailing confirmation from contractor)
6 The floats have be a to operate as specified (waiting confirmation from contractor}
7 The alternatin ump as been wired correctly (waiting confirmation from contactor)
8 Wmng in the ju es next to the nsers has been installed per NEC, (waiting confirmation from
contractor)
YESN .;O'+N1L ~=TY SC NOOKS I3 AN EQUAL CPPOR^JNITY EMF LGYEP A"ID PCL LGAS TIT..E I% REQDIREh1E21TS
...., y ..
Expandetl Features
~/ PbF Unlimited Pages
Complete
General Comments
1 The storm pond and swales are under construction and will be cleaned with the completion of the
construction,
2 The storm pond is part of the football baseball and track construction and vnll be completed w+th the
completron of construction,
3 The landscaping and Penang on the southeast property lines are part of the football baseball and track
construction and will be completed with the completion of construction
4 iJerther a maintenance drive nor sidewalks are part of this contract The work described was part of an
alternate brd which was rejected,
5 It ~s unclear as to what is regwred in the request for cleaning of the planter strip along the southeast
fencing and the homes on 10TH,
6 See number 2 above,
7 The northeast property line is hydro seeded
8 The wooden fence at the entrance to the site from Carter St has been replaced
9 The fence along the Hawks Landing Subdivision is constructed on the distract property and installed
horizontal to the earth The fence is constructed as a visual buffer between the district property and the
homes m Hawks Landing It does not appear as if the gaps below the fence affect the visual buffer
between fhe school and fhe homes Speafically which lots have construction debris remaining on their
property assoaated with the school construction
10 The parking lot stripping will be corrected per the drawings (waning schedule from contractor)
11 The design for improvements to SR 507 has not been approved by NISDOT as of the date of this letter
It is expected that an approval of the improvements will 6e received by the end of August 2G07
Construction advertisements and bidding can not be expected to be completed prior to the end of
September 2007 There remains a possibtl~ty that construction of the improvements wdl not be
completed this calendar year
Documentation
Does the aty have templates to use for the frontage improvement deferrals the dedicabon of sewer anti
water lines, the easements for sewer and water systems and the storm water maintenance agreements If
they are available would you forward them to the d+sinct~
Construcbon as-bwlts are m rewew Is the aty requesting a copy of all or speafic as bu~lts~ Please indicate
which as hu+lts, by d+saphne, you are requesbng
Expanded Features
PbF Unlimited Pages
Complete
Yelm High School
Sevrer System
1 Inlet Baines have been mstalled m tanks A and B, (Wartmg confirmation from the contractor)
2 See#1
3 Float positions have been corrected (waiting confirmation from contractor)
4 Wumg corrections have been completed (waning confirmation from contractor)
5 Service disconnects are lockable (waiting confirmation from contractor)
6 Fusing for tanks A and B has been corrected (waiting confirmation from contractor)
7 Mam tine gate valves have concrete pads and traffic beanng nngs have been mstalled, (waiting
confirmation from contractor)
8 Ciean out cap is marked m parking adjacent to Auto Shop (wading confirmaton from contractor)
9 The tank at the 4D0 budding is to he replaced per city direction The toning wire will be mstalled per the
new tank design
10 See ~ 9, 4VaiUng for revew and approval from City of Yelm of resubmitted design
11 The tank serving buddmgs 300 and 500 rs not m a traffic area Gates have been mstalled to prevent
vehicles from entenng this area
General Comments
1 Landscaping at 93~' ave entrance and north boundary is under review Resolution is expected within
the next two weeks,
2 Relocated portables were reconnected to the water and sewer Connection diagrams will be submitted
within next two weeks
3 The sidewalks have wncated domes
4 The old Yelm High School sign to be removed within next two weeks
5 The storm swale along 5R 510 has been Leaned,
6 The ADA parking stall to be repainted
Documentation
Does the cdy have templates to use for the frontage improvement deferrals, the dedication of sewer and
water lines the easements for sower and water systems and the storm water maintenance agreements If
they are available would you forward them to the district
Regards,
Edmg Birkland
Director of Facilities and Consiruchon
Yelm Community Schools
' Expanded Features
' ~ wDF Un6mrted Pages
Complete
Cc Alan Burke, YCS Supermtondent
Shelly Badger Gty of Yelm, Administrator
Stan Zelinski, Erickson McGovern A8E
Bob Tauscher, JWM&A, Civtl Engineers
Ray Mow Erickson McGovern A&E
City of Yelm
Community Development Department
]05 Yelm Avenue West
P O Box 479
Yelm, WA 98597
October 15, 2007
Erling Birkland, Facilities Director
Yelm Community Schools
PO Box 476
Yelm, WA 98597
RE Ridgeline Jumor High School -Updated Punchlest Items
Yelm High School -Updated Punchlest
Dear Rocky
This letter is updates the status of the remaining punchlest items at Ridgeline Junior
High School and Yelm High School and as a reminder that the Temporary certificates of
occupancy expire at the end of October
Enclosed please find the status of the punchiest items provided the Distract in August of
2006 and updated on September 11, 2007, for both Ridgeline Junior High and Yelm
High School The temporary Certificates of Occupancy issued prior to the start of
school for these projects expire on October 31, 2007 The remaining items need to be
resolved prior to issuance of any further occupancy permits for either project, except as
noted below
Items that have been completed, inspected, and approved by the City are marked as ~,
items that have been deferred are marked as C~1 and items that are incomplete and must
be addressed pnor to October 315 are marked with ^
Ridgeline Jumor High School
Water System
p The water valve box located at the Carter Street entrance has a sewer lid on it,
which needs to be replaced with a water lid
D The valve box for the fire hydrant at station 5+g2 gg needs to be cleaned out
^D The valve box at station 7+17 05 needs to be cleaned out
~ The fire hydrant height, Sta 3+00 00 and next to the domestic water meter,
needs to be verified that it will not be too low after landscaping has been
installed
(360) 958-8938
(360) 958 3199 FAX
u~u~u~ c[ yelm vin us
^D The fire hydrant at station 13+12 45 needs to have bollards installed to protect it
from damage
~ The bollards need to be installed around the air release
^O The air release needs to be raised to final grade of the landscape
17 The existing Mdl Pond School fire hydrant located m back by the play ground
needs to be modified, as it is too tall now that the grading has been completed
and is unusable for fire protection purposes and can not be serviced by the
Public Works Department
O Mill Pond School requires a Reduced Pressure Backflow Assembly
l7 The City recommends that you connect the Reduced Pressure Backflow hot box
to an electrical source
Sewer System
l7 The STEP sewer circuit breakers inside the building are not labeled as required
to allow service personnel to disconnect the power
^ One of the gravity sewer manholes before the step tank remains to be vacuum
tested
t7 Ground water wells (pyzometers) were required as part of the solution to high
ground water and the STEP tank, but have yet to be installed
This requirement was rescinded by the Community Development Department
^D Both 110 volt wiring and low voltage wiring (control wires) were installed m the
same conduit, and must be separated in individual conduits While this appears
to have been corrected, there is no indication (such as asphalt/concrete patches)
that another conduit installed The contractor will have to provide evidence that
another conduit was installed
^O The pumps in the STEP tanks have run continuously shortly after the start of
School and will now have to be replaced prior acceptance by the City
^ The floats are not operating according to specifications
O The alternating relay within the pump control panel is not working correctly or is
not wired correctly
^O Both 110 volt and control wires are protruding out of the conduits and exposed
next to the tank riser
General Comments
~ The storm pond and swales need to have debris removed
To be completed at the time of football field completion
D The slopes of the storm pond need to be hydro-seeded
To be completed at the time of football field completion)
Page 2 of 6
~ The landscaping and fencing is not complete around south end of the ball fields
To be completed at the time of football field completion
^ The maintenance driveway entrance to south ball fields from parking lot is not
complete and the sidewalk at this location is not complete
While the contractor notes that this improvement was part of an alternate bid, the
civil plans approved by the Cfty (see attached copy of page from approved
construction plans) clearly show the sidewalk and driveway approach being part
of the base bid The City approved the plans based on this information
^O The planter strips along the southeast fencing between the School and the
homes 107th loop need to be cleaned
D The area between the property Ime fence and baseball field needs to be
reseeded
^O The area at the north east property line needs to be hydro-seeded
^O A portion of fencing for the storm pond m the Hawks Landing subdivision, located
at the north entrance to the school, needs to be replaced
O Property owners m the Hawks Landing Subdiwsion, located at the north property
line, have noted that there is a gap at the bottom of the fence and the ground and
that there is construction debris graded material on their property from the School
construction
^ The parking lot striping does not match the approved plans and appears to
contain more compact spaces than allowed
While the contractor notes that the existing striping meets City requirements, this
is not the case The civil plans approved by the City show a total of 196 spaces,
with 46 compact stalls A total of 49 (25%) maybe compact stalls per City Code,
while there are at least 68 compact stalls on the site
~ Required improvements to SR 507 must be completed no later than July 31,
2007
Prior to October 31St, 2007, the Distract shall provide copies of WSDOT approved
Plans for Approval and construction plans to the City, along with a schedule
which includes bidding the project, construction, and completion of construction
by July 14, 2007
Documentation
O The deferral agreement for frontage improvements along Mill Road has not been
submitted
~ The dedication of sewer and water Imes and appurtenances has not been
submitted
l7 Easements for sewer and water systems have not been provided
Page 3 of 6
^O The stormwater maintenance agreement needs to be recorded
O Construction as-bunts need to be submitted and approved
Yelm High School
Sewer System
O Inlet baffles must be installed in tanks A and B (32" "down pipe" off the "T" and an
"up pipe" into the nser
~ All risers in tanks A and B need to have a smooth top edge to ensure a good seal
with the riser lid
~ The floats in tanks A and B are not positioned correctly on the float trees
T-~ ~ :~..°.~.t..~.^°....:.".~L°. A. ...~'~_R ::.11 ~.~ th° J b ..... th ~.....It.~-rrc.,d fv is
The Public Works Department has researched your position that this requirement
is not in compliance with the National Electnc Code and has waived the
requirement
O Then service disconnects for tanks A and B handles in tanks A and B must be
lockable and able to accept a City of Yelm lock
^ The service disconnects for tanks A and B need to have one additional fuse
installed to separate the three circuits (2 pump and 1 control circuit)
~ All mainline gate valves in the sewer main lines must have traffic bearing rings
and covers and a concrete pad per the Yelm Development Guidelines
O The clean-out cap in the side sewer for building 300 could not be located (Sta
4+76 00)
~ The valve box containing the service line ball valve and service line for the tank
at building 400 must have toning wire brought to the surface
^ The tank ongmally proposed to be retrofitted for use for building 400 did not pass
the leak test and needs to be replaced
^ The 10,000 gallon tank serving buildings 300 and 500 needs additional bollards
placed to prevent vehicles from parking on the tank or the lid, as it is non-traffic
bearing
The fencing was apparently removed from this area and the STEP lids have
been broken Bollards (not fencing or ecology blocks) need to be installed
around the tank to protect it from traffic The broken lid must be repaired and all
damage repaired
^ A punctured butt connector needs to be replaced in the "J" box in the riser
^ A wire nut was used to "make up" the connections in the "J" box in the nser
Only heat shrink butt connectors are allowed
Page 4 of 6
^ The remote disconnect switch must be dulled to allow placement of a city
padlock when the switch is in the "on" position
M..L h.+c .. nn{ u ric "merl e nu{{~ .. .. {c T}.o~o .. {c no~+.~l }n L.o
The Public Works Department has researched your positron that this requirement
is not rn compliance with the National Electric Code and has waived the
requirement
Note The four comments above apply to the 1500 Gallon STEP Tank at Auto
Shop, which was not installed at the time of the first or second inspections in
August 2006 and May of 2007
General Comments
^D Landscaping is not completed at the 93rd Street entrance, and along the north
property Ime
x^ If the portables have been connected to water and sewer, plans need to be
submitted and inspections completed
O The sidewalks do not meet ADA requirements as they do not have truncated
domes
The sidewalks do NOT have truncated domes as noted by the contractor, they
are stamped in a diamond pattern Truncated domes were required as part of
the civil plans approved by the City (see attached copy from Sheet C2 11 of
approved construction plans and referenced standard specifications)
Because the requirement for truncated domes was placed on the approved civil
plans by the School Districts engineer, the City will require the stamped concrete
to be placed at this time However, the District should be aware that rt changed a
requirement of the civil engineering plans and created a situation that does not
meet the current standards of the Americans with Disabilities Act The Crty
understands that the Distract will take take responsibility for these decisions
O The old Yelm High School sign on Yelm Avenue West (SR 510) must be
removed
^D The stormwater Swale along Yelm Avenue West (SR 510) needs to be cleaned of
debris
^D The required ADA stall has been painted over and does not meet ADA
standards
~ Required frontage improvements along Yelm Avenue West (SR 510) will be
completed through the Drstncts participation in the Killion Road Local
Improvement District
Page 5 of 6
O The nght-of-way required for frontage improvements as part of the LID needs to
be dedicated to the City The City will provide the required deeds and
dedications for the right of way
Documentation
O The dedication of sewer and water lines and appurtenances has not been
submitted
t7 Easements for sewer and water systems have not been provided
~ The stormwater maintenance agreement needs to be recorded
O Construction as-bunts need to be submitted and approved
When all required improvements are complete, please contact Steve Harrington of the
Community Development Department at 458-8423 to schedule a re-inspection
Sincere} ~`i i~
unity Development Department
Shelly Badger, City Administrator
Tim Peterson, Public Works Director
Jon Yanasak, Re-use System Manager
Jim Gibson, Development Review Engineer
Alan Burke, Yelm Community Schools Superintendent
Page 6 of 6
Page 1 of 1
Jtm Gtbson
From Grant Beck
Sent Tuesday October 16, 2007 12 03 PM
To 'rbirkland@ycs wednet edu'
Cc Jim Gibson, Tami Mernman, Steve Harrington, Tim Peterson Kevin Ray, Jon Yanasak
Subject Punchlist
Attachments Punchlist 10 15 07 pdf
Rocky -
Attached as an update on the status of the punchlist items for Ridgelme Middle School and the High School is an
updated list with everything marked of which the Cary is aware at this point If you have any questions about any
of the items give me a call Please also note as indicated in the letter that you should coordinate any final
inspections of outstanding issues through Steve Harrington of Community Development
Grant
5/8/2008
Page 1 of 1
Jtm Gtbson
From Grant Beck
Sent Tuesday November 13, 2007 5 43 PM
To Jim Gibson
Subtect FW Correspondence for School Punchlist
Attachments Ridgeline Middle School Correspondence doc
Talk to me tomorrow
From Steve Harrington
Sent Tuesday, November 13, 2007 4 40 PM
To Grant Beck
Subject Correspondence for School Punchlist
Grant I have attached a copy of the memo containing all correspondence I have had with the Yelm School
District consultants and the contractors or subs I hope this brings you up to speed on what action has been
taken along with the progress of work being done to complete the punchlist items
Thank you,
Steve Harrington
Engmeenng /Civil Inspector
City of Yelm
Office (360) 458-8423 /Field (360) 561-4264
5/8/2008
Rldgelme Middle School Correspondence November 7, 2007
Grant The following are a-mall correspondence for Yelm School Dlstnct
(Rocky), Yelm School Dlstnct Contractors and myself
Correspondence: Yelm School Dlstnct /contractors and
Myself
October 24, 2007 From Steve Harrington
I called Rocky of Yelm School District to ask about the status of punchlist items and when he
planned on having all items complete and call to set up a walk thru He said they are going to
have a walk thru scheduled for October 31, 2007 at 8 00 a m I told him I was not aware of
this walk thru and he will need to call me and schedule it for the various departments within
the aty He gave me a run down of what is left to complete
Ridgehne
Storm pond is under construction
Striping of parking lot (Stalls) He is going to recount the number of stalls
Sewer has been resolved Wood & Son s have completed vac test and floats are done
No offsite drawings approved by WSDOT yet for SR-507
High School
Electrical disconnect is done Per the contractor
2 -Pumps installed are working
Bid awarded to N W Cascade to replace Tank
300-500 Bwlding needs bollards (This area is gated) No parking in this area
Butt connector & wire nuts done on sewer
Disconnect for sewer has been drilled for padlock
Contractor has told him all items will be complete by October 31, 2007 Rocky is going to
notify all contractors, that all work will have to be completed by the 31~' of October 2007 I
informed Rocky that if all work is completed before then, to call me and schedule a walk thru,
so we can look at the items before then and any repairs or fixes can be completed before
Oct 31
Thanks
October 25. 2007 From Rocky
Stan & Ray
I received a call from Steve Harrington at the City of Yelm regarding the status of the
puchlists for Yelm High School and Ridgeline Middle School Steve requested a date that the
City could reinspect the sites Steve also reminded me that the Temporary Occupancy
expires on Oct 31 2007
Groff did have an Electrician on site at YHS today and he indicated that he would be at RMS
this afternoon I can only assume that all of the electrical issues have been completed
Still remaining are two sewer issues at RMS
Please pass this on to the contractors to insure completion not later than Oct 31 2007
Rocky
October 25, 2007 From Gary Gonzales of Groff Electric
Ray/Mike
We are on both sites today replacing disconnects on the Yelm project and punchlist items at
Ridgehne It seams that the Cdy of Yelm has decided that they want 3-pole disconnects in
lieu if the single pole disconnects that they originally asked for Also someone (not Groff) has
drilled out all of the handles of the existing disconnects that were provided Who is the
phantom that is tampering with my egwpment~ I am really starting to get tired of all the B S
that I have taken from this City and I feel that I have gone the extra mile and expense trying
to accommodate them I will talk to Kirk tonight to see where he is regarding their punch list
and their dream list (Which changes daily)and will advise you in the morning or maybe late
tonight
October 25. 2007 Ray Mow of Erickson McGovern PLLC
Mike /Gary,
Please advise on the status of the City's punchlist for YHS
Thank you
Raymond Mow AIA
Associate
Erickson McGovern PLLC
RayCa?EricksonMcGovern com
October 30, 2007 From Rocky
Gary, Steve
I was informed today that all punchlist items remaining at YHS, with the exception of the 400
bwlding tank replacement, are complete and ready for inspection
Thank You
Erling Birkland
November 1, 2007 From Rocky
Gary
The City of Yelm and I reviewed the punchlist at the high school today and found the
following
Several of the butt splices in the tanks A & B and in the tank behind the auto shop have
damage to the insulation It appears as if the crimping tool may have punctured the wnyl
insulation In addition, wire nuts are used in the explosion proof ~-box for all wiring The issue
of not using a butt splice only pertains to the connection of multiple conductors The two wire
connections are required by City Sewer Standards to be connected with a heat shrink butt
splice
As soon as the damaged butt splices are replaced and the wire nuts for the two wire
connections are replaced with butt splices I believe we are complete m regard to the City
sewer electrical punchlist
November 1.2007 From Steve Harrington
Jim Rocky called me first thing this morning I asked him about Ridgeline punchlist He
said according to his contractors, the city has come out and did all the inspections and
everything is done Rocky was not aware of any such inspections, he was never informed of
one I asked Rocky if it would be possible for everyone (City School Dist and Contractors)
to come in and sit down at the table to discuss all issues at the schools and get it all out in the
open and find out what needs to be completed and get an at tentatroe schedule from
everyone when items will be completed Rocky thinks that would be great The following is
Rocky s schedule
Today Afternoon
Mon Morning or Afternoon
Tues Afternoon
Wed Morrnng
tie is on vacation from Wednesday until the 15`"
If there is anyway we could make this afternoon work that would probably be best so it will
give us time to get issues taken care of before he leaves on vacations Maybe you could talk
to Tim this morning when you meet with him then we can schedule something with Rocky, let
me know
Thanks,
November 2, 2007 From Steve Harrington
Rocky
I only had 2 issues from our dept Sewer still has issues Randy Hatch is going to go out to
the middle school and look at what needs to be completed then he will let me know We
could probably meet at the middle school this afternoon
November 2, 2007 From Rocky
Steve
Unfortunately I will be out of the district this afternoon Perhaps we could meet either Monday
or Tues of next week
Rocky
November 2, 2007 From Rocky
Steve,
Do we still want to schedule a meeting at RMS~
Rocky
November 2, 2007 From Steve Harrington
I will look into it
November 2. 2007 From Steve Harrington
Grant Jim asked me to give you more detail on what I had discovered on the parking lot
striping for Ridgeline Middle School When out in the field with Nisha, we measured the
compact stalls (they are correct) along with adtacent stalls and found some odd bail sizes
(see attachment) The compact stalls were put in correctly, per plans There are 20 parking
stalls not put in correctly per plans They are the wrong size I scaled these and compared
them to field measurements If you have any further questions I will explain it to you or show
you on the plans
Thank you
The following is taken from the memo I typed and e-mailed to you
Ridgelme Middle School Walk Thru November 1, 2007
Grant Nisha and I went out to Ridgeline Middle School to check the 2 items from our department
on the punchlist They have not completed these two punchlist items per plans There are
callouts on these items that appear to refer to the wrong drawing sheets for details These two
items that remain to be completed are as follows
1 Maintenance Driveway Entrance to South Ball Fields from Parking Lot is not complete
Explanation Maintenance Road Plan is on sheet C 1 5 not sheet C 2 14
Parking Lot Striping is not per plans, they are not per scale and do not match
Explanation Drawing Plan Sheet C 4 0 calls for a quantity of 20 parking stalls
measunng 9' wide x 20 long These 20 stalls have been stnped correctly They
measure 9' wide x 18' long (not per plan) There is a note referring to striping detail (C
2 10) there is no detail (C 2 10) however there is a stnping detail (4-24) on sheet C 1 5
Sheet C 1 2 gives the layout for the parking lot striping Parking lot stalls are not sized
per plan
November 7, 2007 From Chns Hansen
Stan,
I received a telephone call lust minutes ago from Steve with the City of Yelm lie is has
questions as to the completion of three items at RMS
1 Parking stalls adtacent to the compact parking stalls are not installed per plan
2 Ball field maintenance road not installed per plan
3 Questions concerning wiring with the septic systems
Stan, Rocky is out for the next week and I am not versed on all that is going with protect
completion If you can email Steve back (or call 360 458 3835) maybe we can get some of
the items in question cleared up and completed Please cc Rocky and me for future
reference
Thanks,
Chns
November 13, 2007 From Grant Beck
Steve -
Chris Hanson called to check in with you to see if Stan Z has gotten back to you about your
email regarding Ridgeline his number is 458-6130 or 239-8816
Grant
November 13. 2007 Steve Harrington
I called Chris Hansen of the Yelm School District He asked me if I had heard from Stan of
Erickson McGovern I informed Chris that I had not heard from them He said he would call
them and find out about the status of the punchlist items Chris has also informed me that
the concrete maintenance road was completed today he said the concrete is still green
Chris will be back in touch with me as soon as he gets in touch with Erickson McGovern
and talks with Stan
November 13, 2007 Chris Hanson
Chris called me to inform me that he has talked with Stan of Erickson McGovern Stan had
told Chris that he had spoke to Josh Miller of Jody Miller Construction and was told by Josh
that they are working on the punchlist items
This was updated on November 13 2007
CITY OF YELM SEWER DEPARTMEN f
November 21, 2007
Re Updated Punch list Ridgelme School
The # 1 pump was operating 7 days per week and 24 hours per day and now has
6975 hours of operation This pump and motor must be replaced
All ` 2 wire" splices must be connected with `Heat shrink' Butt Connectors All
multi-wire connections (more than 2 wires) must be connected with water proof
wire nuts
3 Some of the ex~stmg `Heat Shrink' butt connectors are punctured and must be
replaced
4 There are currently 4 `on-otfl floats operating 3 pumps I his ~s not wired
correctly and must be re-wired
FROM YELM SEWFR DEPT
FAX NO 360-458-8166 Nov ~9 2007 02 13PM Pi
FAX TRANSMISSION
CITY OF YELM
P O t30X 4 79 - 931 Nl' ROAD Nl;
~ YELM, VGA 98597
nu 3 GO-~S R-8411
~~~~ FAX 360-45R-H166
10 G ~' 1 'la r-- ~
I Ax#.
Fron) ~fJit,Qy'
DATE f/-~2q-f~ 7
PAGES, ~ , )ncludmg this
Cover sheet
Subject 1=~N,~Z-/~(bG~1aN~ Yr1~DnZF Sit-~vo~--
Cam(?MMENT5 1 ~ ~ o`~ ~-ART'S le- ST 5 , ~' ,
Cj l I ~r I- ~ . ~(~
** it } ou do not receive .th topics o~ anv ~upy is not ieg~ble, please ca11 (3E D) 45`i-841 1
as soon a° possible
r'
City of Yelm
V/ \`~!
v z+r M
Community Development Department
]05 Yelm Avenue West
P O Box 479
Yelm, WA 98597
IIN~,
~~i~~1M
geline Junior
~ary certificates of
Inct m August of
igh and Yelm
the start of
:ems need to be
ro~ect, except as
ire marked as ~,
~mplete and must
-~
O Inlet baffles must be installed in tanks A and B (32" "down pipe" off the "T" and an
"up pipe" into the riser
^D All risers in tanks A and B need to have a smooth top edge to ensure a good seal
with the user lid
~ The floats in tanks A and B are not positioned correctly on the float trees
(360) 458-8438
(360) 458 3Y 14 FAX
www cc yelm ma us
The Public Works Department has researched your posft~on that thfs requirement
~s not ~n compliance with the National Electric Code and has waived the
requirement
^O Then service disconnects for tanks A and B handles in tanks A and B must be
lockable and able to accept a City of Yelm lock
^ The service disconnects for tanks A and B need to have one additional fuse
installed to separate the three circuits (2 pump and 1 cont~;ol circuit) Completed
O All marnhne gate valves in the sewer mare lines mus~~ha've traffic bearing rings
and covers and a concrete pad per the Yelm Development Guidelines
Q The clean-out cap in the side sewer for budding'300 coul~dl{not be located (Sta
4+76 00) II~E~~~~~~li ~r~~~~~~01i
O The valve box containing the service line ball valve and servicerlii for the tank
at budding 400 must have toning wirelbrought to the surface ~i~~4
^ The tank originally proposed to be retrofrttled for usef~for building 400 did not pass
the leak test and needs to be replaced Not~Completed -Expected by end of
December d~~I~IHu.. il~~~~ir.
^ The 10,000 gallon tank se
placed to prevent vehicles
bearing .uiillur~~.
)0 needs additional bollards
o ~,~he hd, as it is non-traffic
The fenc-ng was apparen fly removed afro'm th-s area- and the STEP hds have
been broken~~yBoilards (riortifenang or~ecology blocks) need to be installed
around thettank to protect itiifrom traffics The broken lid must be repaired and all
n~fm ~ ~~Il~
damage repaired„ ,ri}~1y "IIINitur~,..
mg~the meetin Rock sa-al'ttia'tlhe had res onded to Grant w-th an
iil'a'n'd Metter starting that the tank was not gong to have bollards
tilled because traffic could not reach th-s area any longer They gated
fire lane an'd~cars could not reach th-s tank any longer Tim Peterson
I that th-s would be ok+if we had an acknowledgement from the school
r/ct that they would replace any broken Gds m the future
^ A purictu~~ed butt connector needs to be replaced in the "J" box in the riser
Rocky to(alirectythe electrical contractor to replace these
^ A wire nut was)'u§ed to "make up" the connections in the "J" box in the riser
Only heat shrink butt connectors are allowed Th-s was disputed by Rocky
due to the L and I code However he was gong to fix the problem and look
for a type of sp/-ce that would meet both the PW needs and L and l needs
T-m agreed
^ The remote disconnect switch must be drilled to allow placement of a city
padlock when the switch is rn the "on" position School to dell even through
not L and I allowed
Page 2 of 4
r
t
'~
~ e
t
^~' t
o
~ ' ,.,''~ ..,,r
t
d
t
T
~
*
~w
aa
, ar~es
e-s
a.; ,ese-wne+iF
s~ee
a-
e~~
-
e
s~
,
The Public Works Department has researched your positron that this requirement
is not rn compliance with the National Electnc Code and has waived the
requirement
Note The four comments above apply to the 1500 Gallon STEP Tank at Auto
uut'
Shop, which was not installed at the time of the first or second inspections in
August 2006 and May of 2007 ,ill~~l~~ ~~li,
General Comments
^O Landscaping is not completed at the 93rd ~ tp~eet entrance, ancJl aloing the north
property Une ~!~ ~~~~ ~~ , ~4,if~lEli1
D If the portables have been connected (to water and sewer, plans need to be
submitted and inspections completed '~~ ~',~~~II 'lll~ll~fyl41` 1i1~11
O The sidewalks do not meet ADA requirementsIas they do not have truncated
domes ti{II-rli,.. ''{IIII6,.
The sidewalks do NOT have frirnc'ated~domes as`noted by the contractor, they
nn, dhnnl, 'nnp
are stamped in a diamond patterns Truncafedldomes{Iwere required as part of
the civil plans app to fed by the Crfy1(see~~attacfied{!copy from Sheet C2 11 of
approved constru'ctionRplans and referenced standard specifications)
llillih, 'il~lil 'llillU''
Because the'repurrement for truncated domes was placed on the approved ciwl
m ,i+, uv m
plans by the, School Distracts engineer,~~fhe City will require the stamped concrete
to be placed atEthrs timei~iHowever, the IDistnct should be aware that it than ed a
' '46 ~~' II 1{Iirlilllllil'!Vu `tU g
requ(rement of the~c~ y~11 engrneering~plans and created a situahon that does not
meetlthe~current standards of the Americans with DrsabibGes Act The City
dsnrr I'll "a 9i"'
!understands that the L7rstrrct will take take responsibility for these decisions
Illy ';11111e `liiil,.
IThe old Yelm HighlSchool~sign on Yelm Avenue West (SR 510) must be
O Theistbrmwater swale along Yelm Avenue West (SR 510) needs to be cleaned of
debnsil~~l~~~ih Ill~~~~~~1
O The required ADA stall has been painted over and does not meet ADA
standards ,is~~~llli
D Required frontage improvements along Yelm Avenue West (SR 510) will be
completed through the Districts participation in the Kd{ion Road Local
Improvement District
O The right-of-way required for frontage improvements as part of the LID needs to
be dedicated to the City The City will provide the required deeds and
dedications for the right of way
Documentation
Page 3 of 4
O The dedication of sewer and water lines and appurtenances has not been
submitted
C] Easements for sewer and water systems have not been provided
~ The stormwater maintenance agreement needs to be recorded
~ Construction as-budts need to be submitted and approved
When all required improvements are complete, please
Community Development Department at 458-8423 to
Sincerely,
Grant Beck, Director
Community Development Department
c
Shelly Badger, City Administrator
Tim Peterson, Public Works l]irec
Jon Yanasak, Re-use System~iMa
Jim Gibson, Development Re~ie~
Alan Burke, Yelm Community Scf
~~~1~4~;;~~iii
~I~~~~I
(~~~~~~IIIi-I
Harrington of the
inspection
Page 4 of 4
City of Yelm
Community Development Department
105 Yelm Auenue West
P O Box 479
Yelm, WA 98597
September 11, 2007
Yelm Community Schools
Erling Birkland
PO Box 476
Yelm, WA 98597
RE Ridgeline Junior High School -Updated Punchlist Items
Yelm High School -Updated Punchlist
Dear Mr Birkland
Enclosed please find the status of the punchlist items provided the Distract in August of
2006 for both Ridgeline Junior High and Yelm High School The temporary Certificates
of Occupancy issued prior to the start of school for these protects expire on October 31,
2007 The remaining items need to be resolved prior to issuance of any further
occupancy permits for either protect, except as noted below
Items that have been completed, inspected, and approved by the City are marked as O,
items that have been deferred are marked as D and items that are incomplete and must
be addressed prior to October 3151 are marked with ^
Ridgeline Junior High School
Water System
x^ The water valve box located at the Carter Street entrance has a sewer lid on it,
which needs to be replaced with a water lid
~ The valve box for the fire hydrant at station 5+82 89 needs to be cleaned out
^D The valve box at station 7+17 05 needs to be cleaned out
O The fire hydrant height, Sta 3+00 00 and next to the domestic water meter,
needs to be verified that it will not be too low after landscaping has been
installed
~ The fire hydrant at station 13+12 45 needs to have bollards installed to protect it
from damage
^D The bollards need to be installed around the air release
O The air release needs to be raised to final grade of the landscape
(360) 458 8438
(360) 958-3]99 FAX
www c[ yelne wa [w
O The existing Mill Pond School fire hydrant located in back by the play ground
needs to be modified, as it is too tall now that the grading has been completed
and is unusable for fire protection purposes and can not be serviced by the
Public Works Department
O Mill Pond School requires a Reduced Pressure Backflow Assembly
~ The City recommends that you connect the Reduced Pressure Backflow hot box
to an electrical source
Sewer System
^D The STEP sewer circuit breakers inside the building are not labeled as required
to allow service personnel to disconnect the power
^ One of the gravity sewer manholes before the step tank remains to be vacuum
tested
O Ground water wells (pyzometers) were required as part of the solution to high
ground water and the STEP tank, but have yet to be installed
This requirement was rescinded by the Community Development Department
O Both 110 volt wiring and low voltage wiring (control wires) were installed in the
same conduit, and must be separated in individual conduits While this appears
to have been corrected, there is no indication (such as asphalt/concrete patches)
that another conduit installed The contractor will have to provide evidence that
another conduit was installed
D The pumps in the STEP tanks have run continuously shortiy after the start of
School and will now have to be replaced pnor acceptance by the City
^ The floats are not operating according to specifications
~ The alternating relay within the pump control panel is not working correctly or is
not wired correctly
~ Both 110 volt and control wires are protruding out of the conduits and exposed
next to the tank riser
General Comments
Q The storm pond and swales need to have debris removed
To be completed at the time of football field completion
Q The slopes of the storm pond need to be hydro-seeded
To be completed at the time of football field completion)
Q The landscaping and fencing is not complete around south end of the ball fields
To be completed at the time of football field completion
^ The maintenance driveway entrance to south ball fields from parking lot is not
complete and the sidewalks at this location is not complete
Page 2 of 6
While the contractor notes that this improvement was part of an alternate bid, the
civil plans approved by the City (see attached copy of page from approved
construction plans) clearly show the sidewalk and driveway approach being part
of the base bid The City approved the plans based on this information
~ The planter strips along the southeast fencing between the School and the
homes 107th loop need to be cleaned
O The area between the property line fence and baseball field needs to be
reseeded
^D The area at the north east property line needs to be hydro-seeded
t7 A portion of fencing for the storm pond in the Hawks Landing subdivision, located
at the north entrance to the school, needs to be replaced
O Property owners in the Hawks Landing Subdivision, located at the north property
line, have noted that there is a gap at the bottom of the fence and the ground and
chat there is construction debris graded material on their property from the School
construction
^ The parking lot striping does not match the approved plans and appears to
contain more compact spaces than allowed
While the contractor notes that the existing striping meets City requirements, this
is not the case The civil plans approved by the City show a total of 196 spaces,
with 46 compact stalls A total of 49 (25%) maybe compact stalls per City Code,
while there are at least 68 compact stalls on the site
Q Required improvements to SR 507 must be completed no later than July 31,
2007
Prior to October 31S`, 2007, the District shall provide copies of WSDOT approved
Plans for Approval and construction plans to the City, along with a schedule
which includes bidding the project, construction, and completion of construction
by July 14, 2007
Documentation
^ The deferral agreement for frontage improvements along Mill Road has not been
submitted
^ The dedication of sewer and water lines and appurtenances has not been
submitted
^ Easements for sewer and water systems have not been provided
^ The stormwater maintenance agreement needs to be recorded
^ Construction as-bunts need to be submitted and approved
Page 3 of 6
Yelm High School
Sewer System
O Inlet baffles must be installed in tanks A and B (32" "down pipe" off the "T" and an
"up pipe" into the riser
O All risers in tanks A and B need to have a smooth top edge to ensure a good seal
wdh the user hd
O The floats in tanks A and B are not positioned correctly on the float trees
^ The wire connections in tanks A and B within the J-box in the vaults need to be
made up with heat shank connectors and melted completely
t7 Then service disconnects for tanks A and B handles in tanks A and B must be
lockable and able to accept a City of Yelm lock
^ The service disconnects for tanks A and B need to have one additional fuse
installed to separate the three circuits (2 pump and 1 control circuit)
^D All mainline gate valves in the sewer main lines must have traffic bearing rings
and covers and a concrete pad per the Yelm Development Guidelines
O The clean-out cap in the side sewer for bwlding 300 could not be located (Sta
4+76 00)
O The valve box containing the service line ball valve and service line for the tank
at building 400 must have toning wire brought to the surface
^ The tank originally proposed to be retrofitted for use for building 400 did not pass
the leak test and needs to be replaced
^ The 10,000 gallon tank serving buildings 300 and 500 needs additional bollards
placed to prevent vehicles from parking on the tank or the lid, as it is non-traffic
bearing
The fencing was apparently removed from this area and the STEP Inds have
been broken Bollards (not fencing or ecology blocks) need to be installed
around the tank to protect it from traffic The broken lid must be repaired and all
damage repaired
^ A punctured butt connector needs to be replaced in the "J" box in the riser
^ A wire nut was used to "make up" the connections in the °J" box in the riser
Only heat shrink butt connectors are allowed
^ The remote disconnect switch must be dulled to allow placement of a city
padlock when the switch is in the "on" position
^ the explosion proof "J" box used for the pump wires within the pump vault of the
tank, has wire connections "made up" with wire nuts These wire nuts need to be
replaced with heat shank butt connectors
Page 4 016
Note The four comments above apply to the 1500 Gallon STEP Tank at Auto
Shop, which was not installed at the time of the first or second inspections in
August 2006 and May of 2007
General Comments
^ Landscaping is not completed at the 93rd Street entrance, and along the north
property line
A solid fence is required along the entrance of 93rd street, and the approved
landscape plans call for grass or sod along the north property line, between the
. driveway entrance and the soccer field (see memo of 12/2006)
x^ If the portables have been connected to water and sewer, plans need to be
submitted and inspections completed
^ The sidewalks do not meet ADA requirements as they do not have truncated
domes
The sidewalks do NOT have truncated domes as noted by the contractor, they
are stamped in a diamond pattern Truncated domes were required as part of
the civil plans approved by the City (see attached copy from Sheet C2 11 of
approved construction plans and referenced standard specifications)
~ The old Yelm High School sign on Yelm Avenue West (SR 510) must be
removed
O The stormwater swale along Yelm Avenue West (SR 510) needs to be cleaned of
debris
^O The required ADA stall has been painted over and does not meet ADA
standards
^ Required frontage improvements along Yelm Avenue West (SR 510) will be
completed through the Districts participation in the Killion Road Local
Improvement District
^ The right-of-way required for frontage improvements as part of the LID needs to
be dedicated to the City The City will provide the required deeds and
dedications for the right of way
The Distract has been provided a deed to be executed and returned to the
Community Development Department
Documentation
^ The dedication of sewer and water lines and appurtenances has not been
submitted
^ Easements for sewer and water systems have not been provided
^ The stormwater maintenance agreement needs to be recorded
^ Construction as-bunts need to be submitted and approved
Page 5 of 6
When all required improvements are complete, please contact Steve Harnngton of the
Community Development Department at 458-8423 to schedule a re-inspection
nity Development Department
Shelly Badger, City Administrator
Tim Peterson, Public Works Director
Jon Yanasak, Re-use System Manager
Jim Gibson, Development Review Engineer
Alan Burke, Yelm Community Schools Supenntendent
Page 6 of 6
n
JWM&A
Jerome W Morrissette & Associates Inc , P S
RE~ErVED
AU6141007
1700 Cooper Point Road SW #B 2 Olympia WA 98502-1110
(360)352 9456 / FAX (360)352-9990
LETTER OF TRANSMITTAL
TO Communtty Development Department
Ctty of Yelm
PO Box 479
Yelm, WA 98597
Job No 03157
Date August 13, 2007
Attention Mr Jtm Gtbson, PE,
Mr Steve Harnngton
cc Erlmg Btrkland, Yelm Community Schools
SUBJECT Rtdgelme School, STEP Tank Reports
I am sending you attached the following Items to accord with that attached copy of Jtm Gtbson's memo to
Bob Tauscher (dated February 3, 2006)
COPIES DATE DESCRIPTION
4 page 2 of 4 of Floatatton Report
4 Floatatton Report Supporting Calculations
4 Groundwater Report, stgnature page wrth Ed Wiltste's
stgnature across tits PE stamp
If you have any questions or need any additional information, please call me at (360) 352-9456
SIGNED tt~,/' Z/~~GG~ro/"
Doug Lund, P E
Senior Protect Engineer
Cmd / Mumapal / Geotechmcal Engmeenng and Planning
Pz~e 1 of 1
Jim Gibson
From Jim Gibson
Sent Friday, February 03, 2006 9 31 AM
To 'Bob Tauscher'
Cc 'stan','Rocky Birkland' Grant Beck
Subtect Ridgeline -Step Tank Reports
Bob,
I received the requested reports for the installation of the STEP tank at Ridgeline Middle School
However there were some missing portions of the reports
1 The Floatation Report by D_o`_u'g Eklund'was missing page 2 of 4 and all the supporting
calculations
2 The Groundwater Report by Ed Wiltsie was complete however I would ask that he place his
signature across his professional stamp
I know this is being tacky but the way I read the RCW's a professional engineer must sign across the
stamp to make the seal binding If you want I can return the reports so you can add the
requued information I have placed them in the wdl call box but I can mail them back if you
would prefer Thank you for the assistance in resolving this
Jim Gibson P E
qty of Yelm, Development Review Engineer
PO Box 479 YeIm,WA 98597
Ph 360 458 8438 Fx 360 458 3144
/img cr y_eLn wa ns
2/3/2006
Mr Jtm Gibson, PE
January 21, 2005
Page 2 of 4
RE~E~~RD
AU6141007
based on the observed soil conditions that ground water may rise to the mid point of the tank,
elevation 347 4 The Xerxes program is not capable of determining the groundwater level at
which the groundwater would produce a factor of safety of 1 2 It ~s appa~ ent, using the Xerxes
criteria, that there is some level between groundwater at the m~dpomt of the tank and
groundwater at the top of the tank where the factor of safety would be 1 2 We have more
thoroughly analyzed the probable maximum ground water elevation at the STEP tank site and
find that the maximum ground water elevation is 347 Please see the attached letter report and
attachments by Ed Weltsre of our office
We have redesigned the STEP tank location to take advantage of a parking lot island adjacent to
the STEP tank location as shown on the approved plans At this revised location the tank would
have 0 5 feet greater depth of cover than over the previous location while maintaining the tank
inlet invert elevation shown on the approved plans Moreover the cover depth at this revised
location would include the additional weight of a concrete walkway over the top of the tank
This serves to increase the factor of safety for floatation for the STEP tank With the STEP tank
at thrs revised location we have calculated the ground water level at which the tank would have a
factor of safety for floatation at 1 2 to 1 Our calculation follows the Xerxes methodology and in
fact uses much of the calculated forces directly from the Xerxes calculations Our calculation
uses the same unit weights for backfill as the Xerxes calculations Also our calculation uses wet
backfill (lighter umt weight) weight where some of the backfill over the top of the tank would be
dry (heaver umt weight) We find that the 1 2 to 1 factor of safety for floatation would occur at a
ground water level of 351 74, accordrg the calculation as described above This ~s about 4 feet
higher than the maximum groundwater level according to our analysis
We have heard that rt has been suggested that the Xerxes warranty would be void if the STEP
tank is installed without anchorage We queued Xerxes and found out that without anchorage,
the Xerxes warranty would be in effect unless the tank floated If the tank floats for whatever
reason the Xerxes warranty would not be m effect We find that this ~s m conformance with
your letter to us dated December 16 2005
In your letter to us we noted that you state that rt is not feasible to use a piezometer to co-
ordinate maintenance of the tank to avoid the high ground water season We are only aware of
one maintenance operation that would cause the factor of safety of floatation to be less than 1 2
to one, that would be if the ground water level were ever to reach elevation 351 2 during the high
ground water season and the tank were to be pumped empty So long as the ground water level
rs below 351 7 that tank could be pumped empty at any time and the factor of safety for
floatation would be greater than 1 2 to I One might try to pump the tank empty for one of
several reasons
RECEIVED
AUG 14 2001
Calculate Ground Water Elevation Required to Produce 1 2 to 1 Factor of Safety for
Floatation at the 50,000 STEP tank at Ridgehne Junior High School
Since the Xerxes program is not able to calculate the ground water level at which the
factor of safety falls to 1 2 to 1, a calculation needs to be made to estimate the level This
calculation should be conservative, that it to say it should error of the side of showing a
lower groundwater level than on showing a higher level fora 1 2 factor of safety To
improve the factor of safety, the calculation accounts for locating the tank under an island
m the parking lotto increase the cover over the top of the tank by 0 5 feet to a total cover
of 4 2 feet The 4 2 feet of cover includes a 4 inch thick concrete slab over the tank
Xerxes noted that their method of calculating the factor of safety for tank floatation is
based on the method outlined m the Petroleum Equipment Institute Recommended
Practice 100 (PEI/RP 100) This calculation is made m accordance with the
recommended practice fisted m PEI/RP 100 and uses the unit weights fisted m the Xerxes
calculations and uses the backfill surface area same area above the tank as does the
Xerxes calculation The calculation shows that the 1 2 factor of safety for floatation
would at a ground water level below the top of the tank Thus some amount of the
backfill below the top of the tank would be dry To help keep the calculation
conservative, the unit weight of the backfill below the top of the tank is taken as though
the backfill ~s wet Thrs calculation uses the Xerxes Dipstick Calibration Chart for this
tank to calculate the tank displacement volume at the 1 2 factor of safety ground water
level A correction factor is used with the Dipstick Chart volumes to make the displaced
volume of the tank meet or exceed the value fisted m the Xerxes floatation calculations
The calculation shows that the 1 2 factor of safety would occur at a groundwater
elevation of 351 71 feet
Step One Determine the werght of the backfill above the tank
Use the weight of 408,624 12 lb from the Xerxes calculation for
groundwater level at the top of the tank with 3 7 feet of backfill
See Xerxes calculation sheet for "Non-Anchored Water at Tank
Top" dated 12/16/05
alculate the weight of the 4" concrete slab over the top of the tank Per
erxes the allowable size of the slab is 70 08 feet by 14 feet Use 150
lb/ft3 (per Xerxes) to calculate the weight of the slab
`~~,1 70 08' x 14' x 4"/12" per foot x 150 lb/ft3 = 49,0561b
--'7 See Xerxes calculation sheet for "Non-Anchored Water at Tank
__~~,,ff Top" dated 12/22/05
Calculate the weight of the 2" of backfill under the concrete slab Use 100
lb /ft3 (per Xerxes) for dry backfill
70 08' x 14' x 2"/12" per foot x 100 Ib/ft3 = 16,352 lb
Add the weight of the 50,000 gallon tank = 18,300 lb
Sheet 1 of 2
MINNEAPO IS, MN 55431 1288 tNww K 9525 88 7-1 89 0
CORPORATION
Dipstick Calibration Chart for 50,000 Gallon - 12' Diameter SW Tank
DIPSTICK
READING
GALLONS
'`~`~~~
DIPSTICK
READING ~`4°'`~„'
` ~.;~_~
~'GALLONS~,
DIPSTICK
READING nn`~"`,Y3~ ~'',
GALLONS s,„7 DIPSTICK
READING
~Y~
~k~~'YD OfPSTICK
GALLONSS~,^,g1 READING ~.'~;'~ t
»
~°,GALLONS ~,~
p ^«'{470x'-x'7s~'P 13 3/4' ' ;»2634~i'k ° 27 1/2 ~' 7194 i"~%„" 47 1/4' .~~°y~p1,12783_~°~,,,~ 55 ;~r~18974Tk,°,~
1/4 ~,~'..15'~^,°~ 14 ~,~2704_~ ~x 273/4 r'7288~°'r' 471/2' ,'j*12692 `,~°a-,: 551/4 ;~"19090w„ry
1/2 ~'~29 14 1/4 P~'a2775ki= 28" `"i-~=-;7362~Yj~,~i 41 3/4 13000 ~ 55 1/2 ~=z,,19206j'~~,`»'
3/4 ~?'T'46.e'~t~ 141/2" .ir`~t2846A,'~,5~~ 281/4 ~'*`,747Z$.~¢5~, 42' ~"~13109,,,'E;'I,", 553/4' ~T(i~19322~x
1 ;;',~r'~ '66~`~~~ 74 3/4 ;,;~. ~2916~ _- 28 1/2' ~k„Tx7572~~~ 421/4" ~13278,~ 56 ~TM~~19439 ,'~~
11/4' ~~°'.`x~88~,am~ 15 ,+~$~2990s~n'n 283/4 `,{L"~g7667~.~.'"~ 421/2 ~.~?13327~°.~s~ 561/4' '~, s19555„~~_
11/2 112 ~~ rt 151/4 ~3f~~3063'Cgr.,,~* 29 -°F X7763+r„~; 423/4 ~13436~,t°'~~ 561/2' y~~196724 `,
13/4 '°138T[.^+s.
~c~ \ 151/2' ,,»3196_
µ 291/4 '~x7859T
F~~ 43 "13545 f,
-dsY ~ 563/4 ~=+,-19788 t`
N ~ _Lw ~
2 ~~, X166 rs#~'il 153/4 '~;~3210""' 291/2 k'r;7955x,,,~ 431/4 ~13_655_"'`x 57 2~519905r `
21/4 p~,~195~„~',; 16 ~w,~,~3285a'`„ 293/4' ~h '°8052~~;,; 431/2' y,7£=J 37,86,x.,"-. 571/4 „20021
2 1/2' m.°~~.226'y`r .I' 16 1/4 "i',>-3360 30 'S s' 8749 _° K 43 3/4' ~.`G~13875;'~ ~ 57 1/2' Y20138" ' ~i
2 3/4 ""~"'y7258~'~-g 16 1/2 ~,~r3435 „,E'h, 30 1/4 p'~`3~"'8246'~t ~" 44 ~13985,~ '~ 57 3/4' ~20255y,''~
3 P.~t292~.,~ 76 3/4 '„~y3511 3;,` 30 7/2 R+~~8343Ti+~1 44 1/4 x,',14095'3"^,,; 58' 20372`....rr
3 1/4" a'.y'~~`327i~~TM~='" 17 ~}~ 3588 ~,' 30 3/4' =`8441 zr~-, 44 7/2 x14205 ;.~ 58 1/4 ~.~20489 ~i
31/2 r ~"363,*~ ~ 171/4 p '3665 31" I,a~~8539',~ 443/4" a~+,T~14318=_~», 58-1 /2 ,~~20806i.~~'
33/4' ~°'~E=4007 '~1:x 177/2" `=X3742"+ 317/4 ,~`~,T,S8637,+~=; 45' ^y~g=-14_427d,~;" 58-3/4 .=~~20723d ~'
4 ~'~~°439~,4s~`~ 173/4 ;'~.`~!3820„~- 311/2 ~~8736~ 451/4" ~1,4538~~+g 59 20840a°~
41/4 %~~~'479 i'ya+r~' 18 ~M"S(~3899!,'~.i 313/4 :c,~#a8835 ~q" 451!2 74649*~.s, 591/4' ~t„°20958',~~
41/2'
43/4' i~;~.9520~r {.L`-
~-562'N~`,a3 181/4
767/2 ~,~3978~~a^
''"~Z405~,7~{t~ 32
321/4 1,~~,~,8934~,
;r'9034~rw~ 453/4
48' ~"~$714780
~~14672_ti~r~"" 591/2'
59-3/4 ~a21075~r i
y21792~`r
5 ~605'~[,i';~ 163/4' ~,4'~.~4137,,,'~`~- 321/2" ~~;T9134F 461/4 `+`~,"_14983aq, 60 ~~~21310 _
51/4 ~~6>~` ~~ 19 ~`~4217,~; 323/4 x„~9234~R' 461/2 ,15095 60-i /4 ',~2742T1~,,"-~
' S 1/2' ~x694"•r~x
~ _ 19 1/4 ~"4298~ ~ 33 »~-'~',~9334~~ 48 3/4" i5207~4"~"~ 60-1/2 ¢t'~p12t545~` u
53/4' ~740~zi
` 19 V2 ~~,i379;~43 331/4 '~'¢~y`'9435.,3 47" '_s15319~~'~ 60-3/4 ~'w2)662~t ,.
6 ~" 787 19 3/4' .4461 ~p 33 1!2 9535r„'~-" 47 1/4' sF 15431 61 27780 ,i"
61/4 7,835 20' ~~ry4543,, 333/4 ,~F.~~9637~~'"~'x' 471/2 ~15544x~~~,?i 61-i/4 X3321898',
61/2 ,`,.z*'~,,°x.884"'." 207/4' ,~T Z,t4626-^'~"^ 34 ~>~9738~'~ 473/4 ~~5656~..s~'j 61-t/2 220,75~a~Q
63/4 r~.~,934''"~ 207/2' ~"~-~4709~.~ 341/4 '~; ~9840~" 48' 157469i-~€f 613/4 ,~22133~X„x:p
T ~$,~985~" 203/4" y~479,~ 341/2 9942~~~ 481/4 15882~~
~~ 62 22251r+~~7,~
71/4 ~~~1036py 21 .~,~4676~ 343/4' ~ ~004~4~ 481!2 g°~15995#,T~#a 62-7/4 '~22369,1;'y~
71/2 410~89~~ 21 1/4' 14960~',~., 35 4y~. ~101~4,6r~, 483/4 ~ a1~108` 62-1/2 ~2248a -';~iy,
73/4 F~`~-~1,.1.z4-..a~~ 211/2 504,5~5~.;.rt 351/4 ~s 10?49~,'+~"+~~ 49 16221~t5~;~ 623/4 '~°22605~: >~
g i~°'1196 21 3/4 L .a.5730~,`a=~ 351/2 ra~~10352z tea" 91/4 16334' 63 27235 '!
8 i/4' ~ ,5x„12~Sf~~ 22 a ,'",52767~j°µn 35 3/4' ~10455'~TZ1~7s 49 1/2 1~6446~ 63 1/4 22841~Gy,
6 1 /2 `x ~~~,306~~~ 22 1 /4 S"~x„~,5302 ~Y -~ 36 ~~ y 10,g„559~m 49 3/4 ~~,.~76561!~x T ;x 63 112 ^~22959~~ ;,
B 3/4 fw; r,~1362a~ez.~ 22 i/2 ~;~^em5388*~.~; s 36 t/4 ~ ~ 1066~:a~,~`A 50 rci66~55, 63 3/4 7~7s,2307,7~<ry~ -
9 - s~142~a~~,~ 223/4' ~»w'°5475 r" 361/2 $:'a xr10766_~ 501/4" r~~1~6789.:,~_^.~, 64 .231954^"
91/4 1477,a 23 _5562 t ~
r 363/4 ~~: 10870;.,"2~a 501/2 ~,~,'.~16903~~iTS 641/4 ~a`~~23313 '
91/2' ,1536 yr, 231/4' '5649 ~' 37 ».~s~10975-;, 503!4 ~1,".1,~70175^t ~y 641/2 r~23431
9374 "»~595kr ~
~~ 231/2 yu a`~5737s~~+ 37114 o~L ai1D79k ;~ 1 _..~,~1~73~,f 643/4 ¢~23~549n ^
10
hey
1655=~3
'
i' ~`P`~ ~-^.. v'- 233/4 x~~.. 5826,{¢`.'
9.~.~ice-ID 4ii, 371/2
e
i 11184'+x
]"`[' PS. 511/4 ~gi~17~246 "'N*
y
- 5 f~ 65
a}
z723667zf
~uu .i 2~+
101/4 S'~17169" 24 ~- r 59~14_a'i' 373/4 ,_ sit28_9„~ 1 1/2 P~:i17360 i 65-1 /4 ~}'~i23786 ~~
101/2
~C
5'.a ~mM~.7W'r7e 241 ~x;:T6003at!;>:~_
Yr-mar. m~cxx ~ 38 s,~ ~11395'~~"
~ a _rwa. why 4 ~,~~17475i~.r
-o- ~r.~ 65 € 23904.E=7
~~
103A ~:*,~~?839q~ 24 <609~"`~~ v~ ii500 yw~ ~za~i~5~x ~2~, a~:9
tt ~~ =.?~02~~~„ ~.~s~~ ~°;~,~°6+~~` ~ =ttoar ~; -2a~aD r~l
Ae*'[Pr~
d'h~~S SC .eve }im'~d4W
N
~' i
dfe~3'}Y"iNyG~3 f^i X64`-4~n'~Fi4 ~i
c~ ~
ti ~".~"1'h
j~y+
C
~ ~~/. ~Wi.aA 95'~'V* ~
[
~FiS.~ ~ h>~ ~.~. t
N'~~ i~"'.+dF=Hrs~ 5
k"Tn.._......~~a° q~i
'~A~.k ~v~v'~
12 ='.^p21601 25 3/4 ~~6i~5M: 39 1/2 ~20~1,~~ 3 1/ ~gy~16165~~. 67 ~.~e24614~~, x
12 1/4' ~2~2y6,~; 26 'g ~x6637~T ~ y 39 3/4 ~,~12138 ;yT; ' 3 7 16 80 67 /4 ,ate 24732
~
121/2 °~, 29ssy~h, ~~6729x»*?' Mg 12„245,~fs ,'
~ ~.~~~1-,83_95~~s +;24850~
123]4 ,x,235 7r+ _
- 1 Fa~,L r662i"y
a 0 ,3C~12352~ .~=y18 17~ ~ 7 4 '~ti249 9i
13 r sr22427~" 263/4 ~,° 6914 401/2 u 12460 541/4 '~r n18827G,T_"~ 68 -^25087
131/4 "'y'2495, _ 27 ,~, a, 7007 403/4 ~-r~12568, 541/2 ~ 51~8742y, 681/4 ~~25205 5^
13 1/2 2564 27 t 4 7700, 41 12675 4 3/4 ri ,18858 ~ 68 t/2 ,,.; 25324
CAUTION Do not use the Callbratlon Chart without reviewing Xerxes® Installation Manual and Operating Gwdeiines, and Kerzes® applicahle
Limded Warranty, copies of which are m the literature packet delivered to the sde, nr available at www xerxescorp com
IQ)SO/LO OSOSZIx :?r-ESb'B4Y ~* ^~FOZObb_~' y'°'89E9E~==n t~~£LOZ£"~3
>~~08884~i~ bl ~""6Z6£ti ~~'« L ~~O.l9Z8En ~. 4E [fi9lE~Z'~ Z Z
LZ£84.a8a S t i'~:tH£BEbu~'.,~sS~ b/£ Ol ~ ."1b91BE~ Z L 9 `'~rs~Z9G'lEttb~w: b L Z9
n ~
C -+rE9Z84~~ -L°'z=~.y C :i
~ LbL£b_ R nr x~
4s3L708E'-- "y`9
99l£LFe'+h3°
-
.~'881Bb= ~ SS9£b ~-" '"'~Ob6LE `TM-' _
'~09S 1E=r'
+3~'/4~£E L84~~~ ~'49S£b_-~ ' 6E8LE ` n.i£9l£ -!^
~~~L908bj r~~, • .LL6£4~ A z b E SZLLE L S 8l£LE .;`' 8
`sF~OOO84 L) BLEEP L 9C ~ ZOZiI ~
''",-"s~ =~" 'eb~= `s ` ~=4 -~"sea ~"~
~~,, yy~
r+i LJ' biC "~
eo ~~ ~~ ,.~ ~ .
} ° ~~i3
i~~.0 ~ ~ ~'~
-•'.L6LLb`"-~' •` 660Eb'~- z- '~'Z ZLE:'-+' b BOE
i~9ZL 4Sc
'
t~ ~ ~SOOE4~~~ ~~'b9l[£ l~ L b ~~L£LOE.f`+"~.
',E~3+t£6ZOS~l`s
~.98ZOS~s"-el
,. ,~9LZOSr~".F'is
~+~E9ZOS~l~
'~~96ZOSb..~'
~"a~9ZZOS
G+~'rbOZO'S`~ki:
1"i~08L05
_= 45 LOS !~.
'LZ 1053.
.~'aLfi00SC
~.~'L900S'~`~;
5b£OOS~~
l l
b L 9 l
8El
b £ SEL
Z/L S£l
b/L S£L
SEl
b b L
t bEl
b/L bEI
bEl
b/E EEl
Z/L £EL rv
{
~Y~B 9L6~'~II~'~
~,1'168SL4
fi ~'l8LSL9+~"
'§~ID'iLVDtti ~~
'~SL6L4f.
`~I~ZOEL~ ~'s~
~c 0£ZLb~
i-~i~9S l"Lb,~
~~Z80Gq`f~
+i'~800L4w'
~.^~~EE694t~,~'~
""s xm~LS896k1i~'
L9L94 T1
Ycs~d SOL94°.~
4 l l
Z l
4/E lZl
Z/L l l
4/L l l
l l
,b/E OZL
Z/
4/L 0 l
„OZL
b/E fill
,Z/t fill
b/L fill FAG ~'OL6Z4
9lBZb '?
~`LZLZ9~v
~~"SZ9Zb=,
,~e3liN0£SZb~
~ bEbZ4
L£EZb~*''~
a.u~lbZZbw~n~
s~461d4
--*~s+~L40ZY;#~
4nra'~646Lb~'SI
'~`~Z99 Lb~
~ESLIb~
F'~a~SS9lbsr~.~
B
b/E LOl
Z/L LOl
b l LOl
LOl
b1E 90l
Z/L 8pl
b 1 90l
9 l
b/£SOl
„Z/} SOl
9/L 90L
SOl ~v
ymy_p~
'^~SLOLEy~~^x`
~~9969E~
SB9E
r1~~7L9E
~~~BE99E~
~^~,":9ZS9E~-.~,
9L49£
f'k,90E9E~
8819E
09EC~
~a'`9LfiSE"~'~
99BSE~~
'`S9LS£
P`'bb99£~'S~
Z/l
b/L E
E
6/E Z6
Zll Z
,b/l Z6
Z
b/£ L
„Z/l L6
b/L l6
l
,b/£O6 °~'~*'LZ9OE4 Exit'
rs40S0£'~
"y88E0E' ~'$
~°'LLZO£~~r
#n;'R4910£xi`",tz
~LEOOE~
66Z'~h'~
~6096Z
P~'i°=L896Z~k~
~6956Z€ie
ZS46Z
'•~5££6Z
sx9LZ6Z~~
~1~0661Z
6L
6L
6L
b E 8L
Z/l BL
b l 9L
8L
LL
Z t LL
„b/LLL
LL
,blE 9L
Z/l 9L
10005"' b/L EEL s.8Z994yU~*~ ,fill t~+~9SS l4r'~*i'~ b/E bOl ~'+~~Z£SSEl c*ad ,Z/L 06 t~ #eE868Zr_`5~~; ,b/l 9L
9966b'L EEl ~OSS94~~~,~ 4/E 9ll ~~LS4 Lb~ti Z/l bOl ~-~LZbSE~;=~ b/l O6 "~S988ZVE#-~ 9L
y'i;;,~D£66b~#~~ b/E ZEl .y~}KZLb9V J'~ Z/t BU -~`rfr8SEl4~,~ b/L bOl a60ESE~'.,,,=~`-T O6 L~94L8Z' b/E SL
;1~4Z6884,ti~~
'£5864'n r~i Z/L Z£L
,b/l ZEl 46£94"..'
~SlE9--b~~ b/L BU
„8ll 6SZ4`b~c~~'
=~i~6Slflti,.„;?'" bOl
b/£ £Ol t`r~4E 'L6 LS£t„
'„~.880SE~i'~ b/£ 68
,Z/L 68 ,~0698Z1~
ELSBZ• t~ Z/L SL
,b/L SL
~'jb1964~~~" Z£t 9EZ9bF~ „b/E Lll :.~"1"` 6SOlb ~ Z/L EOL =~£Lfib'E'~~-= „b/L 68 ~S6EBZ SL
~~ELL6b~ b/E LEl S",1.k~9SL9~r~~ Z/t LLL ~ t~„65604.$ b/l EOL ~~L99bE'~d~-2 68 #i ~LLZBZ~.,~ bl£ bL
~""~L6L64,~,".y' Z/L LEl ~`'~; SL09b, ~~, b/l Lll v^`~BS906 ~#` £Ol ~~-6tiLhE~~ b/£ 88 ~~`f65 L9Z<` Z/L 4L
=_`~3B8964~ ~ b!l lEl '~5*S66Str`5sy';q Lll ~`'LSLOb;_'~, ,b!£ ZOL =;'~9£84E~;'-°', Z/l 98 ~4 Z408Z`.~ ~ b!l bL
,a-irEb966 ~e , LEL `t'L`,£L6Sb~2: 4/E 9ll ~»'9S90b-"';,,~,.~- Z/l ZOl :'ak'bZSbE~ ;;',: b/t BB ~.`~*,bZ6LZ.Yll",', ,bL
86S66yr', 4/E OEl ~~~ZEBSb'} Z/l 9tl ~"'"bSSOb~ ,b/l ZOL " :~LLbb'E~~' 8B ~908LZ~,~F,Ti" ,blE EL
_+'-",~;Z9S64 ~,
~ Z/l OEl -3,•-6tiLSb~": „b/l 9LL --a.~ESb04 y"~; ZOL ~B6ZbE~~`'~ b/E L8 j~..~6989LZ ~=4 Z/l £L
-.~SOS6Y
My,. ,b/l OEl =.°-sL99Sb ~~,'-. 9lL ',$''1SE04"'-~ b/£ lOl ..k;,SB LbE„ -~ Z/L L9 ~'wOLSLZ.['~~. bll EL
~~~LSb6b~7{,~ OEl ';t'SttrbBSSb`^"Ey`?,F b/E 9ll -"~',6bZOb~'`sen Z/L LOl ~~LOb£-~ 4/l L8 ':'~,ZSVLZ`~ ~ EL
~~~.390b6bi,7 i b/E 6Zl ysy~00SS4 n Z/l Sll 'yy'941Ob,~ „b/L LOL 'a ~8S6EE'`L~„~ L8 r ~b£ELZ~~~1; ,b/E ZC
4'`~9SE6b~'~ Z/L 6Zl r;`LlbSb~..~ „b/l Sll ~6b00b3 LOL .~~S48EE~ ,b/£ 9B dik~9 LZLZ~~ Z/t ZL
6'°~"BOE6b~ b/L BZl ~"s=~"'~Z££Sb ~,~ SLL ~~L486E` b/£ OOl g~~;~IELEE ~i2~8` „Z/l 98 ,~j~~860LZ e~„~L~ ,bll ZL
°9SZ6b'?~`i] 6Zl 'S1`~':BbZSti ~'l' 4/E bll '~~~LE86E~ „Z/L OOL ~Ll9EE~ b/L 98 ;,"0869Zn~k#'; ZL
;'~. 40Z64eE;;~ b/E 8Zl ~d+Z91Sti~.4" „Z/L bll ~~;,bEL6£$s",? b/l OOl b05£E 98 ~i= 1989Z~,- ,blE lL
N ~lS Lfitir ~• ,Z/L 8Zl r~~~LLOSb~,yf „b/L 4LL .~;~,oesse~n 001 ~06££E~~~ ,b/E SB i £YL9Z}r"~''~ Z/l lL
~~,'L6064~4 ~~, b/L BZI ~y, X16644 ~a',,~',~'_ „bll ;~~9ZS6E=~; 4/£66 ~tt°„y9LZEEf, Z/l S8 ~~SZ99Z~ ,4/L lL
~4'ZbOfibs ~ ~BZI ',~ SO6b4x ,bfE £ll z;,c ZZ46£ Zil 66 ~,;rl9l£E° 4/l S9 ~L059Z~ lL
x:,98684 b/E LZl a,b~,;8L84b~r Z/l ElL s~~9lE6E ,bll 66 ~?"L40£E ,S9 ~`,~69£9ZI;,,s,~rt"~, b/E OL
>,1. y0E686.~~ Z/L LZL ~~" eL£Lbb,~gy'y~ b/l ELL ",6LZ6E'1 „66 £Z£6ZE~ „b/£ 48 uOLZ9Z~ ,Z/l OL
5~,.,(EL884.,`~%y „b/L LZl '+,`. ~E494'bl:~ „£lL ="~_BOl6E~ } b/E 86 ~"~.3'j949ZE^'°k Z!L b8 ~ZSl9Z,~'~, b!l OC
~~S1984~ ;g3 LZL rs~ SSSbb` 4/£ Zll '=~LEOO6Ei~3~' „Z/l B6 °EOGZE ~~ ,b/t 48 T rb£09Z,!ti a~',_- ,OL
`,jC LSLBb ,b/E 9Zl rf,•,L9b44f ,~ Z/L Zll ~., 8688E *~'' b/L 86 „~BBSZE„c, 48 J eSl6SZ b :, „b/£ 69
~,~L69'96;.`~ Z/L 9Zl '~,`,~`,,BL£bb~~~ ,b/l Zll ~~. Z6LBE~ „. ,96 `„s£LbZ£,5 ~ 4/£ E9 ",;,z.L6LSZai6 Z/l 69
.'~yL£994~ g b/L 9ZL "'~69Z44"c~ Zll ~.h LB99£'~'•--xc, 4/£ L6 -~° BS£ZE>~.~ Z/t E9 '1'~6L95Z~;~`, b/l 69
7~°~"~LLSBb,J 9ZL ;~.~"OOZbb„,p~°r b/E LLL -~+---`"LBSBE~-~, Z/L L6 },~";~84ZZE; ~~ 4/l E8 "..~n%~.,09SSZ,,,~~ fig
""i'9L994 •$~(. ,$ b/E SZI ~_''`lk'O L'ltib Z/t 111 $'"bL4BE~ „b/L L6 a°9ZLZ£%~ £9 '~„'~b4SZ'."'3~ 4/£89
~SNOIItl'Jti},},
~r~x'°~t[ri 'JNIOtl3N
MOI1Sd10 ''~SNO~;l~li~tl0°'
[,y~q~~#, ONIOtl3H
NOI1Sd10 °aENOllV9iY-r
;~,}~"-~F..~~ 9NIOtl3N
HOI1Sd10 „SNOIItl'J~
='s„w~"„„~r.~~~i` `JNIOtl3tl
NJI1Sd10 „i I+SNOIItl"J.y"
a s•~';3w, ~- ONI073B
1IOLLSdIO
~lu~l MS lalawela ,Z~ - uoII~J 000`0510} uey~ uol~elglle~ >lolisdla NOllt/aOdFJOO S3Xa3X
XERXES® NON-ANCHORED CITY OF YELM
RIDGELIKE MIDDLE SCH OOL
WATER AT TANK TOP
IYANCY CALCULATION
JWL 12/16/05
TANK DATA INSTALLATION
NOM CAP (GAL) 50000 TOTAL COVER INCLUDING SOIL & 3 70
TYPE (SW=I,DWI=2,DWII=3 1 TOP SLAB (FT)
DRY=1, WET=2 1 TOP SLAB THICKNESS (IN 0 00
TANK DIA (FT) 12 TOP SLAB LENGTH (FT) 0 00
+++r*r**+r rrrrr****r**r rrrrrar r+*+*r****rrrrr**rr+ TOP SLAB WIDTH (FT) 0 00
PROD STORED (GAL) 0 k OF 30" DIAMETER RISERS 2
SPEC GRAV USED ] 00 k OF 24' DIAMETER RISERS 3
BRINE FILL GAL 0
SAFETY FACTOR
DOWNFORCEfl1PFORCE= 0.93 :1
TOTAL WEIGHTS
DOWN FORCES
CONCRETE WEIGHT 0 00 LBS
BACKFILL WEIGH7 408624 12 LBS
TANK WEIGHT 1830000 LBS
PRODUCT WEIGHT 0 00 LBS
TOTAL DOWN FORCE 426924 12 LBS
UP FORCES
TANK DISP FORCE 456775 15 LBS
TOTAL UP FORCE 456775 IS LBS
WORKSHEET
TANK D4TA
SHELL DIAMETER -- --- 1150 FT r ACTUAL CAP (GAL 50293 00
SHELL LENGTH------------- 62 92 FT r TANK WT (LBS) 18300 00
DOME PROJECTION - - 2 58 FT ' 0 A L (FT) 68 08
MID POINT HEIGHT--- - -- 9 45 FT ' NUMBER OF RIBS 50 00
COLUMN HEIGHT ----- -- 1520 FT * r+s***rrrrr*rrrrrrrrrsasar*+***r* rr+rr**rrr
RIB VOLUME -- -- ---- - 4407 00 CU IN DOME A (SQ FT) 44 41
DOME VOL (CU FT) 659 64
REINFORCED CONCRETE VOLUMES (CU FT )
TOP SLAB 000
TOTAL DRY VOLUME 000
FORCE = VOL Y150 LBS 0 00 LBS
BACKFILL VOLUMES fCU FT )
OVER TANK (DRY)------------ 323094 107459 WET
END-WEDGES (DRY)----- --- 157 16 88 98 WET
TOTAL DRY VOLUME 3388 10
TOTAL WET VOLUME 1 ]63 58
FORCE (DRY) = VOL X 100 LBS 338809 52 LBS
F ORCE (WE'1) = VOL K 60 LBS 69814 60 LBS
BUOYANCY
SHELL VOLUME ---- -- 6534 93 CUBIC FT
DOME VOLUME--- -- - - 659 64 CUBIC FT
RIB VOLUME-------------- -- 127 52 CUBIC FT
TOTAL VOLUME 7322 09 CUBIC FT
VOL X 7 48 GAL/CU FT 54769 20 GALLONS
FORCE = GAL Y 8 34 (LBSJGAL) 456775 15 LBS
XERXES® NON-ANCHORED RIDGELINE MIDDLE SCHOOL
BUOYANCY CALCULATION WATER AT TANK TOP YELM COMMUNITY SCHOOL
JWL 12/22/05
TAI]T{ DATA INSTALLATION
NOM CAP (GAL) 50000 TOTAL COVER INCLUDING SOIL g 5 80
TYPE (SW=I,DWl=2,DW6=3 I TOP SLAB (FT)
DRY=1 WET=2 I TOP SLAB THICKNESS(IN 3360
TANK DIA (FI') 12 TOP SLAB LENGTH (FT] 70 08
rrrrrrrrrrrrrrrsrsssrr rrrrrrrrrrrs+r rsr•srrrsrrrrr TOP SLAB WIDTH (FT) 14 00
4ROD STORED (GAL) 0 # OF 30 DIAMETER RISERS 2
SPEC GRAV USED 1 00 H OF 24' DIAMETER RISERS 3
BRINE FILL GAL 0
SAFETY FACTOR
DOWN FORCE/UP FORCE = 1.70 • Z
TOTAL WEIGHTS
DO]]'N FORCES
CONCRETE WEIGHT 41209000 LBS
BACKFILL WEIGHT 347543 69 LBS
TANK WEIGHT 1830000 LBS
PRODUCT WEIGHT 000 LBS
TOTAL DOWN FORCE 777933 69 LBS
UP FORCES
TANK DISP FORCE 456775 IS LBS
TOTAL UP FORCE 456775 IS LBS
WORKSHEET
TANK DATA
SHELL DIAMETER-- - ---- 11 50 FT * ACTUAL CAP (GAL 50293 00
SHELL LENGTH- - ------- -- 62 92 FT ' TANK WT (LBS) 18300 00
DOME PROJECTION - --- 2 58 FT * O A L (FT) 68 OS
MID POINT HEIGHT---- --- 8 75 FT * NUMBER OF RIBS 50 00
COLUMN HEIGHT------ ---- 1450 FT * *******rrrrrrx trr rrrrsrssrrrarrrs rrxrrrrr rr
RIB VOLUME---------- ----- -- 4407 00 CU IN DOME A (SQ FT) 44 41
DOME VOL (CU FT) 659 64
REINFORCED CONCRETE VOLUMES (CU FT 1
TOP SLAB 2747 27
TOTAL DRY VOLUME 2747 27
FORCE = VOL X150 LBS 412090 00 LBS
BACKFILL VOLUMES (CU FT 1
0 VER TANK (DRY)--- --- ---- 2629 62 1093 65 WET
END-WEDGES (DRY)---------- 131 52 96 84 WET
TOTAL DRY VOLUME 2761 14
TOTAL WET VOLUME 119049
FORCE (DR]~ _ ]'OL X 100 LBS 276114 46 LBS
FORCE (]i'ET) = VOL X 60 LBS 71429 24 LBS
BUOYANCY
SHELL VOLUME- -- ------ 6534 93 CUBIC FT
DOME VOLUME------------- 659 64 CUBIC FT
RIB VOLUME------- - ----- 127 52 CUBIC F3'
TOTAL VOLUME 7322 09 CUBIC FT
VOL X 7 48 GAL/CU FT 54769 20 GALLONS
FORCE = GAL X 8 34 (LBSJGAL) 456775 IS LBS
A 7o Da
rj~~ MIN FINISH GRADE ELEV =357 33
~ \ , ,
a
m
r-
N
0
0
N
(h
m
5
0
T
m
3
c
m
F-
a
d
rn
L
N
~~
~-__
-.
TANK EMPTY
° ~
N ~
•- h
~~...
12
- 'ELEV 353 33
Q 351 71
-GROUND WATER LEVEL
AT 1 2 FACTOR OF
SAFETY FOR FLOTATION
3473 8` INVERT IN=35i
33
NOTES
50,000 GALLON STEP TANK 1 CONCRETE DRY USE 150 Ib/LFy49056 Ib+
SECTION A-A O (pER XERXES)
NTS
O2 BACKFILL DRY USE 100 Ib/LF
(PER XERXES WET)
O3 BACKFILL DRY USE 60 /b/LF 408 624+16 352 Ib
(PER XERXES, WET)
O4 BACKFILL WET USE 60 /b/LF
* PER APPROVED PLANS AND DETAILS
50,000 GALLON STEP TANK
LONGITUDINAL SECTION
NTS
,~' Civil Muniupal Geotechnical Engineering and Planning °°°w°i°°' A0~" 50,000 Gallon Step Tank
u°° ax °~rt
Ridgeline Junior Ground Water Level At 1 2 F S
Jerome W Mornssette & Associates Inc , P S ~~°. °•~ ail h Schoo4
7700 Cooprr Pt Road 5 W #~ 2 Olympia Wa 98502 1110 Ph 3G0 352 9456 Fx 3G0 352 9990 wii ~mD ~ 03157~Step Tank Defod SHT 1 OF 1
RECEIVED
AUG 1 4 2061
regazd to penodre mowing to prevent the growth of woody vegetation on the pond bottom or side slopes
Based on visual observations the growth m the pond consisted maznly of alder, which is a decrduous tree
that drops tts leaves each Fall The leaves would add to the fine sods, nutrients and abundant water to
produce a pond bottom biomat that would seriously reduce infiltration rates This condition may also
have been influenced by localized groundwater mounding beneath the pond due to the concentration of
runoff m the pond
As such, the GEODATA groundwater hazazd mapping for this pond azea also reflects poor pond
performance due to poor maintenance and localized mounding during an extremely wet period Hence,
the actual local maximum shallow groundwater level is most likely somewhere between elevations 345 ft
and 348 ft
Retunung to the staimng observed m the excavation (elevation 347 4 ft), tt is probable that the maxunum
excursion was about 347 ft, groen that capillary rise m the soil would result in a slight elevation of upwazd
wetting front and stain mazks in the soil
Recently measured water levels m the athletic field azea west of the school shows present water levels to
be about 346 5 ft Grven that there is most likely some rise m the phreatic surface from the athletic field
are to the STEP Tank azea, a present level of 347 to 347 5 ft would be a reasonable assumption
Finally, measurements were attempted m the Hawks Landing Pond ~mmedrately to the north of the STEP
Tank azea This pond has remained dry through this period and the pond bottom is 348 4 ft
Based on the foregoing, it is cleaz that the shallow groundwater level m the STEP Tank azea ~s presently
below 348 4 ft and is most likely about 347 ft This present conditions ~s occumng during a record
rainfall period as noted above
CONCLUSIONS
Based on the foregoing, rt rs concluded that the approxunated maximum shallow groundwater level of
record m the vicimty of the protect srte ~s about 347 ft and is most likely occurring reoccumng at the
present time
Should you have any further questions or requrre cianfication, kindly contact me at (360)352-9456
Yours very truly,
J W MORRISSETTE & ASSOCIATES INC
~ ~~f~
Edward A Wiltsie, P E
Sr Geotechmcal Engineer/Associate
,3.~v~ Jt~,~
~-- ' ,r~
~ ~ ~°k€~la`` ~~ 11 b
Mr Jim Gibson, PE
January 21, 2005
Page 2 of 4
RF~E~~ea
AU6~ 41007
based on the observed soil condmons that ground water may rise to the mid point of the tank
elevation 347 4 The Xerxes program is not capable of determining the groundwater level at
which the groundwater would produce a factor of safety of 1 2 It is apparent, using the Xerxes
criteria, that there is some level between groundwater at the midpoint of the tank and
groundwater at the top of the tank where the factor of safety would be 1 2 We have more
thoroughly analyzed the probable maxunum ground water elevation at the STEP tank site and
find that the maximum ground water elevation is 347 Please see the attached letter report and
attachments by Ed Wiltsie of our office
We have redesigned the STEP tank location to take advantage of a parking lot island adjacent to
the STEP tank location as shown on the approved plans At this revised location the tank would
have 0 ~ feet greater depth of cover than over the previous location while maintaining the tank
inlet invert elevation shown on the approved plans Moreover the cover depth at this revised
location would include the additional weight of a concrete walkway over the top of the tank
This serves to increase the factor of safety for floatation for the STEP tank With the STEP tank
at this revised location we have calculated the ground water level at which the tank would have a
factor of safety for floatation at 1 2 to 1 Our calculation follows the Xerxes methodology and m
fact uses much of the calculated forces directly from the Xerxes calculations Our calculation
uses the same unit weights for backfill as the Xerxes calculations Also our calculation uses wet
backfill (lighter unit weight) weight where some of the backfill over the top of the tank would be
dry (heavier unit weight) We find that the 1 2 to 1 factor of safety for floatation would occur at a
ground water level of 351 74, according the calculation as described above This is about 4 feet
higher than the maximum groundwater level according to our analysis
We have heard that rt has been suggested that the Xerxes warranty would be word rf the STEP
tank is installed without anchorage We queried Xerxes and found out that without anchorage,
the Xerxes warranty would be m effect unless the tank floated If the tank floats for whatever
reason, the Xerxes warranty would not be m effect We find that this is m conformance wrih
your letter to us dated December 16, 2005
In your letter to us we noted that you state that rt is not feasible to use a piezometer to co-
ordinate maintenance of the tank to avord the hrgh ground water season W e are only aware of
one maintenance operation that would cause the factor of safety of floatation to be less than 1 2
to one, that would be if the ground water level were ever to reach elevation 351 2 during the high
ground water season and the tank were to be pumped empty So long as the ground water level
is below 351 7 that tank could be pumped empty at any time and the factor of safety for
floatation would be greater than 1 2 to 1 One might try to pump the tank empty for one of
several reasons
RECEIVED
Calculate Ground Water Elevation Required to Produce l~~rt'o114Factor of Safety for
Floatation at the 50,000 STEP tank at Ridgehne Junior High School
Since the Xerxes program is not able to calculate the ground water level at which the
factor of safety falls to 1 2 to 1, a calculation needs to be made to estimate the level This
calculation should be conservative, that rt to say rt should error of the side of showing a
lower groundwater level than on showing a higher level fora 1 2 factor of safety To
improve the factor of safety, the calculation accounts for locating the tank under an island
m the parking lot to increase the cover over the top of the tank by 0 5 feet to a total cover
of 4 2 feet The 4 2 feet of cover includes a 4 inch thick concrete slab over the tank
Xerxes noted that their method of calculating the factor of safety for tank floatation is
based on the method outlined m the Petroleum Equipment Institute Recommended
Practice 100 (PEI/RP 100) This calculation is made m accordance with the
recommended practice fisted m PEURP 100 and uses the unit weights fisted m the Xerxes
calculations and uses the backfill surface area same area above the tank as does the
Xerxes calculation The calculation shows that the 1 2 factor of safety for floatation
would at a ground water level below the top of the tank Thus some amount of the
backfill below the top of the tank would be dry To help keep the calculation
conservative, the unit weight of the backfill below the top of the tank ~s taken as though
the backfill is wet This calculation uses the Xerxes Dipstick Cahbrat~on Chart for this
tank to calculate the tank drsplacement volume at the 1 2 factor of safety ground water
level A correction factor is used with the Dipstick Chart volumes to make the displaced
volume of the tank meet or exceed the value listed m the Xerxes floatation calculations
The calculation shows that the 1 2 factor of safety would occur at a groundwater
elevation of 351 71 feet
Step One Determine the weight of the backfill above the tank
Use the weight of 408,624 12 lb from the Xerxes calculation for
groundwater level at the top of the tank with 3 7 feet of backfill
See Xerxes calculation sheet for "Non-Anchored Water at Tank
Top" dated 12/16/05
Calculate the weight of the 4" concrete slab over the top of the tank Per
Xerxes the allowable size of the slab is 70 08 feet by 14 feet Use 150
lb/ft3 (per Xerxes) to calculate the weight of the slab
70 08' x 14' x 4"/12" per foot x 1501b/ft; = 49,056 lb
See Xerxes calculation sheet for "Non-Anchored Water at Tank
Top" dated 12/22/05
Calculate the weight of the 2" of backfill under the concrete slab Use 100
lb /ft3 (per Xerxes) for dry backfill
70 08' x 14' x 2"/12" per foot x 1001b/ft3 = 16,352 lb
Add the weight of the 50,000 gallon tank = 18,300 Ib
Sheet 1 of 2
woa dloasaluax mmm;e algepene io'a;is ay; of pa~anllap;aHoetl a~n;ela;q ay; w aye yalyal;o sa#doa'Que~~eryl pa;iwll
algeagdde ®saxaag pue'sawlaping 6ugeratlp pue lenueW uogelLelsu/ osawaX 6wnlama~;noy;Im Neya uoge~gqea ay; asn;ou op NOILttla
'bZ£SZ° -` Z/l 9 Y0 BS88l~1 '~ b £ bS SL9ZL± lb OOIL+ + b L LZ + 49SZ UL EL
SOZSZF--: b1L 89 ~'`Z4L9rl# ~ UL 4S 99SZ1 bEOb LOOL~s LZ aS6bZ` - 4/l El
~+L905Z ~+ 99 -+~CZ991` `i blL bS 09bZ L'%f ' Z/l Ob ' 4169 i ~' b E 9Z LZbZ +-~N EL
696bZ ,,%~ ~al llS9l`~"'£ 'Z £Z l~'~'y4 b ~'"t=1Z89 ~~~~ Z `-6SE # `"~ bE l
05 4 .~ +` SS6£8l ~- + SbZZI ,a 6 µ't= +. l t
, Gr s•. ~a
Z£LbZ~
q `T NH^-w. 5
-~1ne08Z81~~
t E -ywn ..',.+s),
'+''-.9ElZl ~
6 + ~ n-a
"L£99ia-<',i
Z i9 ~}ow , ~t..a~
+ro~sr9ZZZ~ t+i
,4 l Zl
'-~'b196Z L ;7
~
=~
Y
`~S9191
~s b/L ES ~~ ~I EOZIt L 6£ SbS9
~'
~
~
~~
--' £ SZ ~~091Za~'~
. ,Zl
xp ~~k {{
~~
y
~
,
~~YIl~ - `Ik.~ll i~ `.{~.IN
~ ~
g.
~
y
~
" _- 1 bi „'iz'~ 5
~p
HaY"~`~'~ +'i`
~ ~kyc] 19}[.x{.
'R 'fyy j C
+4f1 r Y Y1 Y'Y. ~ yp ,..N w.
i.-~ Y'5 9Q ev'~ .d~~ ~~~p,
Y r 3?P+gM ~.y j~ 7 b Gl iYll
'~'(!I'V' f"
I`i^^5 ~' f~li` -r-r=~ s`~y'au ib a,._~~~s ~j}ry'° ;
+~Oblbr'.~»;S =AE'~~40LL 1~ ~~ k'_~~i9091L'~~~1 ~~E919~* l+=ks Zt O6L~~~ ll
{"'~ ZObZ'~''3.'~ 2~='~68SLlV~ ~ti~"OOSII~ -".-+~E6093'- l^~6E91"~=~ 4/E Ol
~~-b408~ Z l ~+SLtiLI~~~ £ ~=* S6Ell~k :"~ >'~£009:`~~ Z ir°=~LLLI"~ ~ Z l Ol
99LG~~ b/t-9 -""809ELL~- ZI IS ~~4+68ZU$ti .` b£L£ ~~`s bl6S~~''#s~d bZ ~~'~&9LLl~'.~.: b/L Ol
-+~L99£Z~a ~E~'C 94ZLl .~~ 4/L LS ~'~~`bBLtl~~>P Z/l LE r~i '9ZBSu ~r b/££Z ti.~~'SS9l~~ ,OL
` T~649EZ~ro".~c~` b!E b9 _
~ >LELLI „` tS ~+~~'6LOlLl~"'~''" 4/l L£ "kLELS~'a°' ~
" Z/l £Z " ~1~~S6Sl" ='~ b/E 6
~ IEbEZ''^ Ul b9 .it ~LlOLl:''+' b1E OS 4-SL601 "'ate [E _
~` 6495 bli £Z '-9ES1
^ U16
~iEIEEZ N'c° b/l 49 z~r£069 L'tK~> Z!L OS - 'OLEO CF~i{ 4/E 9E ' Z9SS a K~ EZ 'LL4l
1 b/l 6
.i=S6lEZ +L ,b9 +%st +88L91a#~* b1l OS ~"F99LOl~i~l'"rk UL 9E ~SLbSP ~+' 4/£ZZ ~i#`=OZb I". ~ 6
-»~:LLOEZ~hw b/E 9 '~i~:~SL991`~c:^, OS ~`_'iZ9901~~~+'. b/l 9£ _~~a98ES~~ Z/L ZZ ~~A~~Z9E lSs ~=' ,b/EB
~":"'6S6ZZ~~~ Z/l 9 :'=.'~19S91v~~+ 4/£ 64 ~ ~?'~6SS~Ol'L''~"1~ 9£ :~+ 14ZOES ~ix'~ b/l ZZ 1~s~tiwJ'L"90E1~S.°_", Z/t B
`~alb92Zcy~ b/l E9 w •.u87491`_~ Z!1 fib z~SSbOI^~~« 41E SE ~~91ZS ~~ ZZ -_~~vISZLY. 4(l 8
i9~£dLZZz E9 `'4E£9l' 41l 84 's^~5a ZSEO^ls~°r" Z/l SE ~'OE LSC'.fi~1 b/£ lZ i°ua/tf-~"~a9611 9
ii5c"S09ZZ*s- ,b/E Z9 _
%'.alZZ9l'~fa" 64 ~~;~64ZO1"~# b/t SE ''; k'~:~'S40Sa~~ Z/t lZ ~>_=~'-'Ztilll'~]`'.s~. 4/£ G
L94£Z5`_'0# Z/t Z9 bank 80L91 S°~ „b/E 84 4 Ot;~z SE .:~=~"0964.'~~ b/L lZ v~l~^690 L+~^~a ,UIL
A'~„`~v 69EZZ~'U.a~ 4/t Z9 5665 L~+~- Z!t 84 S°~:W,~bb001 +~~ 4/E 4E ~9L94~a' lZ ~-~°9E04~*~'~'~ b/L L
'?FZISZZZ~iF Z9 ~~'~ ZBBSI'~.~ blt Bb ~>=~Z466^'~fis'~ Z/L 4E ~+-+P Z6L4 b/E OZ w'rS86.i.~T, L
4:~£EIZZz 4/£ l9 & «°f69LS l~ ~ „8b ~ 4~Ob96~ „b/l bE ~~~60L4- ~' Z/L OZ ~~'~~'^'~T~b£6 u,x3a„ ,b/E 9
'3~'~S LOZZ»-~~ Z/L l9 ~s~9S9S 1' 4/E Lb ~s~8EL6~' 4£ 'v~_'~'~9Z94~ ,b/L OZ r~~°499~~1~ Z/l9
iB68lZ b/l-L9 SK' o4bS5l~,ld:~ „Z/l Lb ~',3„'LE96i'l~ 4/E EE ~ ]'3E454~ ,AZ '~'~SEB~ 4/L 9
~.' ~09L1 l9 wa`LUl E4S l~~ blt Lb ~`L.5956'+r~' Z/l EE ~~L944U~, b/£ 6l ~~LB'LS'~"`~ ,9
-~Z991Z~-`-` 4/£-09 u~YB L'ESl're'"7 db `aSEb6~._-' 4/L E£ >`~~6L£b UL 6l a~~~ObL' 4/ES
' i"SbS IZ~;i, Z/l 09 ,~'~,~LOZS L~` „4/E 9b ~"'~YbE£6, YL~ ,EE 86Zbsr'"'~ „b/l 6l ~M469W:t€.1". ,Z/l S
,..ERLZ4lZ~~ b/l 09 9'60$lh."s~ UL 96 ~s!xfb'£Z6 ~~ 4/E Z£ 4b~LlZb~~ 6l >~~ 649~u 4/L S
"-OIEIZ,r;'"„~ „09 `~'i~E8641a#~c 4/L 94 ;~"-~4E 16~~,ilF Z/l ZE ~~LE Lb>"-~~`* b/£ 9L :~~S09 c,,'~ S
f°`Z6l'lZ~ z „b/E 65 ~~,aZL84l :"'s%'" 9b `x~`-'j~bE06"~'+Wgll' b/l ZE -S~'~-LSO43ab"~~ Z/L BL 3Z9S `~6'~~i 4/£ b
•"~SLO LZi~~- Z/l 6S +"'t'~'~~09LbL~~s 4/E Sb ~=z1bEfi8'~'~'~F~ ZE
.
~9L6E~3~ b/l 8t *'~'~OZS x~ Z/lb
i` ~,~8S60Z~},~ 4(l 6S H'cr~649b 1~"»v~ ,Zll Sb Y~`"~£89~ ~~~ b1E lE m ~669Ety
' 9l ~'; 6L4?`"-~-e 41l 4
j ;„Ob80Z"~ ,6S ~T'[~~8£S4 Lid= b/l Sb af~r~,9ELB~<',~ Z/l lE ~ ~kOZB£~_yS' 4/ELL 'i?`cs'6Eb~t~ „b
i"6ZLOZ,'^~j'_ 4!£ 8S 'W3 LZbbl ~"',w ,Sb ~>„LE98 j,`,. „b/l LE c ZbLE ~~ „UL Ll i ~>; 0044 <.} 4/E E
~s,9090Z~",~' Z/L 8S >*"/<i'19 L£bl;lkxn 4/Ebb L 6ES8`G';'':~ LE iS99E'„n~~ blL LL '"`£9Er r' ,Z/L £
s'V~ 6840Z'a~_~__ „4/l-9S ~ -`~ SOZ4 L' „Ul bb -??a 1448„'§ 4/£ OE ,s c, B9SE'~'*'X Ll y,.`~ LZE~ 4/t E
y;'I~ZLEOZ~""~r'; , BS „~iS604',h~~^y'; b/t 44 ~I^'~eE4E8 ~~ „ZIL OE ,,"`„'~{lLS£~ ,blE 9l ~~.Z6Zw+~~ .E
;^~SSZOZ+~'"~ 4/£LS ~;a1~596E1`~~,~ bb 'sij~9bZ8~-~„"S~' ,b/l 0E ~ a+SEbEe..-''3ti „Z/L 9l =~3~,e 8_SZ e,~s 4/EZ
~ .: rx8E LOZ'"g; ,Z/l LS „" i-! SLBEL~s`,'',y b/E Eb - a_6619 Xj OE . +"09EE''~ 4/L 9l i t-~^„'9ZZ-'a''~~ Z/t Z
~^`;:-1Z00Z"`q b/L LS ""~1S9L£l"Y8 Z/t Eb ~~ ZSOB ^"e9` ,4/E 6Z ~~SBZE'~„~}r ,9l '!"`ssS6l'`','~M 4/L Z
',,-SO66L '~~'~ LS ;~'>SS9EL-~ ,4/L Eb ^_"v'SS6L`., ,e „Ul 6Z '~-OIZE a+',? ,b/E Sl ^is{;..991a ~'~'~' ,Z
'~88L81`.,r 4/£ 9S ` S4S£L' M~ Eb BSBLr"Sy;, „b/L 6Z ~' 9ElE%-~`+ Z/l SL ~:,. ~9E 1, a,_~ b/E L
>ZL961~+~s Z/l 9S ,:^?~9EbEl?='sF` 4/E Zb ~' £9LL_„,_y,~.+F 6Z - ~E90E~~ ,b/l Sl a;~~T Zllk',~yu'~ Z/l L
'"SSS6l~~ „b/L 9S ~`e~'li?LZ££l`%,? „UL Zb °';;.'y,L99L~4,'~{ „b/£9Z ~`. ~O66Z h;.r~ Sl ~y~~98,pT.,~,~ b/l L
"'6Eb6L~~.L, ,9S ~C.k~'9 LZ£Li~i 4/l Zb ^,v~ZLSL~s°s'''~i-t Z/l 9Z i~R~19lBi,'~" b/E bl ~'~~.'~.,,~,`, 99,~t L
_+ZZE6l^-j ,b/E SS '~"~'y 6O LEL Y~;~ „Zb ,-3x ~LLtiL„-_m'a „b/L BZ #{"~948Z: ~,y, .Ul bl t~=~9b« b/E
,r tr 90Z61 ~y~ Z/l SS (,EL000EI~,j., 4/E lb 3z`.i"~ZBELa~~r ,BZ ~;S~SL'LZn~~ 4/l bl hPr~6Z„"+`' „Z/L
.= 706061'~z „b/L SS "= Z68ZL r` Z/l lb „~~89ZTL ~P; bl£ LZ ~~;,'bOLZ~~ ,4l lg~ 5l', b/l
C c.,~>L691 SS F'£G£8LZl„~~s b/G lb ;=~{`b6lL~,.-'tv Z/l LZ 4"in~bE9Z'o '~ ,b/EEL `aal~`0`'""~'° ,0
>gtSNOlltlO
c-'~~~~ 'JNIOtl3N
MOI1Sd10 zGS,t+SNOlltlO
~-~~t~~ ONIOtl38
NOI1Sd10 '". SNOlltlO i~
~ ~I ONIOtl38
NOILSd10 <~~SNO'IltlO~
~k'~'~~ ~ ONIOtl3tl
MOI1SdI0 SNOlltlO'~'1
~ ~~„~' `~~'~ ONIOtl38
NOI1Sd10
~lu~l MS aa~aua~la lZ L - uoII~J 000`09 ao~ l~~u~ uol~eagil~~ ~{ogsdld
NOIltl80d2f00 l
069L-L88-Z56 8824-~£V55 NW`SllOdtl3NNIW
woa d;oasax~ax nnnnnn H100S 30N3Atl S3X83X 1061 ®~
1g1S0/LO OSOSZ Ix 3~<&ES49b`_',~ +'~OZObt~rw :Lr`. 89£BE:L+~.~ +~~E IOZEas~.E"'+'
Tx'. i06E84i~~ 4 l S t'~6Z6Eb~,~ tl ^~19Z8£'~~" b E 96 L&~d'V'L69LE ~=.w~ Z l Z
~~r LZE84 t ~`'~'!t9£B£4`a~iY b Oll +`b519£~`~ Z/l 98 5+"'Z9LLE6,~ 4 L Z9
~•E9Z94F3'~=
y ~~}'LbL£b4'~"N .a.r.: LbOBE~ ~999LEc~..rN`
+~'`8618b~`+" ~ SS9£b ~' .-~Ob'~6LE~^~' 'BOSS I£s"•~'
.,a ~ElB4~e-+ i 49SEb `~ / ' £EHL£ ° *4Eb lE
a~L90Bb~+re~` l ' LLb£4'~~~ Ol SZLLE< l 9l£l£ l t
~~000 4 6LEE4'+~ ~L 9LE ' ZOZ IE -
'~ -E£6 X98 + L '' `
~~a"S99 u',<l,`L.z -"`~~~ ,"~"q'Ea'~ '°ea^N60 +e_e
- -'nL6LLb'~< '~ ~=660£4 =+- ~ F Z6ZLE' ~ ~i~ - °b'S90£r
55~b8ZLLb~''.~~ ?"+S00£4 rf fi +;48 Ll £r"k~<5 '±~~zL£GO£~~~'~'
~ 6S9L4~' stio Ol6Zb b~ ` ro+.SLOLE~~ ~~ilZ90Eu"'~
+£6265 i•~~ L ~'~6H9L4~'i 4l L a~wr948Zb'cu°`~ OL v~99fi9EE~~ E 6 ~~:~40SOE
i.~B9ZOS~ l l »9-+4i8lSLb~c',~w ZZl ~~ZLZb~ b LOL 4`LSH9E l E6 ~'99EOE ~-~~ /L
r2.'~18LZOS,~.+i"ds 9El ~.~IixG4bLb=`Z~ b/E lZl ~~rv$5Z9Zb /l LOl 'SL4L9E~ b l E6 ~~~LLZO£'F-~ 6L
";~'E9ZOS 4/£5El '~' SLELb<}?~ Z/t lZl ~:~OESZb~'yk 4l LOl 1~.,$~. BE99E°r £ =F~bS IOE~rr~`n~ bE9L
~~r94'ZOSI
i h9ZZ05~.w
40Z0S"~
^+`~09LOS,~a Z/l SEl
b/l SEl
SEl
4 £ 4 '~'~ZO£Lb4~u~°
+xrkOEZLY~'x~
9SlLb,-~-
~s„Z9OL4 ~'} b/l lZl
lZl
b/E OZI
Z/L L tiEbZ4 ~
~Y~LEEZb'"
-,i.`~lbZZ4~
~~'b'~b LZb~,' LOl
b/£ 90l
/1901
4 L 90l ~`~'~8Z59E'~ ~
`.~`9*„81b9£<~'S
+90E9£~
g8C ~9£k' 4/E Z6
Z/l Z6
b/L Z6
Z6 ~~'L£ODE~.'
~~Z66Z(~~
~+~b096Z~u~+
'~''~LH96Z41a ,Z/l 9L
b/l 8L
8L
b £ L
~'~'bSIOS ~ Z/L bEl w~800L4 3Tr" 4/l OZl ~ Lb'<OZb~ 90l ~L609E~*+ 4/E L6 69S6Z~'~ Z/l LL
M~'LZLOS
~L600S ~w
~~'L900S~ir~,
i4£OOS~.:N b/L 4£l
bEl
b/E £El
Z/l EEl ~L-t`~"oEE694~4.5~
`=~5L 894 F~r
r~~L9L94~~1
~.d SOL9b,;G`~ OZl
4/E fill
Z/L fill
b/l fill ~';L>646 Lb~
<3~--'fiZSBLb'~-'
+£SL'lb~a~
'~~SS9L4~; t/E SOl
Z/I SOI
q/t SOL
SOl '~9L6SE
~~998SE~~
-~SSLSE~
:-~tb49SEs--~' Z/L L6
4/l l6
l6
b/E O6 ~ZSb6Z'~t
~oSSE£6Z~i
+~R`u+~8LZ6Z35"r~.Z'
~t~0046Z'e<~-~ b/L LL
LL
4/E 9L
Z/l 9L
xx w10005~i" b/L EEL a'~~Ss f'-'BZ994k i~ fill ~r»~9SS L4~`L~i 4/E bOl ~Z£SSE~~'_Esa Z/L 06 ~w~E86BZ,^~a b/L 9L
i9966b E£L ~~OSS94 i~-~s b/E Bll LSb lb~s~ Z/L bOl #*~~ldbS£s.a~ b/L OB =~S99BZi :~'" 9L
C-ir~0E66 b/E Z£L
-.._,--
gFkZLb9ti~ ,Z/l Bll `3r}--95E1b ~I; b/l bOl ~e3~60ES£r O6 '~~84LHZ ~= bl£SL
^~Z6964,"<_-, Z/L ZEL <~'~'.46E94 4/l Hll ,`T~~6SZ Lb r„ 40l w~iL6lSECs"",~ b/£ 68 .~.n0£98Z:~,~+ Z/t SL
~<'E5964s"c'~~ b/L Z£l ~~SLE94' 9ll i ir65 L14'}.~s 4/E EOL :&+.'1990SE~i`.,~ Z/L 69 ~£lSBZ A:~ b/L SL
b186G}`'`~~ ZEL s.x9EZ94~~~~ 4/E LII Y~R 6SOl4"t;>~< Z/I EOL `~,+'EL64E ~~„~": b/L 68 'k'~S6EBZa"`/ SL
ELL64 4/£ LEL ~.4s' 9S 19b~ ~ Z/L Lll §;'+~'6S60br„`~'7 b/t EOL > n?1994£ c,Ll'.+, 6H r=~ LLZBZ6f°~- .b/£ bL
~'L£'L87~ ,Z/L L£t td~. 5L094~ 4/L LLl ".Lt>f9S804 ~ EOL '.~<,64'Lb£~~ „b/£ 98 `rxH6S l9Z~v"~ Z/L bL
;i8H96bi b/L lEl ~ :S66S4 ~ „Lll ~'..~`-'LSLOb~a'~ b/E ZOl " 9E9bE.~':;~ Z/L 9B `~ Zb09Z„~
~ 4/L 4L
,E496b~.. lEl z~'iE l6S'b, b/E 9ll `,~F<9S904p^^V~-,~= ,Z/L ZOL 6^ xbZ54£r~t''# b/L BB z<+4Z6LZ;t ~' 4L
~,H6564r b1E DEl >~...~ZE'HSV~ Z/l 9ll ~'~ CSSOb 4/I ZOL ~^`~Llb4E. ~ 8H ''s.55908LZ,s~ir b/E £L
*Z5S64_s~#~`` ,Z/l 0£L ,^~.~~ 64LSb+~~ 4/L 9ll -k.~Y ESbOb ~` ZOl 1t,286Zb£:~ b/E L8 42>n"899LZr ~~ ,Z/L EL
,sSOS64~'r} b/L 0£L =x L99S4'i!%g 9Ll '~=HlSE04~s"5i' 4/E lOl ~,.SB LbE;-W ;< Z/L L8 8, iOLSLZ~~~ „b/L EL
„-z{y'LS464i4;91-, OEL ~-~bBSSb,":,~ ,b/E Sll ~' 64Z043:+'~`" Z/L LOl ~ °ZLOb£°ui'~ti bll LB ~~ZSb'LZ.,,a.; ,EL
~'n~H0484}~3 ,b/£ 6Zl 'xS'~,"0055b~~~~ ,Z/l Sll ~rTj`.:9b,1'Ob`'~`,~; ,b/L LOL ~8§6E£~~p ,L8 }:'ig4E6LZir;, bl£ ZL
~„`?~8S£6ti?Y',~ Z/t 6Zl ~Kr`LL4S4~'z 4/l Sll {`~-?44006~'b lOl r,~rS48EEa~~' 4/£ 98 3E'.t',.9lZLZ'".,.fd Z/l ZL
~„~,"90£6b''~; 4/t 6ZL L^r",'~,~ZEES~'+ Sll 31,'Fy,}'„L466E' b/E OOL ;"~pl£L££;i Z/l 98 ='1~,~860'LZ 7+n~ blL ZL
;~?95Z6b~-~ ,6ZL I~'a,86ZSb,"~„^+~ b/E bll ~.~3`LE86E."~,~`. Z/100t Lt_9EE~a"y~' „b/L 9B ~0_969Z.~au ,ZL
r:~blbOZ6b 4/E 8ZL "^sia`-9Z9LSb~' 3i Z/L bll ~'.#ib£L6E'~ b/L OOL @'~'bOSE£"+,~Lx, 98 ~~1999Zi~ bl£ lL
~',wlSl64~~`j Z/L BZL ifi`}``CLOS4'',` b/l bll ~'OE96E~?I OOL q'v~-`O6E££~"~$ ,.b/E S8 ~~E4L9Z iii ,Zll lL
~'a<,t L6064 ,b/t 8Zl '~;gr46644 `~.+',„; 4Ll ',~'y'9ZS6E.; w;`~,'~ b/E 66 w?~aa9LZEE~„a Z/l S8 ~~,3~SZ99Z 4/L lL
-',~ZbO64,i"'~"'~ 8Zl ~'S064b 4/E ElL e`;aF~ZZbfiE~-~ „Z/l 68 L91£E~ 4/t SB ~',}-LOS9ZF LL
s9H6H4' ,bl£ LZL g~°a~8184b_',*-~m Zll £ll ~~HlE6E y bIl 66 w~.~'L40££~#~ ,SH ~,~68E9Z,pL,,~y ,4/E OL
sw~0E684Ly~~l- Z/L LZI w~ 1EL49„-",~ b/l Ell '~'£LZ6E;, wY 66 ~2'xx ZE6ZE§~'~, ,b/E 49 OLZ9Zr'q~.~ ,Z/l OL
;,~',,+EL98b` ,b/l LZL ~" ~,Eb94b~`_~ ,£ll 4'~8016Ey` b/E 86 `~~~819ZE~.~? Z/L b9 "SZS L9Zk NO' 4/l OL
;6~51'884,a LZl it ,z,'SSSbb'~s` 4/E Zll wti£OO6Ei~i71 Z/l 86 ~ ~EOLZE~;~ „blt b8 ~~ ~4E09Z+~'~ „OL
~y.,LSLBb'+ ~° b1E 9Zi L9bb'4 ~ ZIL Zll _ ~9699£r, +~ b/l 86 ,,,,=HBSZE';, b9 -..~S165Z b/E 69
~,~7YL698b~,}3~ Zll 9Zl ,'~nIzU BL£44„ „b/L ZII ,:',.kiZ6L9£"~yy, „96 .<r,P ELbZ£,~'-~.b ,4/E E9 w'~~'L6GSZ.~'Y ^' ,Z/l 69
F'~fL£984 ";,~ 4/L 9Zl +z,~68Zbb~~ .Zll -'`L89BE5:?~ 4/£ L6 ;~TBSEZE*,P Z/L EB sa•{6L9SZ+~F; 4/l 69
'~s`~LL58b~y„"s*' ,9Z1 °r'~.;OOZ44,~i~„ blE lLL ~~' IBSB£I'i ,Z/L L6 +r ~.~EbZZE~{t~',' b/L £H ~l„+«rt`,09SSZ `,k 69
'~d`SLS94-~°~ 41£ SZl ~=~~'Olibb Z/L tll ~~bLb9Eu~s t!L L6 BZIZ£*,~~, E9 "ZbbSZa's'~' ,b/£ 89
~J~SNOlltlO~
~~ka ONIOtl3kf
NOI1Sd10 'SNOlltlO"k
~:~:~'~'~~°-."z./. ONIOtl3k!
H9115d10 "",iSNOlltl<J3~
~^"~s."r'E. ONIOtl3k1
NOI1Sd10 ~ +SNOlltlO_`,i
{der; ',`~~zw~ ONIOtl3tl
NOI1Sd10 =1SNOlltlO ,=
;°~," ~, 55..'~°± ONIOtl3Fi
NOI1Sd10
~lupl MS ~a~awela ,Z~ - uoII~J 000`09 ~o~ uey~ uol~8~glle~ ~~lisdld NOllb'liOdaO~ S3Xti3X
®
XERXES
NON-ANCHORED CITY OF YELM
JYANCY CALCULATION WATER AT TANK TOP RIDGELINE MIDDLE SCH OOL
..., JWL 12/16/05
TANK DATA INSTALLATION
NOM CAP (GAL) 50000 TOTAL COVER INCLUDING SOIL &
TYPE (SW=1 DW1=2,DWII=3
1
TOP SLAB (FT) 3 70
DRY=1, WET=2 1 TOP SLAB THICKNESS (IN 0 00
TANK DIA (FT) 12 TOP SLAB LENGTH (FT) 0 00
rrarssrrrrssrasrrrrsrsrrrrsrrrrrrrarrrrrrrrrrsrrrr TOP SLAB WIDTH (FF) 000
PROD STORED (GAL) 0 N OF 30' DIAMETER RISERS 2
SPEC GRAV USED 1 00 tl OF 24' DIAMETER RISERS 3
BRINE FILL GAL 0
SAFETY FACTOR
DOWN FORCENP FORCE _ ~ 93 ,
TOTAL WEIGHTS
DOWM1 FORCES
CONCRETE WEIGHT 000 LBS
BACKFILL WEIGHT 408624 12 LBS
TANK WEIGHT 18300 00 LBS
PRODUCT WEIGHT 0 00 LBS
TOTAL DOWN FORCE 426924 12 LBS
UP FORCES
TANK DISP FORCE 456775 15 LBS
TOTAL UP FORCE 456775 15 LBS
WORKSHEET
TANK DATA
SHELL DIAMETER ---- --- 11 50 FT r ACTUAL CAP (GAL 50293 00
SHELL LENGTH -------- 62 92 FT ' TANK WT (LBS) 18300 00
DOME PROJECTION- - --- 2 58 FT r O A L (FT) 68 OS
MID POMT HEIGHT- ---- 9 4~ FT • NUMBER OF RIBS 50 00
COLUMN HEIGHT --------- 1520 FT r rrr rrrararrraasrr+rrrr rr rrrrrrrrr rrrsrxs rrr
RIB VOLUME--- --- ---- 4407 00 CU IN DOME A (SQ FI) 44 41
DOME VOL (CU FT) 659 64
REINFORCED CONCRETE VOLUMES !CU FT 1
TOP SLAB 000
TOTAL DRY VOLUME 000
FORCE = VOL Y150 LBS 0 00 LBS
BACKFILL VOLUMES iCU FT 1
OVER TANK (DRY)---- - - -- 3230 94 1074 59 WET
END-WEDGES (DRY)-- - - I57 16 88 98 WET
TOTAL DRY VOLUME 3388 ]0
TOTAL WET VOLUb1E 1163 ~8
FO RCE (DRY) = VOL X 100 LBS 338809 52 LBS
FORCE (WET) = VOL X 60 LBS 698]4 60 LBS
BUOYANCY
SHELL VOLUME - ------- - 6534 93 CUBIC FT
DOME VOLUME---- - ---- 659 64 CUBIC FT
RIB VOLUME ------ 12752 CUBIC FT
TOTAL VOLUME 7322 09 CUBIC FT
VOL X 7 48 GAL/CU FT 54769 20 GALLONS
FORCE = GAL Y 8 34 (LBS /GAL) 456775 (5 LBS
XERXCS® NON-ANCHORED RIDGELIKE MIDDLE SCHOOL
BUOYANCY CALCULATION WATER AT TANK TOP YELM COMMUNITY SCHOOL
JWL 12/22/05
TANK DATA INSTALLATION
NOM CAP (GAL) 50000 TOTAL COVER INCLUDING SOIL 8
TYPE (SW=1 DW1=2,DR'11=3
1
TOP SLAB (FT) 5 80
DRY=1, WET=2 I TOP SLAB THICKNESS (IN 33 60
TANK DIA (FT) 12 TOP SLAB LENGTH (FTJ 70 O8
stttttsa sr«««rrrrstsrtr«trr«rrr««r «rr s«r rrtra+srrr TOP SLAB WIDTH (FTJ 14 00
PROD STORED (GAL) 0 # OF 30' DIAMETER RISERS 2
SPEC GRAV USED 1 00 k OF 24' DIAMETER RISERS 3
BRINE FILL GAL 0
SAFETY FACTOR
DOWN FORCENP FORCE = j ']Q j
TOTAL WEIGHTS
DOWN FORCES
CONCRETE WEIGHT 41209000 LBS
BACKFILL WEIGH7 347543 69 LBS
TANK WEIGHT 1830000 LBS
PRODUCT WEIGH7 000 LBS
TOTAL DOWN FORCE 777933 69 LBS
UP FORCES
TANK DISP FORCE 45677515 LBS
TOTAL UP FORCE 456775 15 LBS
WORKSHEET
TANK DATA
SFIELL DIAMETCR-- ---- -- 1150 FT r ACTUAL CAP (GAL 50293 00
SHELL LENGTH - --- - -- 62 92 FT • TANK WT (LBS) 18300 00
DOME PROJECTION ------ 2 58 FT • O A L (FT) 68 08
MID POINT HEIGHT --- ---- 8 75 FT « NUMBER OF RIBS 50 00
CGLIJMN HEIGHT ---------- 1450 FT r 4r«r Yrrrif Yr k44r«««i «rtrt«rtrrrtiFkr ««Y kr t#tt4
RIB VOLUME- ----------- --- 4407 00 CUM DOME A (SQ FT) 44 41
DOME VOL (CU FT) 659 64
REINFORCED CONCRETE VOLUMES !CU FT 1
TOP SLAB 274727
TOTAL DRY VOLUME 2747 27
FORCE=VOL X150 LBS 41209000 LBS
BACKFILL VOLUMES (CU FT 1
OVER TANK (DAY)----- ------ 262962 109365 WET
END-WEDGES (DRY)-- ------- 131 52 96 84 WET
TOTAL DRY VOLUME 276114
TOTAL WET VOLUME 119049
FORCE (DRY) = VOL X 100 LBS 276114 46 LBS
FORCE (WET) = VOL X GO LBS 71429 24 LBS
BUO]'ANCY
SHELL VOLUME------ ---- 6534 93 CUBIC FT
DOME VOLUME-------------- 659 64 CUBIC FT
RIB VOLUME- ------------ 127 52 CUBIC FT
TOTAL VOLUME 7322 09 CUBIC FT
VOL X 7 48 GAL/CU FT 54769 20 GALLONS
FORCE =GAL \ 8 34 (LBSJGAL) 456775 15 LBS
A 7D Da
nj --~ MIN FINISH GRADE ELEV =357 33
a
0
N
W
N
0
0
N
m
m
0
T
J
3
v
m
m
0
x
c
n
t
~~
353 33
4 LEVEL
2 OF
LOTATION
JVERT IN=351
NOTES
50,000 GALLON STEP TANK
SEGT~ON A-A O CONCRETE, DRY USE 150 ib/LF~49056 Ib+
N T S (PER XERXES)
OZ BACKFILL DRY USE 100 Ib/LF
(PER XERXES, WET)
O3 BACKFILL DRY USE 60 Ib/LF 408 624+16 352 Ib j
(PER XERXES WET)
O4 BACKFILL WET USE 60 Ib/LF
:k PER APPROVED PLANS AND DETAILS
50,000 GALLON STEP TANK
LONGITUDINAL SECTION
NTS
81SIO,
~`.r~
` . r
l~~
7~ 01
\~
~~
Gvil Muniapal Geotechnical Engineering and Planning ~°1°a' nvas~ 50,000 Gallon Step Tank
^oo,. o^,~ Ridgeline Junior Ground Water level At 1 2 F S
}erome W Mornssette & Associates lac , P 5 =~F~~. o^~ Hi h School
1700 Cooper Pt Road S W #B 2 Olympia Wa 98502 1170 Ph 360 352 9456 Fx 360 352 9990 o^rt~nn»m g 03157\Step Tank De[oJ $HT 1 OF 1
i
RECEIVED
AUG 1 4 ?OJ7
regazd to penodic mowing to prevent the growth of woody vegetation on the pond bottom or side slopes
Based on visual observations the growth m the pond consisted maznly of alder, which is a deciduous tree
that drops its leaves each Fall The leaves would add to the fine soils, nutnents and abundant water to
produce a pond bottom biomat that would senously reduce uifiltration rates This condtion may also
have been influenced by localized groundwater mounding beneath the pond due to the concentration of
runoff to the pond
As such, the GEODATA groundwater hazazd mapping for this pond area also reflects poor pond
performance due to poor mazntenance and localized mounding dunng an extremely wet penod Hence,
the actual local maximum shallow groundwater level is most likely somewhere between elevations 345 ft
and 348 ft
Returning to the staining observed m the excavation (elevation 347 4 ft), it is probable that the maximum
excursion was about 347 ft, given that capillary nse m the soil would result m a slight elevation of upwazd
wetting front and stain mazks m the soil
Recently measured water levels in the athetc field azea west of the school shows present water levels to
be about 346 5 ft Grven that there is most likely some nse m the phreatic surface from the athletic field
aze to the STEP Tank azea, a present level of 347 to 347 5 ft would be a reasonable assumption
Finally, measurements were attempted m the Hawks Landing Pond unmediately to the north of the STEP
Tank area This pond has remained dry through this penod and the pond bottom is 348 4 ft
Based on the foregoing, rt is cleaz that the shallow groundwater level m the STEP Tank area is presently
below 348 4 ft and is most likely about 347 ft This present conditions is occurnng during a record
rauifall penod as noted above
CONCLUSIONS
Based on the foregoing, rt is concluded that the approximated maximum shallow groundwater level of
record m the vicuuty of the project sde is about 347 ft and is most likely occurmg reoccumng at the
present rime
Should you have any further questions or require clanficatton, kindly contact me at (360)352-9456
Yours very truly, ~, _
aPc ~~"',
~t,'~ t~fi ~,r'. .
J W MORRISSETTE & ASSOCIATES INC P S ~ ` _', r'~ az~
C__.OkR~ ~7J-~1i( N ~J ~ ~ r ~ J ~~ ~~ ~ J~~
a~ ? ~ ~
Edwazd A Wiltsie, P E
Sr Geotechmcal EngineerlAssociate
(~ ~ n; ~tf`
e ~Lr,
'r~~
< c
q~~ .._-
wry ~
t^,~ ~, ~,"
'a~... 1 .~
~^~~'
` ~
'y k~..yPip9y~.i~ ~J ~ 9 V
Mr Tim Gibson, PE
January 21, 2005
Page 2 of 4
RECEIVED
AU614 2007
based on the observed soil conditions that ground water may use to the mid point of the tank,
elevation 347 4 The Xerxes program is not capable of determining the groundwater level at
which the groundwater would produce a factor of safety of 1 2 It is apparent, using the Xerxes
criteria, that there is some level between groundwater at the midpoint of the tank and
groundwater at the top of the tank where the factor of safety would be 1 2 We have more
thoroughly analyzed the probable maximum ground water elevation at the STEP tank site and
find that the maximum ground water elevation is 347 Please see the attached letter report and
attachments by Ed Wiltsie of our office
We have redesigned the STEP tank location to take advantage of a parking lot island adJacent to
the STEP tank location as shown on the approved plans At this revised location the tank would
have 0 5 feet greater depth of cover than over the previous location while maintaining the tank
inlet invert elevation shown on the approved plans Moreover the cover depth at this revised
location would include the additional weight of a concrete walkway over the top of the tank
This serves to increase the factor of safety for floatation for the STEP tank With the STEP tank
at this revised location we have calculated the ground water level at which the tank wou]d have a
factor of safety for floatation at 1 2 to 1 Our calculation follows the Xerxes methodology and in
fact uses much of the calculated forces directly from the Xerxes calculations Our calculation
uses the same unit weights for backfill as the Xerxes calculations Also our calculation uses wet
backfill (fighter unit weight) weight where some of the backfill over the top of the tank would be
dry (heavier unit weight) We find that the 1 2 to 1 factor of safety for floatation would occur at a
ground water level of 351 74, according the calculation as described above This is about 4 feet
higher than the maximum groundwater level according to our analysis
We have heard that it has been suggested that the Xerxes warranty would be void if the STEP
tank is installed vnthout anchorage W e queued Xerxes and found out that without anchorage,
the Xerxes warranty would be m effect unless the tank floated If the tank floats for whatever
reason, the Xerxes warranty would not be m effect We find that this is m conformance with
your letter to us dated December 16, 2005
In your letter to us we noted that you state that it is not feasible to use a piezometer to co-
ordinate maintenance of the tank to avoid the high ground water season We are only aware of
one maintenance operation that would cause the factor of safety of floatation to be less than 1 2
to one, that would be if the ground water level were ever to reach elevation 351 2 during the high
ground water season and the tank were to be pumped empty So long as the ground water level
is below 351 7 that tank could be pumped empty at any time and the factor of safety for
floatation would be greater than 1 2 to 1 One might try to pump the tank empty for one of
several reasons
RECEIVE
AU614 ?007
Calculate Ground Water Elevation Required to Produce 1 2 to 1 Factor of Safety for
Floatation at the 50,000 STEP tank at Ridgehne Junior Hrgh School
Since the Xerxes program rs not able to calculate the ground water level at which the
factor of safety falls to 1 2 to 1, a calculation needs to be made to estimate the level This
calculation should be conservative, that rt to say rt should error of the side of showing a
lower groundwater level than on showing a higher level fora 1 2 factor of safety To
improve the factor of safety, the calculation accounts for locating the tank under an island
m the parking lot to increase the cover over the top of the tank by 0 5 feet to a total cover
of 4 2 feet The 4 2 feet of cover includes a 4 inch thick concrete slab over the tank
Xerxes noted that their method of calculating the factor of safety for tank floatation is
based on the method outlined m the Petroleum Equipment Institute Recommended
Practice 100 (PEI/RP 100) This calculation is made m accordance with the
recommended practice fisted m PEI/RP 100 and uses the unit weights listed m the Xerxes
calculations and uses the backfill surface area same area above the tank as does the
Xerxes calculation The calculation shows that the 1 2 factor of safety for floatation
would at a ground water level below the top of the tank Thus some amount of the
backfill below the top of the tank would be dry To help keep the calculation
conservative, the unit weight of the backfill below the top of the tank ~s taken as though
the backfill is wet This calculation uses the Xerxes Dipstick Calibration Chart for this
tank to calculate the tank displacement volume at the 1 2 factor of safety ground water
level A correction factor is used with the Dtpstcck Chart volumes to make the displaced
volume of the tank meet or exceed the value fisted m the Xerxes floatation calculations
The calculation shows that the 1 2 factor of safety would occur at a groundwater
elevation of 351 71 feet
Step One Determine the weight of the backfill above the tank
Use the weight of 408,624 12 lb from the Xerxes calculation for
groundwater level at the top of the tank with 3 7 feet of backfill
See Xerxes calculation sheet for "Non-Anchored Water at Tank
Top" dated 12/16/05
Calculate the weight of the 4" concrete slab over the top of the tank Per
Xerxes the allowable size of the slab is 70 08 feet by 14 feet Use 150
Ib/ft3 (per Xerxes) to calculate the weight of the slab
70 08' x 14' x 4"/12" per foot x I SO lb/ft3 = 49,056 lb
See Xerxes calculation sheet for "Non-Anchored Water at Tank
Top" dated 12/22/05
Calculate the weight of the 2" of backfill under the concrete slab Use 100
lb /ft3 (per Xerxes) for dry backfill
70 08' x 14' x 2"/12" per foot x 1001b/ft3 = 16,3521b
Add the weight of the 50,000 gallon tank = 18,300 lb
Sheet 1 of 2
~~ ~® 7901 XERXES AVENUE SOUTH www xerxescorp cum
CORPORATION MINNEAPOLIS, MN 55431-1288 952-887-1890
Dipstick Calibration Chart for 50,000 Gallon - 12' Diameter SW Tank
"~"' °
DIPSTICK +~~~~~' ,
READING ,.6;,GALLONS~
DIPSTICK
READING ~`°~ ,
~~;,,`~,,'~`~~ 4
ar~GALLONS3,.,, DIPSTICK
READING ~ 3Y~""'~#i
.d,
~ 6~~
,~,GALLONS'~"4 DIPSTICK
READING `+` "T''~`~'
e
t", "~'tiuk~ ~~
g~GALLONS~ DIPSTICK
READING ' ~`~i
~~
GALLONS',,,
0 ~`~,Or~n`-" 133/4 i2634~ry~ 271/2 ",--,;,~~7,194,ga~a-~,.}, 411/4 ~7„12783~'~j 55' °~-~'g18974A-T
1/4 a~~~,15~`,~~~ 14' ~'x'. z"2704~;.,~ 273/4 ~'?7288."a,.-x, 411M2 9,:12892 w„~ 551/4 ~-,~=~5,19090..,`~..
1/2 '~.,.29~T`;, 141/4" I'~~2775t-;17~,- 28" ~ej7~~g7382~tIW;'t 413/4 ~18000q 551/2 19206 ',',t,
3/4" ,~'2're'46 141/2 ~n2846,~ wr 281/4 ~,7477s='?. 42' ~~13109~," 553/4 %p~19322` _
1 =-`~jws' 86~ r 14 3/4 W+~+"2918~^.+4~ 26 1/2" 'v`-iT7572{;v" 42 1/4 may,-13218 ,.~`~y'- 56 ''~'g19439 ,:
11/4' ~;,"~'88i~ 15" ???~2990q`y3,`w2 283/4 ~=j++~7667~~L' 421/2" ~~13327:~-~ 561/4" y~',19555 Fr.
1 1/2 {'~'~1'12`i ~',~ 151/4' _„~3063r"iyT 29' 'k,.~i 7763,+4.' 423/4 ~ ,<13438 '+~ 56 V2 ~+~19_672a
1 314 ".,".~~' 138 ~,~~, 15 112' _„y 3136 _ ," 29 1 /A ;;.'~ 47859 43 ; ; -13545 56 3/4 ; s?' 197_88 -
2 ,i`~4166~+~+ 153/4' '~`~3210 291/2 '~~;~7955+ 431/4' 4-„13655 x;t 57 -X19905 -,'„~
21/4 n7d195~a~r 16' ~~;~3285r 293/4" a'IJ x'8052„'' 431/2 ~~~„13765y~~t '' 571/4 „y4+f20021.;i;~w
21/2 ;,"+«,.; 226iy>°.,; 181/4" =~~3360,r~ 30 ~ 8149 ~,_ 433/4" ~~13875"~= 57-1/2' "Ct',20736'`1
23/4 ` ys`~^250 161/2" ?x`3'435 rte' 301/4 ~'~-i8246'ri' 44' ~.13985h °~ 57 3/4 ",ft~-. 20255~N~
3 °:~1'E292~~ 163/4' ~,~~3511k~~" 301/2 411'h'~8_343~' 441/4 -:'',14095°:~;. 58' ;ry~20372~;;,J
31/4 ~'~y327„~; ~,:,^ 17 ",{'1_c~ 3588 °.-°t" 303/4' ~'~,~8441;j, r" 441/2' ,%.14205 ~~ 581/4 r'20489P~, ~'S,
31Y2 ,+ '363 ~,c 171/4' p_ _3665.. 31" r+=°8539_' 443/4' ~-'14316 v~ 56-1/2 '>~20606 tC
33/4" ~'_',>400,~'~-"_ 171/2 °x,;,3742 311/4 °'~.,+,8637°~~ 45 "=,~14427 fr;; 583/4 '~=20723.5,
4 ''~~439j~ y'$xq 17 3/4' t~,~3820~'ii; 31 1/2' i,~+,8736 ~7a 45 tl4 ~~1,4538 ~~ 59' ,~'20840ry,rlfi
41/4 +~'~~?479~-y`~w 18 ~,y'~,`=_3699jyE~,;, 31 3/4 Y.'?"~8835t" 451/2' `x^146_49 ~=„ 591/4 ;r1,S~20958k~
4 1 /2'
+°~-+" 520 --•-+
Ye`a=J ..-..A`+°x..4
18 1 /4
x-3978 ;s
L m-+.`. .~i: -
32
i~+a 8934,}x„
_0
45 3/4
~;,, £ ~+.
*~+14760 ~
'Snx. 59 1/2 a° 21075
.'.tlh. ~ (n,
43/4 ~"r 562"ra;,~ 181/2 ~~ 405757Fy, 321/4" .~°~}9034~~ 46 ~.,,~14872xT 593/4' 1$~2_7192i,.r-4,
5 r~+„"`a605,i "'`,1 18 3!4 +~y f;4137,~1,'~~ 32 1!2 ,~q",~9134`~wx„- 46 1!4' r 14983', 60' ",'+~~-°21310•"
5 1/4 `~~~~649~ 19 @r,~4217,a. Yy~ 32 3/4 ss 5`T19234 w~' 46 1/2" ~ ;15095 60 1/4 "'~ 21427„}"
51/2 ~:~694?i 191/4 ~~4298=~y+~ 33 ~+"9334p~i{, 463/4 ~15207~*y~' 60-12 21545'p,F, "'
53/4 ,~cF740~~.,*-~ 191/2 .4379 d^~~M 33114' ^~i ~9435$+yMy 47 b"15319 ~xa:'1 60-314' S~u'21662,";.c
6" ~y~.~787~',c3. 19 3/4 ~4461~y~Trt 33 1/2' ~ ;~~,9535>~`;;~. 47 1/4 Tx15431~ ,,~ 61" '~ 21780 y.k
61/4' ~635y„~~ 20 ~,""1`°~4543~"' 333/4 ~n ~~a9637; t?`~ 471/2 ~~15544'y-`-y* 611/4 ~,=218981,:j
61/2 ~~`,ij~664^i~.~~xS 201/4° 4~~?~4626e.S~ 34 ~Y~"9738~;~ 47314' ~e"}"~'15656P,"~. 61 1/2 i;~220~1511~
63/4' r`~*`;"934y,~g 201/2 ~4709~t' 341/4 ~9640~;~~x 48 ~~,~;15769 "y>r"~ 61-3/4' „22133_~S?¢„
7 -~#~'~'985~'~ 203/4 ~^y-4792~~ 341/2 e~9942~~ 481/4 75682 62 .#222_51
7 1/4 ?~1,1036~ 21' ~~~~487~,~>, 34 3/4 ~ 10044~5~~' 48 1/2" ,~'~75995"~ 62 1/4 ~'2236~~.'
71/2' *q,r+1089 °.~aa"-~n
'e. 9ez.....: 211/4 ~496~i~~' 35 Irr Q~,101a4~ti^
t +o 463/4 -~j.16108~~,t
b. 621/2 ~~~k22487f~r~~
r+ v
73/4 ri tp~1142-~x'?` 211/2 z~'~'SO45F~~s--'~ 351/4' pt~~i14~`10249 ~'~'p 49 r+16221 a`~~ 623/4 2~22605.d ~'
g ~i1196~ 13/4 ;~T~513y~ 351/2 +~1035~y~ 491/4" ~6334~, 63 2723=: 3rss
8114 ~x,~t;.~ 22 w~~521~=5 35314 0456 ;~; 49112 .71,6448 yt~ 63-114 x'°",22841 w~?
8 1/2 J,,~n~1306a'~c~~e 22 1/4 i~,,,~v+~5302+~y";~.~^ 36 ~ri~,r 0559~}~" 49 3/4 ~ ~,~16561~,,tk 63 112 ~p}5il22959~y,^y
83/4' ~,136~ 221/2 t~,:~5388~st,~i 361/4 ~.n ,,108624 x'~ 50 16675'~*., 63314 ~23077~,
9 ~„-,'.,,,1420_°~~t
~ 22 3/4 ~yt 35475is . 36 1/2' tJ~?110766"+ 50 1/4 ~~" 116789_ :~'~ 64' `„~23195_y
91/4 i`_-1477J 23 ~~' 5562.
~ 363/4 ,.'"~+1y10870
" 501/2" j~c~y16903F,E;"`, 64-1/4 s"~K'~233/3r<
91/2 1536r-~ ^
C+ 1 231/4 *f5649
1 I 37 'm/„10975~t<
iKa 1 503/4 ~~r1,7077"'~
{{ .i L,Y-a_ 641/2 t~~s23431
.u.+{w,_
9 3/4' ~59W5~ ~ _ 3 1/2 " ~5737i ' 37 1/4" t X11079^a 51 1~317131~!, 64 3/4 ,23549x_
10' ~~+~i 655~~r 3 3/4 fn'"~s826 yK,cy 37 1/2 ~ fy111y 84i r.a 51 1/4 17246 ~T., 65 ~~2~368~+
101/4 ,~pr~',1~7165t~".aff 4 ~+~5914ka e~ 3734 rj3x11269 w+
" 51 112 ~17360~~y^ 66-114 23786",H
101/2 ~~177,7 ~y,+- X6003 t~~ z~~M 11395 .1 5 .~~.4.7m+t~~ - 2 ~ ~239~0~~
10 34 F839L'S~sF' ~~~6~-93~ ~-` r ~''1~~~ ~s .77 8.,9.YL~ , X240 2 a
11 ,f ~1. ,2ax ~>t:ra~,-Br3s^i a~G1~6~W6,9l i£i "'t`.im17y04~ FAd24140Y
~.n~ i~ w~.~:~~3.+ ~u~~nL."t~aan.d baann.~f' 'r.-..c~~'mir~ a
~''~..-...~' ~~~T. ',''~xiP 4k ~~E.a-~F-ti~ y~-.-.-a~'sw ~9~,.r .-~/
~~f13«,n ~ cl.`t ...: ~ ,"4~:.9r ~ -`v ~~ -4; i
- f'~j. w
12 ~2160>~'
J, a.+.,i 3/4 ~., 6545 *,
A 1/2 ~+12031>"~3°;,
v..~n QCCk 531 ;o- E18~165 ~~
a~~ w 7 ,fig 24614An;1,
Jar
121/4 L~~2226p~v~ ; 6~,~6637~!~^3
~ 4 y,+r~T2138-~^ 53 `.18280 ~ 4 ~,,~247~ 2
1 1/ _ 4Y'`=
+t~+ 'tc 67
-
M+rt 'fa ;;L T72245;'+
r4ss "18395+r,
~cv~-~_ tla~r ,2485
'f
~
1 4 ~,2 59 ~-
" Y{~6821~y,5 3.i' 12352+ 54 3~~18 11ki„o~ 4 ~ *249 9
13 _+ 2427-, 26 3/4 n=,r ~ 6914 y 40 1 2 - 12460+ 54 114 +t +'N18627,.f;~.~ 68 ,.~r25067
13 1 /4 .2495, _ 7 + ,7007
Y 40 3 4 ~ 2568 54 1!2 ~ i18742~ 68 1 /4 dY25205^
13 1/2 2564 7 1 4 7100 41 a 12675 54 3 4 n18858b ' B 1/2 T, 25324
CAUTION Do not use the Calibration Chart without reviewing xerzes° Installation Manual and Operating Guidelines, and Xerxes° applicable
Limited Warranty, copies of which are in the literature packet delivered to the site, or available at www xerxescorp cum
lalso/L6 osaSZL>< ,~ceresti96`~x~. -~ ozoibx~"' ~..~a9E9e~,~ ~~~eiois-~~~
~~O6EB4~"i~'! LSZ =~`{6Z6E4~~'~'b Ll ="^~L+L9Z8£~+.n`-'~++{ bE96 «~BtEi-'r"di Z/l
~=` LZ£84~~`- SZ ~=i8E8Eba"rbx' b Oll ~fbS lB£~~a Z L 96 ~~~ZBLLE rt+` b t ZB
<
=x E9Z96
'~^
~LbL£b`~
r r F'LbO8E0'`'~
~An{~
.L 9991£s't
Y"+8618b1t~~e r~SS9£b ~~'~~"` ~YOb6LE'~3~- ~ rOSS I£~~~a;
~tE£L84'~ +. b9SE4+' EE9LE ` :b£b lE° ^
~wL9094~ L e LLb£b " b . SZLLE - l BLE IE+ ~M
'~~#0009ti .~
' 6L££b~ '
LL9L ~ ZOZ IE ~~
j°, u w~-g.'d* __ y~ `s+ :JflOti ~'a~k pia ~ £s `3'+~
=+L6L b~; - n
`l ~ 660Eb'~`~+ ~ a~--r . -
+~Z6ZLE' =~ ~..-++:-w t
-y"16SBOE°}-
m:-~.-.o
c-[BZLL'~~
~ ~. SOOEb'~~'~'
~~ 481LE .~
~~S ~L£LO£~b
'l 6S"r 9Gb ~; ~'~~Ol6Zb~'~ ±~j SLOL£~~'+~~ ~`a~=LZ90£== ~fx
r
s£6ZOS-~''
j~~'BBZOr~
Z L L
b/L El
~~68SL4~
~48LSL4#
ZZl
'~~9lBZb'-~~
~`~i+IZLZbh-~'i
L
b LOL
39969£
~;,~LS89Ed
l
9050£°a~'
~„~a~BB£OEb'`N+i
6
~i 8LZ05
`".=+'mE9ZOS~a+iS 9£L
b E S£l ~°'LbbLb:w~
~l•5LEL4&'i 4/£ LZL
Z1l lZl aCsuSZ9Zb~'~.,~
~~0£SZbg^~~. Z/l LOl
b l L01 ~~7LhL9E~a
8£99£x" b/L E6
£6 ~~ILZO£~
..bSIO£~^+rf L
b 8L
',#.'~94Z05'''~ Z/I SEI ~l'~"~ZOELb_'~r~T, b/l lZl ~=SbEbZ9+l~'!a'~e LOL ~~¢~s8ZS9E 'fi{.',~4'`.~ b/£Z6 :LEOOE~ Z/L 9L
{9ZZOS."e~.i .b/L SEl {=~=0EZL4.~..~ lZl ~"~LE£Z4~-~ b/E 90l ',~T-.~BLb~% Z/L Z6 ~1Z66Z=~ b l 8L
~~bOZO aS '~~`w~
"SOB L05'v oo
-'r+bS t05 ,SEL
b/ b l
Z l bEt ?~G+49S1'Lb`?
-~~+~~Z80L~b~
~y~-3 BOOLbS`F b/E OZl
Z/l OZL
b L OZL s,~-'.~lbZZb e~;
~~+~44 LZ4'~,
`'~L40Z4..~ Z(L 90l
b L Ol
90l ~~~90E9£!
~~8619E
L909EL b/L Z6
Z6
4/£ l6 ~t~. 4096Zw~=3
~L896ZGi%
`69S6ZTT~~ 8L
6 E LL
Z/t LL
-~,. ~~
fi'LZ IOS'iq
L600S~
b/l b£L
bEl
y1'
'~..^~EE6947~u
~.,.~J~LS994&i°~` OZl
b/E fill ~646L6'~aa
~~~ZSB Ibb€~y b/E SOL
„Z/L SOl `9L6SE'`~+
.:998SE~x"d-- Z/L L6
b/L l6 -~ZSb6Z
~
'SEE6Z3~~ ,bll LL
LL
~~L9005xo~i b/E EEl '~~~18L94 Z/t fill =~ESLIb~,~#%: b/L SOl ~SSLSE~~ L6 ~=~8LZ6Zc b/E 9L
~'-:.'Ib£005'i~,3 Z/L £El its<r~~`50L9°b „b/l fill "y;ti~SS9lb."atif SOl ~*~ubb9SE, b/£ O6 *H,'~OOL6Z~ Z/L 9L
.~1000S;~r'g' 4/l E£L ~'~F`'9Z994-.~ 6LL '"~''9SSlb'-~: ±~' 4/E bOI `=-~Z£SSE":`=: Z/L O6 E86s~ 61L 9L
~"99866iJBo; ,EEI ~~OSS9b b/E BLI `".'~-.6LSbib:'~',4n Z/l bOl 4'+?.lZ4SE~~.FS b/l 06 ~x"S988Z w' 9L
~s0E66b ~ b/£ ZEL ~k FZ'L49b'S~~ Z/l BLL 89E 1b>~.,~"' b/l bOl a°,'4~60£S ~^y~~' O6 ~'~94LBZ' 4/£ 9L
Z686b~ , Z/1 ZEL a-'R46E94f~'~^ „b/l 8ll x~6SZlbc`r ~ 40L m -L6lSE ~ b/E 69 =',~e0E9BZa* n Z/l SL
aa,s ES86b~r.Y~*'", 4/l Z£L f~~Sl£94'~~ 9LL ~e- y'l6S LL4at:~i b/E EOl '~'„~980SE Z/l 68 sk~EISBZx,itw blt SL
~91964~y°~ Z£L ~9EZ94r~~` b/E Lll ~x~+6501b ~ Z/L EOl "+£L64Ed~'~ b/l 88 ,~a S6E8Z°t~"~~ SL
ELL66~;~' b/E LEl s~95 L94~..i Z/l LLL 65604~''~-y b/l EOl F~'L984£t~`~' 69 ~='=~LLZBZ~`'I 4/E bL
`~~1EL64~~$ Zil t£l ?SL09b'b "~` bll tll `~~~85804'"iYt~r EOL t_`~k^64LbEi~'...4d" b/E 88 `1`~6SLBZ'l °'!t Z/l 4L
=~~8896b~ b/L LEl "_`9S66Sb ~ ~Lll .1'~''LSLOb~iJ~ ,b/E ZOL ;r'49E96E;i`--~ „Z/l 88 ''''ZbOBZs ,b/L bL
n?~E496ti',-,.-i`'~' LEl f`£l6Sb,~'gcia ,b/E 9ll ~95904~~~ Z/I ZOI !"J+YbZSbE~i.m „b/L 99 3':8~bZ6LZ~'`'7,' bL
,86S6b,1~, ,b/E OEL n~,'ZEBSb~" Z/L 9ll `c.~'bSSObB' b/L ZOL „~~Llbb6~ ~~ 98 4,~w909LZr~y t b/E EL
;Z$Sfibg_a Z/L OEl ~.(,";-64LS4"~'~ b/l 9LL ;;-%£SbOb°%~/ .ZOI td ~86ZbEF,T,=~ ,bl£LB ii~~889LZ~~~?w Z/l EL
SOS6ti'~,,.,~t 4/l 0£L x-L9994 t ~ 9ll `~LSBObc ~i0i° b/E LOl ,+$'.SBIb£~.'~ Z/L L8 ,~~OLSLZ~ ~i~ 4/l £L
'ybLSb64 ~~ OEl ~i~~s,4BSSbl't b/E SII '~BbZOti s<° Z/l lOl +~^SPZLObE ~'~,~"t b/L L8 =ZSbLZ`yl~i „EL
~~90464E';, bl£ 6ZL '~{sh; 00SSb;t.3q~ Z/1 Sll :_2 fr9b10b ~ b/L lOl } ~c8S6EE,~-+M~~ L8 -~`,~6£ELZz "ii'~ ,b/E ZL
~'W''195E64'~t ,Z/L 6ZL I!~.`rLlbSby 4/L 5ll fi^~'ib6004 ;iii LI LOL '3,~'1~56B£E+,~T,ysr.' „b/E 98 M4#t„~,9lZLZ~.~,~! Z/L ZL
zsb190£64t ,b/L 6Zl ,w~F~ZEESb,~~ Sll §?~1466E~`c3~ b/E OOl -z`3'~;IELE_E'.n Z/l 98 .~'~860'LZ_=w.~ ,bll ZL
k ~9SZ6ti`w 6Zl i°si 84_ZSb'{P~ „b/E bIL ~.~`LE86E~~r Z/1001 xLL9EEr~' b/l 98 0869Z:~.~ ,ZL
i~k,bOZ64 ,bl£ 9ZL ~J4Z9lSb~ Z/l blL tb£L6£~y~~ 4/l OOl k.';s€"€bOSE£~~~.~ 99 ~,",`y*~,1989Z~~{ 4/E lL
`~~15164''-.~~ „Z/l 8Zl r?,"V`LLOSbt;~ V/l bll ~ DOE96_E ~~ OOl '~O6E£E~.~u~ b/E SB •-,~ EbL9Z~~ Z/l LL
p,,~~L6064w.y~ ,b/L 8ZL `>H-,iLL664~~s~, ,btl ,~,,. ~~9ZS6Eµ~W'^, 4/E 66 ~*' 9LZ££j~.a-"° ,Z/L SB ~~G,SZ99Z~; ,b/l lL
-4pZ40_66,3„~'t' ,BZI ~~SO64b b/E £Ll ~ ~ZZb6£~,~°"h; Z/l 66 ~`q'~.:,tL9 LE_E~'~ ,V/L S8 '~~LOS9Ze.~~ lL
X98684 4/£ LZL ,8l8bbk `.~ Z/l Eli ~81E6Ej ,b/L 66 ~Y.:'LbOEE S9 '.lx~`ng",68E9Z~~a b/E OL
~0£684f,~~,.~ Z/l LZl ~'~p, eLELb4'<,fkd, b/l £ll '"„~ ELZ6E,y`p~--~„ „66 ~~ZE6ZE~C~Yp b/£ 48 :~,OLZ9Z,~auki ,Z/l OL
~,,£L884,'z „b/l LZl ~`, ~E494b~=_> Ell ~80L6E4i~' bl£ 86 ;~. `t`919Z£, ~ ,ZII b8 '~~ZS l9Zxt,Fr bll OL
~ ^~iSL894F,a~?; LZL ~'+~SSSbb'-Ag+~ 4/E Zll ~'EOO6E~".~7 „Z!l 86 °B EOLZE ~,~=+ 4/l 49 `~+b£09Zs.-~ ,OL
~I~LSL84~~'~ b/E 9Zl _+.~,[9bbb i'Y Z/L Zll „~y968BE aK+, „b/l 86 "BBSZE, °
Y 48 .~ ~ 5L6SZ ,,>, b/E 69
~jL6994~-~ ,Z/L 9Zl .'i`x: BLEbb „b/l Zll -.r*Z6LBEyY` „86 ;b EL9ZE' 4/E E8 :.~'L6LSZ' a,`, Z/l 69
LE984''y 4l L 9ZL +ii*68Z461~ „Zll '~'L899£;~r^7r ,b/E L6 Itl''BSEZE y~z? Z/l E9 ~'_<BL9SZ~ '.`, b/l 69
,~~`°L~LS94,~z.."~{ 9Zl c~:'~OOZbbt,;.~, b/E LLL ;~yLBSBE~~~ Z/L L6 f: rn£bZZE ~+`y 4/L EB ;;.~09SSZe„'a 69
~SISBbt~6 6/E SZL ~=•~OLL4tie` ,Z/t 111 ~=-:~bL48£~~ „4/L L6 y'k~9ZLZ£~ E8 -~~ZbbSZ~s '~ ,b/E 89
'-~NOlltl9,~„
~"~_t~,'}'"y 9NIOtl34J
NOI1Sd10 ~- SNOIlV~J4
.;`.~,,`~*~~~±01= ONIOtl3t3
NOI1Sd10 ~'';`SNOIItl'7~",l'
-g x~~~„~5;^Ti `JN10tl38
NOI1Sd10 `` ~SNOIItl'J"~i
rig,. ~~~Y< ONIOd38
NOI1Sd10 «tSNOIIV`J~y~
`4m a~.'af:.a„°,.`z"~'L"~ `JNIOtl3kf
NOI1Sd10
~lu~l MS ~a~awela ,Z G - uollEJ 000'04 ~o; uey~ uogeagqs~ ~ogsdla NOIltJaOdaO~ S3Xd3X
XERXES® NON-ANCHORED CITY of YELM
RIDGELIKE MIDDLE SCHOOL
WATER AT TANK TOP
~YANCY CALCULATION
JWL 12/16/05
TANK DATA INSTALLATION
NOM CAP (GAL) 50000 TOTAL COVER INCLUDMG SOIL & 3 70
TYPE (SW=I,llW1-2,DWII=3 I TOP SLAB (FT)
DRY=I, WET=2 1 TOP SLAB THICKNESS(IN 000
TANK DIA (FT) 12 TOP SLAB LENGTH (FT) 0 00
•rrrrrrssr rrrrrrrrrrrrrrssrrrrrssasr++rrrrrrar rrrr TOP SLAB WIDTH (FTJ 0 00
PROD STORED (GAL) 0 # OF 30" DIAMETER RISERS 2
SPEC GRAV USED 1 00 # OF 24' DIAMETER RISERS 3
BRINE FILL GAL 0
SAFETY FACTOR
DOWN FORCE/UP FORCE = O 93 .I
TOTAL WEIGHTS
DOWN FORCES
CONCRETE WEIGHT 000 LBS
BACKFILL WEIGH7 408624 12 LBS
TANK WEIGHT 18300 00 LBS
PRODUCT WEIGHT 0 00 LBS
TOTAL DOWN FORCE 426924 12 LBS
UP FORCES
TANK DISP FORCE 456775 IS LBS
TOTAL UP FORCE 456775 15 LBS
WORKSHEET
TANK DATA
SHELL DIAMETER ----- -- - 1 150 FT • ACTUAL CAP (GAL 50293 00
SHELL LENGTH- - ----- -- 62 92 FT r TANK WT (LBS) 18300 00
DOME PROJECTION ----- 2 58 FT r 0 A L (FT) 68 08
MID POINT HEIGHT--- ---- 9 45 FT r NUMBER OF RIBS ~0 00
COLUMN HEIGHT ---- - Ii 20 FT a arrrrrn r::rra rrrrrrrrrrara tssasr r rru rrrrr
RIB VOLUME----- -- --- -- - 4407 00 CU IN DOME A (SQ FT) 44 41
DOME VOL (CU FT) 659 64
REINFORCED CONCRETE VOLUMES (CU FT 1
TOP SLAB 000
TOTAL DRY VOLUME 000
FORCE=VOL X150 LBS 000 LBS
BACKFILL VOLUMES (CU FT )
OVER TANK (DRY)---- -- ---- 3230 94 1074 59 WET
END-WEDGES (DRY)-- -- ---- 157 16 88 98 WET
TOTAL DRY VOLUME 3388 10
TOTAL WET VOLUME 1163 58
FORCE (DRY) = VOL Y 100 LBS 338809 52 LBS
FORCE (WET) = VOL X 60 LBS 69814 60 LBS
BUOYANCY
SHELL VOLUME - - --- -- 6534 93 CUBIC FT
DOME VOLUME----- ----- 659 64 CUBIC FT
RIB VOLUME---- - - ------ 127 52 CUBIC FT
TOTAL VOLUME 7322 09 CUB[C FT
VOL X 7 48 GAL/CU FT 54769 20 GALLONS
FORCE = GAL ~ 8 34 (LBSJGAL) 456775 15 LBS
XERXES® NON-ANCHORED RIDGELINE MIDDLE SCHOOL
BUOYANCY CALCULATION WATER AT TANK TOP YELM COMMUNITY SCHOOL
JWL 12/22/05
TANK DATA INSTALLATION
NOM CAP (GAL) 50000 TOTAL COVER INCLUDING SOIL R
TYPE (SW=1 DWI=2 DWII=3
1
TOP SLAB (FT) 5 80
DRY=1, WET=2 1 TOP SLAB THICKNESS (IN 33 60
TANk DIA (FT) 12 TOP SLAB LENGTH (FT) 70 O8
rrrrrrxrrrrrrrssrxxrrsrrrrrsssrsr tr rr trxxrs rrrstat TOP SLAB WIDTH (FT) 14 00
PROD STORED (GAL) 0 # OF 30" DIAMETER RISERS 2
SPEC GRAV USED 1 00 # OF 24" DIAMETER RISERS 3
BRINE FILL GAL 0
SAFETY FACTOR
DOWN FORCE/UP FORCE = Z 7O I
TOTAL WEIGHTS
DOWN FORCES
CONCRETE WEIGHT 41209000 LBS
BACKFILL WEIGH7 34754369 LBS
TANK WEIGHT 1830000 LBS
PRODUCT WEIGHT 000 LBS
TOTAL DO~i'V FORCE 777933 69 LBS
UP FORCES
TANK DISP FORCE 456775 15 LBS
TOTAL UP FORCE 456775 IS LBS
WORKSHEET
TANK DATA
SHELL DIAMETER---- - -- 1150 FT • ACTUAL CAP (GAL 50293 00
SHELL LENGTH- --- ----- -- 62 92 FT • TANK WT (LBS) 18300 00
DOME PROTECTION-- --- - 2 58 FT • O A L (FT) 68 08
MID POINT HEIGHT---- - 8 75 FT " NUMBER OF RIBS 50 00
COLUMN HEIGHT----- -- 1450 FT + "r ssttt trrrrtrrrsat"""."r rtrtrsss ""trrrrr ss
RIB VOLUME ---- -------- 4407 00 CU IN DOME A (SQ FT) 44 41
DOME VOL (CU FT) 659 64
REINFORCED CONCRETE VOLUMES !CU FT 1
TOP SLAB 2747 27
TOTAL DRY VOLUME 274727
FORCE=VOL X150 LBS 41209000 LBS
BACKFILL VOLUMESlCU FT 1
OVER TANK (DRY)--- -- - 262962 109365 WET
END WEDGES (DRY)----- --- - 131 52 96 84 WET
TOTAL DRY VOLUME 2761 14
TOTAL N'ET VOLUME 1190 49
FORCE (DRY) = VOL X 100 LBS 276114 46 LBS
FOACE (WET) = VOL X 60 LBS 71429 24 LBS
BUOYANCY
SHELL VOLUME------- ----- 6534 93 CUBIC FT
DOME VOLUME-- - ----- 659 64 CUBIC FT
RIB VOLUME--- - -- -- ---- 127 52 CUBIC FT
TOTAL VOLUME 732209 CUBIC FT
VOL X 7 48 GAL/CU FT 54769 20 GALLONS
FORCE = GAL X 8 34 (LBS /GAL) 456775 IS LBS
~A 7D Da
~7~~ MIN FlNISH GRADE ELEV=35733
L
a
0
N
N
n
0
0
N
t7
rp
5
0
J
3
m
D
s
m
N
n
d
L
rT
N
~~
353 33
R LEVEL
2 OF
LOTA110N
VVERT IN=35'.
NOTES
50,000 GALLON STEP TANK I CONCRETE, DRY USE 15016/LF~49056Ib+
SECTION A-A O (pER XERXES)
NTS `
O2 BACKFILL DRY USE 700 Ib/LF
(PER XERXES, WET)
O3 BACKFILL, DRY USE 60 Ib/LF 408 624+76 352 Ib
(PER XERXES WET)
O4 BACKFILL WET USE 60 Ib/LF
* PER APPROVED PLANS AND DETAILS
50,000 GALLON STEP TANK
LONGITUDINAL SECTION
NTS
1
NO DATE BY APP REVISIONS [63 ac insros
"'r ~ Crvll Mumapal Geotechnical Eng~neenng and Planning aw61FD 0' ~g~'~ 50,000 Gallon Step Tdnk
use e. osrz
Ridgeline Junior Ground Water Level At 1 2 F S
Jerome W Morrissette & Associates Inc , P S a~a. o.>E Hi h School
1700 Cooper PI Road 5 W #B 2 Olympia Wa 9A502 1110 Ph 360 352 9456 Fx 360 352 9990 oe¢s~ioTrtn g 031$7~Step Tank Defoll $$T 7 OF 1
JTI JJ
12
RE~EI VED
AUG 1 4 2007
regazd to penod~c mowing to prevent the growth of woody vegetation on the pond bottom or side slopes
Based on visual observations the growth m the pond consisted mainly of alder, which ~s a deciduous tree
that drops its leaves each Fall The leaves would add to the fine soils, nutrients and abundant water to
produce a pond bottom biomat that would seriously reduce infiltration rates Tlns condrt~on may also
have been influenced by localized groundwater mounding beneath the pond due to the concentration of
runoff m the pond
As such, the GEODATA groundwater hazard mapping for this pond area also reflects poor pond
performance due to poor maintenance and localized mounding during an extremely wet period Hence,
the actual local maxrmum shallow groundwater level is most likely somewhere between elevations 345 ft
and 348 ft
Returning to the staining observed m the excavation (elevation 347 4 ft), it is probable that the maximum
excurswn was about 347 ft, given that capillary rise m the soil would result m a slight elevation of upward
wetting front and stain marks m the soil
Recently measured water levels m the athletic field area west of the school shows present water levels to
be about 346 5 ft Given that there is most lilcely some rise m the phreatic surface from the athletic field
are to the STEP Tank azea, a present level of 347 to 347 5 ft would be a reasonable assumption
Finally, measurements were attempted m the Hawks Landing Pond inuned~ately to the north of the STEP
Tank area This pond has remained dry through this period and the pond bottom ~s 348 4 ft
Based on the foregoing, rt is clear that the shallow groundwater level m the STEP Tank area is presently
below 348 4 ft and is most likely about 347 ft This present conditions is occumng during a record
raznfall period as noted above
CONCLUSIONS
Based on the foregoing, ~t is concluded that the approximated maximum shallow groundwater level of
record m the v~cimty of the project site is about 347 ft and is most likely occurring reoccurring at the
present time
Should you have any further questions or require clanfication, kindly contact me at (360)352-9456
Yours very truly,
J W MORRISSETTE & ASSOCIATES INC P S ~;;~;.*
r ~ ~
Edward A Wilts~e, P E ~~~~ui ~ ~J ~
Sr Geotechmcal Engineer/Associate ~ I~ork~f'----~ 3
l:xpls~L::> nJt db
Mr Jim Gibson, PE
January 21, 2005
Page 2 of 4
RE~F~VEp
AUG 14 2007
based on the observed sod conditions that ground water may rise to the mid point of the tank,
elevation 347 4 The Xerxes program is not capable of determinuig the groundwater level at
which the groundwater would produce a factor of safety of 1 2 It is apparent, using the Xerxes
criteria, that there is some level between groundwater at the midpoint of the tank and
groundwater at the top of the tank where the factor of safety would be 1 2 We have more
thoroughly analyzed the probable maximum ground water elevation at the STEP tank site and
find that the maximum ground water elevation rs 347 Please see the attached letter report and
attachments by Ed Wrltsie of our office
We have redesigned the STEP tank location to take advantage of a parking lot island adjacent to
the STEP tank location as shown on the approved plans At this revised location the tank would
have 0 5 feet greater depth of cover than over the previous location while maintaining the tank
inlet invert elevation shown on the approved plans Moreover the cover depth at this revised
location would include the additional weight of a concrete walkway over the top of the tank
This serves to increase the factor of safety for floatation for the STEP tank With the STEP tank
at this revised location we have calculated the ground water level at which the tank would have a
factor of safety for floatatron at 1 2 to 1 Our calculation follows the Xerxes methodology and m
fact uses much of the calculated forces directly from the Xerxes calculations Our calculation
uses the same umt weights for backfill as the Xerxes calculations Also our calculation uses wet
backfill (lighter unit weight) weight where some of the backfill over the top of the tank would be
dry (heavier umt werght) We find that the 1 2 to 1 factor of safety for floatation would occur at a
ground water level of 351 74, according the calculation as described above This is about 4 feet
higher than the maximum groundwater level according to our analysis
We have heard that it has been suggested that the Xerxes warranty would be void if the STEP
tank is installed without anchorage We queried Xerxes and found out that without anchorage,
the Xerxes warranty would be m effect unless the tank floated If the tank floats for whatever
reason, the Xerxes warranty would not be m effect We find that this is m conformance with
your letter to us dated December 16, 2005
In your letter to us we noted that you state that it is not feasible to use a piezometer to co-
ordinate maintenance of the tank to avoid the high ground water season We are only aware of
one maintenance operation that would cause the factor of safety of floatation to be less than 1 2
to one, that would be rf the ground water level were ever to reach elevatron 351 2 during the high
ground water season and the tank were to be pumped empty So long as the ground water level
is below 351 7 that tank could be pumped empty at any time and the factor of safety for
floatation would be greater than 1 2 to 1 One might try to pump the tank empty for one of
several reasons
RECEIVED
AUG 1 4 2~si
Calculate Ground Water Elevatron Reqiured to Produce 1 2 to 1 Factor of Safety for
Floatation at the 50,000 STEP tank at Ridgehne Junior Htgh School
Since the Xerxes program is not able to calculate the ground water level at which the
factor of safety falls to 1 2 to 1, a calculation needs to be made to estimate the level This
calculation should be conservative, that rt to say rt should error of the side of showing a
lower groundwater level than on showing a higher level fora 1 2 factor of safety To
improve the factor of safety, the calculation accounts for locating the tank under an island
m the parking lot to increase the cover over the top of the tank by 0 5 feet to a total cover
of 4 2 feet The 4 2 feet of cover includes a 4 inch flock concrete slab over the tank
Xerxes noted That then method of caicutating the factor of safety for tank floatation is
based on the method outlined m the Petroleum Egmpment Institute Recommended
Practice 100 (PEI/RP 100) This calculation is made m accordance with the
recommended practice fisted m PEURP100 and uses the unit wetghts listed m the Xerxes
calculations and uses the backfill surface area same area above the tank as does the
Xerxes calculation The calculation shows that the 1 2 factor of safety for floatation
would at a ground water level below the top of the tank Thus some amount of the
backfill below the top of the tank would be dry To help keep the calculation
conservative, the unit weight of the backfill below the top of the tank is taken as though
the backfill is wet This calculation uses the Xerxes Dipstick Calibration Chart for tins
tank to calculate the tank displacement volume at the 1 2 factor of safety ground water
level A correction factor is used with the Dipstick Chart volumes to make the displaced
volume of the tank meet or exceed the value listed in the Xerxes floatation calculations
The calculation shows that the 1 2 factor of safety would occur at a groundwater
elevation of 351 71 feet
Step One Determine the weight of the backfill above the tank
Use the weight of 408,624 12 Ib from the Xerxes calculation for
groundwater level at the top of the tank with 3 7 feet of backfill
See Xerxes calculation sheet for "Non-Anchored Water at Tank
Top" dated 12/16/05
Calculate the weight of the 4" concrete slab over the top of the tank Per
Xerxes the allowable size of the slab is 70 08 feat by 14 feet Use 150
lb/ft3 (per Xerxes) to calculate the weight of the slab
70 08' x 14' x 4"/12" per foot x 1501b/ft3 = 49,0561b
See Xerxes calculation sheet for "Non-Anchored Water at Tank
Top" dated 12/22/05
Calculate the weight of the 2" of backfill under the concrete slab Use 100
lb /ft3 (per Xerxes) for dry backfill
70 08' x 14' x 2"/12" per foot x 1001b/ft3 = 16,3521b
Add the weight of the 50,000 gallon tank = 18,300 lb
Sheet 1 of 2
° 7901 XERXES AVENUE SOUTH www xerxescorp cam
MINNEAPOLIS, MN 55431-1288 952-887-1890
CORPORATION
Dlpstlck Callbratlon Chart for 50,000 Gallon - 12' Diameter SW Tank
DIPSTK:K
READING -~ =
-;GALLONS = DIPSTICK
READING
rvGALLONS', DIPSTICK
READING "-- ,` ':
GALLONS DIPSTICK
READING -
` °GALLONS~ DIPSTICK
READING ~'", -
GALLONS
0 0 : 13 3/4 .; -- 2634 27 1!2 ` 7194 41 1/4 12783- , 55 r 18974
1/4 15 ;~~ 14' ~, 2704 _ 273/4 { 7288 411/2 - 12892 551/4 18090
1 /2 29" - 14 1 /4" ` 2775 28" '« 7382 ~ 41 3!4" '~_ 13000 , 55 112" , > 19206
3/4 - 46M
Y 74 1/2' ' 2846 281/4" 7477 42 _ 13109 55 3/4 18322
1' 66~ ~ 143/4 r` 2918 281!2' 7572 421(4' 13218 56' 79439
1 1/4' " :88 15" ' 2990 s 28 3/4" 7867 42 1/2" _ `13327 56 1/4" 19555
11/2' ,112 151/4 -3063 - 29" 7763- 423!4' 13436 56112 19672
1 3/4" 138 15 1/2 3136 29 i/4' 7859 43' 73545` 56 3/4 19788
2 166 ~ 15 3l4 3210 29 1/2 7955 43 1!4" ,. 13655 57 19905
2 1/4 - 795 - 16" -3285- 29 3/4" 8052 43 1/2 13765 57 1/4' 20021 _
2 112" 226 16 114 3360 30" 8149 43 3/4 13875 57 1/2 20138 „
2 3/4 258 16 i/2 3435 30 1/4 8246 44 ~ 13985 57-3/4 20255'
3 292' 163!4' 3511 30112 ,6343 441/4" 74095 58 20372
3 1/4' 327 17' 3588 30 3/4" 8441 44 1/2 14205 58 1/4" , '20489
3 112 363 17 t)4 `3665 37" 8539 44 3/4' ~ 14316 58-1/2" 20606
33/4 400 171/2 3742 311/4 18637 45' 14427 56-3/4 20723
4 439, 173/4" 3620 311/2" 8736 451/4 - 74538 - 59 „ 20840
41/4 479 1B 3899 31 3/4 8835 t 451!2' _14649 591/4 +>20958
4112' 520`
; iB 1/4 3'--,=3978 32 a+_8934 453/4' y14760 591/2" 21075
4 3/4" -t~ 562 r 18 1/'L" '; 4057 ;,+ 32 1/4" 9034 46 14872 59-3/4 > 27192
5 -605. 183/4 ,r 4137 321/2 ~ 9734 46114' -,14983 60' 21370
51/4 _"649
. 19 ``,'4217-
" 323/4 ,9234 ~ 461/2" {-, 15095- 601/4' 21427
5 1 /2 6944 -z 19 1 /4 4298 ~ _
" 33' `" 9334 t + 46 3/4" _ + 15207 ` 60 1 /2 21545
53/4" 1 -~7AD',7 a- 191/2' -o-7 4379_" 331!4" 9435 47 15319 - 60-3/4 21662-
6 787 !~, at 19 3/4 4461 33 1/2" , 9535 " 47 1!4 15431 61 .21780'^
61/4 #,~ 8355,, 20" i :4543 ~ 33 3/4' ;. 9637 471/2 „75544- 61 i/4 ,~+- 21898
67/2 °884 „ 201/4 " 4626 34 -'- 9738 47314 15656" 61 1/2' «. 22D15
63/4' '934" 201/2 ` 4709+ 341/4 - ;9840` 48' 15769 61-3/4 22133 '~
7 „` ~ 885"",, 20 3/4 ~ ~ 4782` 34 1/2 9942 +_ 48 1/4 m 15882 ,' 62' 22251
77/4" ; 1036'- 21 4876 343!4" 4~, 700_44 _ 481/2 1, 15995 621/4 + 22369
71/2" , ~1 D69_ 211/4' ~,,, 4960 35 '~" 10146 483/4" ~, 16108 62112" 22487,,.
73/4 1142- 21 1/2 -'°5045 _ 351/4' n `10249 49 ~r 16221 - 62-3/4 22605
B ,-r ,1196 ,. 21 3/4 ., - 5730 35 112' _ 10352= 49 1/4 ~ x-16334 _ 63 22723
8 i/4 +7251 _- ` 22 5216 35 3/4' 10455 ~ 49 1/2 _ 16448 63-7l4 22847-~-
8 1 /2 1306 - 22 1 /4' o ~ 5302 -. 36 ,10559" 49 3/4 16561 ~ 63 1 /2 , 22959
8 3/4' - 1362 ~ 22 1 /2 5388 36 1l4" +~ 10662 50 _ 16675 ~-
{ 63 3!4 + ~ 23077
9' °1420 223/4" 5475 361/2 10766 501/4' 16789 64' 23195
u
91/4 1477 23 5562 36314" 10670 50112 _ `16903 64114 ,
23313
9 1 /2" 1536 23 1 /4 5649 37' 10975 50 3/4 17017 64 1 /2 23431
93/4 1595 231!2' 35787 37114 14079 ~ 55' 17131 64-314` 23549
10' - 1655 23 3/4 5826 37 1/2 11184 51 1/4 77246 65 ~ 23667,
10 l/4' - .. 1716 24' • 5914 3 3f4 11289 51 1 2 17360`: 65 1 4 23786
10 1!2' 7777. s 6003 n 3 11395 + 5 3 4 ' 17475
T 65-1 2 23904
10 3 4 1 39 7 i 24 2 ~ 60 3 + 1500 , , 1758 - - 4022
11 1902+_ ~ ~ =1 X61 3 ~ yfi 11606 7770 4140 '
5
~ r, - _
~ ~
i
12' -+2160 253/4 6545 397/2 12031 531/4 18165 67 .24674
121(4" - 2226 , 26 6637 39 ,12138- 5 1 2 _ 18280 67-1 4 24732
12 1/2 229 6729 72245 "1839 , 24850
12 3 4 - 2359 6821 4 12352 i 1851 ~ 7 24969
13 _ 2427 26 3/4 6914 40 1/2 12460 54 i!4" 78627 68 25087
131/4 2495 2 7007 403/4 12568 541/2 18742 68-1/4' ,25205
13 1 /2 2564 27 1 4 7100 41 12675 54 3 4 18858 68 1 2 25324
CAUTION Do not use the Callbratlon Chart without reviewing Xerzes° Installation Manual and Operating Guidelines, and Xerzes° applicable
Limited Wartanty, copies of which are in the literature packet delivered to the site, or available at www xerxescarp com
XERXES CORPORATION Dlpstlck Callbratlon Chart for 50,000 Gallon - 12' Diameter SW Tank
DIPSTICK
READING -
~~ ,GALLONS DIPSTICK
READING
`GALLONS DIPSTICK
READING
GALLONS DIP571CK
READING ~
GALLONS DIPSTICK
READING - r~'
GALLONS
fib 3(4' r 25442 83' .~ 32128 +, 97 11A 38474 111 1 i2 ., ~ 4411 D 125 3/4' ~ 48515 '
69' 25560` 831/4' 32243 971/2' 38587 1113/4 44200' 126" ...48577
691/4" 25679 831/2 ' 32358 973/4" 38687 112" 44289 1261/4 48637, _~
69 1/2 25797, 83 314' 32473` 98" 38792 112 V4 _44378 -" 126 1/2' ."48697
693/4" 25915 84' 32588 981/4 ' 38898 1721/2" 44467 1263/4 ` 48757,
70 26034 841/4 32703 981/2 - 39003 1123/4 '°44555 127 48815
70 1l4' 26152 84 112" 32818, - 98 314 39108„ ' 113 44643 127 1/4" 48873
701/2 26270 643/4 32932" 99 "39213+ 1131/4" 44737 1271/2 °46930
70 374' --'26389 , 85 "'33047_' 99 1/4' i 39378 ` - 773 1/2" - 44878 127 3/4" 48986
71 -_ 26507_ 851/4' `33187,.% 991/2 ,. 39422°~s 1133/4 44905, 128 r 49042
71 1/4' ' 26625~ -
Y 851/2 _33276 _ 993/4 39526 ~~ 114 ~ 44991 1281/4' 49097 `
71 1 /2 _ 26743,` ~ 85 3/4" 33390 100 39630 ` 114 1 /4" ` 45077 128 1/2' 49151
71 3/4' • 26861- 86 '' 33504 100 1/4 ~ 39734 _ 114 1/2" .45162 128 3/4 49204
72 26980 ' 86 1/4" - 133617 +-_ 700 1/2" 39837 114 3/4 45248 129' 49256
721/4" _~ 27096" 867/2 ! 33731- 1003/4 -39941 715' 45332 1291!4 „49308;
721/2 27216 " 863/4" _" 33845 101' F 40044 1751/4" 45417 1291/2' ,r 49358
72 3/4" 27334 87 33958 101 1/4 40146 175 1/2 - 45500 - 129 3/4 49408 ~
73 27452 , 87 1/4' 34072 101 1/2" __ 40249 175 3/4' 45584 130 49457
73 1/4 27570- ' 87 !/2 ,34785 101 3/4 40351 116' 45667 130 i/4' 49505
73 1/2 , 27688 _ ' 87 3/4 ' 34298 102 40453 ., 116 1/4' 45749 130 1/2 ,~ 49552
73 3/4' 27806 BB 34411 " 102 fl4 '40554. N6112' 45832 - 130 314' -i 49598
74' 27924 88 1/4" 34524 ' 102 1!2 40656, 176 3/4 , 45913 131 49643+ -
74 1 /4 28042 88 f /2' 34636 102 3/4 , 40757 +-^ 177 _,", 45995 131 1 /4 ,.49688 `_
74112 's 28159 883/4 "34749 103 40858 177114' 46075 * 731112' x49737, `
74 3/4 28277 89 34661 103 1/4 -40959 117 1/2 _.46156 137 3/4 49773
75 28395 891/4 i 34973 1031/2' _41059, , 1173/4' 46236 _ 132 ~y 49814
751/4" 28513 891/2 _ 35086 1033/4' 41159 118 ~ .46315; 1321/4' ,-X49853=
75 1/2 28630 - 69 3/4' 35197 104 41259 118 1/4 `x,46394- 132 1/2' 49892 ;
75 3/4 , 26748 . ~ 90 , 35309 f 04 1/4 41358 718 1/2 46472 132 3/4 ,49930" -
76 -^28865 901/4 _35421 1041/2 „41457 1183/4 ',`46550 133' ,.49966 4
761/4" '28983 r
~ 901/2 ,,y35532 104 3/4' _41556 _ 119" =,46628 _ 133 1/4 `50001 ,
76 1/2" „
~29100 _ 90 3/4 s ~' 35644 105' -41655 119 1/4 =46705 133 1/2 + ~ 50034
76 3/4' + 29218 '" 91 "_ 35755 1051/4' ~ 41753 179 1/2 46781 133 3/4' 50067,
~
77 29335,,,_ 97 1/4 _35866 1051/2' - `41852 7793/4 346857 734' 50097 '
771/0. ~;*29452z 911/2 Lr,t=35976 1053/4 41949-' 120" 46933 1341/4 50127
77 i/2 K+29569" 91 3/4 _k„ 3608L'r 106 "42047 120 7/4 -' 47008° 134 1/2 '50154.~E
773/4 '29687 _
n 92 36198 10614 42144 1201/2 - 47082 13434 _,50180;+i
78 ~.- 298043 921/4 +36308 1061/2 42241 1203/4 - 47_156 x 135' -x`50204"
•
78 1/4' * ~ 29921% - 92 1/2 + ,36418 706 3/4 a 42337 727 .47230 7 1/4 50226
-
781/2 30037+~ 923/4 '~~. 36528 107' 42434, ~ 1211/4 473021 1351/2 50246
78 3/4 30154 ,, 93' 36638 107 1 4 42530 - 121 1!2 :47375 135 3!4 ' * 50263
79 _ ,30278 931/4 ~ 36747- ~ 1071/2' ~„ 42625 ~ 121 3/4 47447 13 50278~
79 , , "s 30388 ^ 93 1 /2 ~ 36857 i 07 3!4 ~ 42721 122 47_518; 136 1 /4 _ w5_0288 , -
7 ~ 30504 3 36966 ~ tQ8 42816-- 1221/4 47589 1 7!2 50293
+ 30621 ~ 37075, 42910 47659
0 30737
``' 37184 43005 47728
30854, 37292 43099 r 47797
309 0 37401. 43192 7865
0 750 3286 793
31202 37617 43379 48000
1 31318 9 1 2 37725 10934 43471 1 4 48067
31434 4 _37833 43564 48133
31550 37940 43655 48198
31666 38047 43747 48263
82 1 4 31782 6 7 2 38154 10 3 4 43838 1 5 48327
821 2 31897 9fi 34 F 38261' 111 43929 1 51/4 48390^
32013 38368 44020 48453 x125050 07/OSfbf
XERXES® NON-ANCHORED CITY OF YELM
RIDGELIKE MIDDLE SCH OOL
WATER AT TANK TOP
iYANCY CALCULATION
- - JWL 12/16/05
TANK DATA INSTALLATION
NOM CAP (GAL) 50000 TOTAL COVER INCLUDING SOIL & 3 70
DWI=2,DWII=3
TYPE (SW=I 1 TOP SLAB (FT)
,
DRY=I, WET=2 1 TOP SLAB THICKNESS (IN 0 00
TANK DIA (FT) 12 TOP SLAB LENGTH (FT) 0 00
tsssrt sasrrsrtrrtt:rsrssrrrrttrrr++rrrrasarrssrrsr TOP SLAB WIDTH (FT) 0 00
PROD STORED (GAL) 0 q OF 30 DIAMETER RISERS 2
SPEC GRAY USED 1 00 N OF 24" DIAMETER RISERS 3
BRINE FILL GAL 0
SAFETY FACTOR
DOWN FORCE/1JP FORCE = Q93 • ]
TOTAL WEIGHTS
DOWN FORCES
CONCRETE WEIGHT 000 LBS
BACKFILL WEIGH7 408624 12 LB5
TANK WEIGHT 18300 00 LBS
PRODUCT WEIGHT 0 00 LBS
TOTAL DOWN FORCE 426924 I2 LBS
UP FORCES
TANK DISP FORCE 456775 15 LBS
TOTAL UP FORCE 456775 15 LBS
WORKSHEET
TANK DATA
SHELL DIAMETER- - --- I 1 50 FC " ACTUAL CAP (GAL 50293 DO
SHELL LENGTH ------------- 62 92 FT ' TANK WT (I,BS) 18300 00
DOME PR07ECTION - --- 2 58 FT " O A L (FT) 68 08
MID POINT HEIGHT--------- 9 45 FT ' NUMBER OF RIBS 50 00
COLUMN HEIGHT----------- 1520 FT r rrrssasrssr raarrttttrtrr:+araa sssasarr rtrrr
RIB VOLUME------- ----- -- 4407 00 CU IN DOME A (SQ FT) 44 41
DOME VOL (CU FT) 659 64
REINFORCED CONCRETE VOLUMES (CU FT )
TOP SLAB 000
TOTAL DRY VOLUME 0 00
FORCE = VOL X150 LBS 0 00 LBS
BACKFILL VOLUMES ICU FT I
OVER TANK (DRY)- --- - ---- 3230 94 1074 59 WET
END-WEDGES (DRY)- -- -- 157 16 88 98 WET
TOTAL DRY VOLUME 3388 ]0
TOTAL WET VOLUME 1163 58
FORCE (DRY) = VOL X 100 LBS 338809 52 LBS
FORCE (WET) = VOL X 60 LBS 69814 60 LBS
BUOYANCY
SHELL VOLUME- ------- --- 6534 93 CUBIC FT
DOME V OLUME------- ----- 659 64 CUBIC FT
RIB VOLUME --- - --- 127 52 CUBIC FT
TOTAL VOLUME 7322 09 CUBIC FT
VOL X 7 48 GAL/CU FT 54769 20 GALLONS
FORCE = GAL X 8 34 (LBSJGAL) 456775 15 LBS
XERXES® NON-ANCHORED RIDGELINE MIDDLE SCHOOL
BUOYANCY CALCULATION WATER AT TANK TOP YELM COMMUNITY SCHOOL
JWL 12/22/05
TANK DATA INSTALLATION
NOM CAP (GAL } 50000 TOTAL COVER INCLUDING SOIL &
TYPE (SW=I,DWI=2,DWII=3
1
TOP SLAB (F"F) 5 80
DRY=1, WET=2 1 TOP SLAB THICKNESS (IN 33 60
TANK DIA (FT) 12 TOP SLAB LENGTH (FT) 70 08
##ww}####xx#xtx#xxw####w#x######wr###w#r##xrxx}wxx TOP SLAB WIDTH (F17 1400
PROD STORED (GAL) 0 # OF 30' DIAMETER RISERS 2
SPEC GRA V USED 1 00 # OF 24" DIAMETER RISERS 3
BRINE FILL GAL 0
SAFETY FACTOR
DOWN FORCE/UP FORCE = 1.70 I
TOTAL WEIGHTS
DOWN FORCES
CONCRETE WEIGHT 41209000 LBS
BACKFILL WEIGHT 347543 69 LBS
TANK WEIGHT 1830000 LBS
PRODUCT WEIGHT 000 LBS
TOTAL DOWN FORCE 777933 69 LBS
UP FORCES
TANK DISP FORCE 456775 IS LHS
TOTAL UP FORCE 456775 15 LBS
WORKSHEET
TANK DATA
STIFLE DIAMETER-- -- --- ll 50 FT + ACTUAL CAP (GAL 50293 00
SHELL LENGTH------- ------ 62 92 FT + TANK WT (LBS) 18300 00
DOME PROTECTION --- - -- 2 58 FT + O A L (FT) 68 OS
MID POINT HEIGHT-- -- ---- 8 75 FT * NUMBER OF RIBS 50 00
COLUMN HEIGIIT--------- - 1450 FT + +++++*+++**++*+###«#w#ww#####xxxs s#x#w#w+#w
RIB VOLUME--------------- - 4407 00 CU IN DOME A (SQ FT) 44 41
DOME VOL (CU FT) 659 64
REINFORCED CONCRETE VOLUMES !CU FT 1
TOP SLAB 274727
TOTAL DRY VOLUME 2747 27
FORCE = VOL X]50 LBS 412090 00 LBS
BACKFILL VOLUMES (CU FT I
0 VER TANK (DRY)- ----- ----- 2629 62 1093 65 WET
END WEDGES (DRY) -- ------ 131 52 96 84 WET
TOTAL DRY VOLUME 2761 14
TOTAL WET VOLUME 1]9049
FO RCE (DRY) = VOL X 100 LBS 276114 46 LBS
FORCE (WET) = VOL X 60 LBS 71429 24 LBS
BUOYANCY
SHELL VOLUME------ ------ 6534 93 CUBIC FT
DOME VOLUME- - - - -- 659 64 CUBIC FT
RH3 VOLUME---------------- 127 52 CUB[C FT
TOTAL VOLUME 7322 09 CUBIC FT
VOL X 7 48 GAL/CU FT 54769 20 GALLONS
FORCE = GAL X S 34 (I,BS /GAL) 456775 15 LBS
~A 7D Da
MIN FINISH GRADE ELEV =357 33
v \ 1
G
N
N
0
0
m
0
T
3
a
m
m
s
m
F-
n
L
353 33
R LEVEL
2 OF
LOTATION
UVERT IN=351
NOTES
50,000 GALLON STEP TANK
SECTION A-A O1 CONCRETE DRY USE 15016/LF~4g05616+
(PER XERXES)
NTS
O2 BACKFILL DRY USE 100 Ib/LF
(PER XERXES, WET)
O3 BACKFILL, DRY USE 60 Ib/LF 408 fi24+16 352 Ib
(PER XERXES WET)
O4 BACKFILL WET USE 60 Ib/LF
*PER APPROVED PLANS AND DETAILS
50,000 GALLON STEP TANK
LONGITUDINAL SECTION
NTS
RECEIVED
AUG 1 4 2007
1
IIL VIJI VIVA i.. i OE 1/I8/C6
~" '~~~~ Civil Mun~cipal•Geotechmcal Engmeenng and Planning mam BY ne °~"" 50,000 GdOn Step Tdnk
~.°°°. o.,E Ridgeline Junior
Jerome W Morrlssette & Associates Inc , P S Hi h School Ground Water Level At 1 2 F S
cxca® ar °n1E
1700 Cooper Pt Road S W #8 2 Olympia Wa 98502 7110 Ph 360 352 9456 Fx 360 352 9990 °ex r~ionm 03757~Sfep Tank Defod SHT 1 OF 1
i _. i
RECEIVED
AU614 1007
regazd to penod~c mowing to prevent the growth of woody vegetation on the pond bottom or side slopes
Based on visual observations the growth m the pond consisted mainly of alder, which ~s a deciduous tree
that drops its leaves each Fall The leaves would add to the fine soils, nutrients and abundant water to
produce a pond bottom bromat that would seriously reduce urfiltratron rates This condrtion may also
have been influenced by localized groundwater mounding beneath the pond due to the concentration of
runoff m the pond
As such, the GEODATA groundwater hazazd mapping for thrs pond azea also reflects poor pond
performance due to poor maintenance and localized mounding during an extremely wet period Hence,
the actual local maxunum shallow groundwater level rs most likely somewhere between elevations 345 ft
and 348 ft
Retunung to the staining observed in the excavation (elevation 347 4 ft), it is probable that the maximum
excursron was about 347 ft, given that capillary rise m the soil would result m a slight elevatron of upward
wetting front and stain mazks m the soil
Recently measured water levels m the athletic field azea west of the school shows present water levels to
be about 346 5 ft Given that there is most likely some rise m the phreahc surface from the athletic field
are to the STEP Tank area, a present level of 347 to 347 5 ft would be a reasonable assumption
Finally, measurements were attempted m the Hawks Landing Pond munedrately to the north of the STEP
Tank area This pond has remained dry through this period and the pond bottom ~s 348 4 ft
Based on the foregoing, it ~s clear that the shallow groundwater level m the STEP Tank azea is presently
below 348 4 ft and is most likely about 347 ft This present conditions is occumng during a record
rainfall period as noted above
CONCLUSIONS
Based on the foregoing, it is concluded that the approximated maxrmum shallow groundwater level of
record m the vicinity of the project site is about 347 ft and is most likely occurnng reoccumng at the
present tune
Should you have any further questions or require clarification, kindly contact me at (360)352-9456
Yours very truly,
~rP M '9 r
~~ i~ ~ iJi
J W MORRISSETTE & ASSOCIATES INC P S cf'rf',~°~ w;,A'~~"t°
~~ ~s ~~,. ~'~ ~U ~I
~.ca~( YJ ~.~U I.~f~ ~° ~ ~ ,1tV
~~ ~,
Edwazd A Wiltsie, P E ~ ~,
Sr Geotechmcal Engineer/Associate ~ ,~A~ ~ ,
r_
e„O.c. c
~t§i~~:, ~9 it
'a
Cr
e~
August 15, 2006
Yelm Community District
Erling Birkland
PO Box 476
Yelm, WA 98597
City of Yelm
Community Development Department
105 Yelm Auenue West
P O Box 479
Yelm, WA 98597
RE Ridgelme Junior High School
Irr~gatron Consultant Fees
Mr Birkland
We have received the following invoice and charges from Skdlings and Connolly Inc
These fees were incurred as a result of the design process for Ridgeline Reclaimed
Water Irrigation system
Please remit the fees directly to Skillings and Connolly The total fees are $1,000 25
If you have any additional questions or comments please do not hesdate to ca44 or
contact me at ~img@ci yelm wa us
Community Development Department
Respectfully,
c~ ~ ~~-
im Gibson P E
Development Revlew Engineer
cc
enc
(360) 458-8438
(360) 458-3794 FAX
www ca yelm wa as
SKILLINGS
~ ~ ~ cONfYOLLY
Apr+l 12, 2006
#02007-18
Ms Stephanie Ray
C+ty of Yelm
PO Box 479
Yelm, WA 98597
RE Progress Letter - Ridge Ltne School Irrigation -Task 18
Dear Stephan+e
The work assoc+ated with this +nvo+ce Is as follows
• We began work+ng up pred+ct+ons of supply, demand, and storage requirements
for the reclaimed water system, rev+sed the model for a different water+ng cycle at
R+dge L+ne, drafted a letter to the parties concerned
,9 We answered a quest+on from the landscape arch+tect regard+ng the pressure
short falls at M+II Pond and R+dge Line
• We preformed a study on several water+ng scenarios for M+II Pond and R+dge
0 L+ne
If you have any quest+ons, please call me at 491-3399
S+ncerely,
SKILLINGS CONNOLLY, INC
Th~ Sk+ihngs, PE
Princ+pal
ENGINEERING • SURVEYING • ENVIRONMENTAL • REflL ESTBTE SERVICES
PO Oox 5080 Lacy Wa:hington 98509
360 491-3399 Fax 360 491-3857
www sk~Ilings com
_ ~ SKILLINGS ~=~~' -
CONK®LLY
Invoke Number 2012
April O1, 2006
Invoice
To Gty of Yelm
PO Box 479
Yelm, WA 98597
Prolect 02007-18 Yelm - Ridge Lme School Imganon -Task 18
Manager Tom Skilhngs
Professlonal Sernces for the Penod 2/26/2006 [0 3/25/2006
Bdlmg Group 00001
Yelm - Ridge Lme School Imganon -Task 18
Professlonal Services
Destge Servtces Bill Hours Bdl Rate Charee
Engineer 4 25 62 42 265 30
Senior Management 4 00 183 74 734 95
i ~ Design Servtces Total 8 25 $1,000 25
Professional Servtces Totals $1,000 25
Prolect Totals:
*** Totai Prolect Invoice Amount $1,000 25
Aged Receivables
Current 31-60 Davs 61-90 Davs 91-120 Davs > 120 Davs
$1,000 25 $0 00 $0 00 $0 00 $0 00
AR mva~ces are due upon rere~pG A lase charge of / 5 % wJ/ be added ra any unpaid balance after 1S days
Approved for Payment
Dffie
'• Prolect
'6 BARS ` _
BARS '
l
ENGINEERING • SURVEYING • ENVIRONMENTAL • REAL ESTATE SERVICES
PO Box 5080 Lacey Washington 98509
36A491-J399 Fax 360-491 3857
www sklllings coin
Sktllmgs Connolly, Inc
Pn $ox 5080
Lacey, wA 9sso9 ~ ~ ~ ~ 9 ~ E
Phone 360-491-3399
Fax 360-491-3857 ..... 1 e n..n,
Statement of Account pe~emao,~~„~
For Clty of Yelm
PO Box 479
Yelm, WA 98597
02007-18 Yelm - Rldge Line School Imgatlon -Task 18
00001 Yelm Ridge Lme School Imgatlon Task 18
Invoice Doe
Imome Tvee Dale ate
2012 lnvo~ce 4/1/2006 4/1/2006
Crty of Yelm - Perlod Ending 8/10/2006
Invoce Payments/ ~Curu~em
Amount D~scomt CreditsBetamers ~ a ncs
Repott Totals $1 000 25 $0 00 $0 00 cSi-ODO" 2i~
Accounts Receivable Aging Summary
$ 0 00
Current 31 60 Davs 61 90 Dass 91 120 DavsV-F30~
$0 00 $0 00 $0 00 $0 00 eSS~S
PAST D U E
Approved for P<^,yment
Prolec-~----"---date
~_~ ~"-a
--------_ ~~ ~.ar~S ~
August 10, 2006
O The stormwater maintenance agreement needs to be recorded
^O Construction as-bunts need to be submitted and approved
Yelm High School ~~~ Z ~ C~J
Sewer System ~ ~; gy~,t,Q- ~,~'~,
~ Iniet baffles must be installed in tanks A and B (32" "down pipe" off the "T" and an
"up pipe" into the riser _
O All users in tanks A and B need to have a smooth top edge to ensure a good seal
with the user lid
O The floats in tanks A and B are not positioned correctly on the float trees
The .. or.+r. n MnLn D -.nrl Q uidhm 4he I hr.v m fhe v nIM ..oorl +n hc.
mnrlo ~ .n+h he.+i nhr nL n eni.~rc -+nrl meRerl n~mnle4el..
i rp.ccc-rr
The Public Works Department has researched your position that this requirement
is not ~n compliance with the National Electric Code and has waivect\the
requirement
x^ Then service disconnects for tanks A and B handles in tanks A and B must be
lockable and able to accept a City of Yelm lock
The service disconnects for tanks A and B need to have one additional_fuse
Se~'°/ mstalled to separate the three circuits (2 pump and 1 control arcuit)
x^ All mainline gate valves in the sewer mam lines must have traffic bearing rings
and covers and a concrete pad per the Yelm Development Guidelines
O The clean-out cap m the side sewer for building 300 could not be located (Sta
4+76 00)
~ The valve box containing the service line ball valve and service line for the tank
at building 400 must have toning wire brought to the surface
~ ^ The tank originally proposed to be retrofitted for use for building 400 did not pass
SR -' the leak test and needs to be replaced
~ C~The 10,000 gallon tank serving buddmgs 300 and 500 needs additional bollards
placed to prevent vehicles from parking on the tank or the lid, as it is non-traffic
t ~., bearing ~~ l-y>r
pl`"u G.t ~ The fencing was apparently removed from this area and the STEP lids have
~(° been broken Bollards (not fenang or ecology blocks) need to be mstalled
around the tank to protect it from traffic The broken lid must be repaired and all
damage repaired
p~ ^ A punctured butt connector needs to be replaced m the"S" box m the user ~a,~~
fw
t ^ A wire nut was used to "make up" the connections m the "J" box m the user n~r~ s
/ w~ Only heat shank butt connectors are allowed
E Page 4 of 6
b~~t~
J~ ^ The remote disconnect switch must be drilled to allow placement of a city
~~ padlock when the switch is in the "on" position ~ ~~lc~ vaa.~ ,,_ ~...~ ~ u ~ -/ y 2
tars r ;as-~a<,re sennest~o,=.s-~;,eee~ ^„ ,., «P--.,.n =::. ~=.ats~„ese~;.Te~ats r~eed~e
The Public Works Department has researched your position that this requirement
is not in compliance with the National Electric Code and has waived the
requirement
Note The four comments above apply to the 1500 Gallon STEP Tank at Auto
Shop, which was not installed at the time of the first or second inspections in
August 2006 and May of 2007
General Comments
~ Landscaping is not completed at the 93rd Street entrance, and along the north
property line
t7 If the portables have been connected to water and sewer, plans need to be
submitted and inspections completed
t7 The sidewalks do not meet ADA requirements as they do not have truncated
domes
The sidewalks do NOT have truncated domes as noted by the contractor, they
are stamped in a diamond pattern Truncated domes were required as part of
the civil plans approved by the City (see attached copy from Sheet C2 11 of
approved construction plans and referenced standard specifications)
Because the requirement for truncated domes was placed on the approved civil
plans by the School Distracts engineer, the City wtll require the stamped concrete
to be placed at this time However, the Distract should be aware that it changed a
requirement of the civtl engineering plans and created a situation that does not
meet the current standards of the Americans with Disabilities Act The City
understands that the Distract will take take responsibility for these decisions
~ The old Yelm High School sign on Yelm Avenue West (SR 510) must be
removed
t7 The stormwater swale along Yelm Avenue West (SR 510) needs to be cleaned of
debris
t7 The required ADA stall has been painted over and does not meet ADA
standards
~ Required frontage improvements along Yelm Avenue West (SR 510) will be
completed through the Districts participation in the Killion Road Local
Improvement Distract
Page 5 of 6
~ The nght-of-way required for frontage improvements as part of the LID needs to
be dedicated to the City The City will provide the required deeds and
dedications for the right of way
Documentation
D The dedication of sewer and water lines and appurtenances has not been
submitted
O Easements for sewer and water systems have not been provided
O The stormwater maintenance agreement needs to be recorded
D Construction as-bunts need to be submitted and approved
When all required improvements are complete, please contact Steve Harrington of the
Community Development Department at 458-8423 to schedule a re-inspection
unity Development Department
Shelly Badger, City Administrator
Tim Peterson, Public Works Director
Jon Yanasak, Re-use System Manager
Jim Gibson, Development Review Engineer
Alan Burke, Yelm Community Schools Supenntendent
Page 6 of 6
October 15, 2007
Erlmg Birkland, Facilities Director
Yelm Community Schools
PO Box 476
Yelm, WA 98597
Community Development Department
105 Yelm Avenue West
P O Box 479
Yelm, WA 98597
RE Ridgeline Junior High School -Updated Punchlist Items
Yelm High School -Updated Punchlist
Dear Rocky
This letter is updates the status of the remaining punchlist items at Ridgeline Junior
High School and Yelm High School and as a reminder that the Temporary certificates of
occupancy expire at the end of October
Enclosed please fmd the status of the punchlist items provided the Distract in August of
2006 and updated on September 11, 2007, for both Ridgeline Jumor High and Yelm
High School The temporary Certificates of Occupancy issued prior to the start of
school for these protects expire on October 31, 2007 The remaining items need to be
resolved prior to issuance of any further occupancy permits for either protect, except as
noted below
Items that have been completed, inspected, and approved by the City are marked as ^O ,
items that have been deferred are marked as D and items that are incomplete and must
be addressed prior to October 315 are marked with ^
Ridgelme Jumor High Schoo!
Water System
O The water valve box located at the Carter Street entrance has a sewer lid on it,
which needs to be replaced with a water lid
~ The valve box for the fire hydrant at station 5+82 89 needs to be cleaned out
x^ The valve box at station 7+17 05 needs to be cleaned out
D The fire hydrant height, Sta 3+00 00 and next to the domestic water meter,
needs to be verified that it will not be too low after landscaping has been
installed
(360) 958-8438
(360) 958-3144 FAX
www ec yelm wa ua
O The fire hydrant at station 13+12 45 needs to have bollards installed to protect it
from damage
^D The bollards need to be installed around the air release
^D The air release needs to be raised to final grade of the landscape
^D The existing Mill Pond School fire hydrant located in back by the play ground
needs to be modified, as it is too tall now that the grading has been completed
and is unusable for fire protection purposes and can not be serviced by the
Public Works Department
^D Mill Pond School requires a Reduced Pressure Backflow Assembly
O The City recommends that you connect the Reduced Pressure Backflow hot box
to an electrical source
Sewer System
O The STEP sewer arcuit breakers inside the building are not labeled as required
to allow service personnel to disconnect the power
^ One of the gravity sewer manholes before the step tank remains to be vacuum
tested
O Ground water wells (pyzometers) were required as part of the solution to high
ground water and the STEP tank, but have yet to be installed
This requirement was resanded by the Community Development Department
^O Both 110 volt wiring and low voltage wiring (control wires) were installed in the
same conduit, and must be separated in individual conduits While this appears
to have been corrected, there is no indication (such as asphalt/concrete patches)
that another conduit installed The contractor will have to provide evidence that
another conduit was installed
x^ The pumps in the STEP tanks have run continuously shortly after the start of
School and wdl now have to be replaced prior acceptance by the City
^ The floats are not operating according to specifications
~ The alternating relay within the pump control panel is not working correctly or is
not wired correctly
O Both 110 volt and control wires are protruding out of the conduts and exposed
next to the tank riser
General Comments
Q The storm pond and swales need to have debris removed
To be completed at the time of football field completion
Q The slopes of the storm pond need to be hydro-seeded
To be completed at the time of football field completion)
Page 2 of 6
~ The landscaping and fenang is not complete around south end of the ball fields
To be completed at the time of football field completion
^ The maintenance driveway entrance to south ball fields from parking lot is not
complete and the sidewalk at this location is not complete
While the contractor notes that this improvement was part of an alternate bid, the
civil plans approved by the City (see attached copy of page from approved
construction plans) clearly show the sidewalk and driveway approach being part
of the base bid The City approved the plans based on this information
O The planter steps along the southeast fencing between the School and the
homes 107th loop need to be cleaned
D The area between the property Ifne fence and baseball field needs to be
reseeded
~ The area at the north east property Ime needs to be hydro-seeded
O A portion of fencing for the storm pond in the Hawks Landing subdivision, located
at the north entrance to the school, needs to be replaced
O Property owners in the Hawks Landing Subdivision, located at the north property
line, have noted that there is a gap at the bottom of the fence and the ground and
that there is construction debris graded material on their property from the School
construction
^ The parking lot striping does not match the approved plans and appears to
contain more compact spaces than allowed
While the contractor notes that the existing striping meets City requirements, this
is not the case The civil plans approved by the City show a total of 196 spaces,
with 46 compact stalls A total of 49 (25%) maybe compact stalls per City Code,
while there are at least 68 compact stalls on the site
~ Required improvements to SR 507 must be completed no later than July 31,
2007
Prior to October 31St, 2007, the District shall provide copies of WSDOT approved
Plans for Approval and construction plans to the City, along with a schedule
which includes bidding the protect, construction, and completion of construction
by July 14, 2007
Documentation
D The deferral agreement for frontage improvements along Mill Road has not been
submitted
O The dedication of sewer and water lines and appurtenances has not been
submitted
D Easements for sewer and water systems have not been provided
Page 3 of 6
~fF'ir ,!!CS kj~_, Tyr rw~Z~}tV~q I(,a L.~ ..- -- { ---_/''-_ ~~- v ~_ ~ _ _~
~UC.C.~.l/Kx0 1~~~ ~+N^h¢. ~.~fJ.). \~ Ca. ~..h C~~-c,r t~ SC+v 17a.~~_1`~~TU.1~,;,~_
u+-~ ~t_~~?.+~1, W lYitnltii~ \~L~ U V . ~,r ~i3.L/'--r ~:•~~-.) ~z.(..~;.,~,~.~~" _~
Wa,..~Se\,1t,..~ _Shrih~ ~k~l"'.c,,..v_~2~,~or-5__~~ ~txnv~cXC~~~~~X_.--
~'ol/J?Y _ OT ~n~.` ~~j~L f~I~S ~17.. ~rt II,.v~ ~Or _ L.,c„I.L ___.. _
Ctty of Yelm Sewer Department
08/3/06
Re Punch list Yelm Hlgh School and Rtdgelme School
Yelm H>Igh School
These rtems apply to both Tank A and Tank B
~~ i -~
y 1 /The wire connecttons wrthm th~ J box m the vaults need to be made up wrth heat shnuk
~/ onnectors and melted completely--
~The service dtsconnects need to have 1 additional fuse installed to separate the 3 cucuits
b (2 pump and I control c~rcwt)
1500 gal STEP tank for Auto Shop at Htgh School -
A nctured uti connector needs to be replaced m the " bo m the user
ire"nut wa used to "make up" the connections m the J" ox m the riser Only heat
nk butt~co ectors are allowed
~3 e remote di connect swttch must be drtlled to allow placement of a city padlock when
th switch is n the "on" positron
the~explosto proof "J" box used for the pump wires wrthm the the pump vault of the
~.l tarill~,c~`, has w e connections "made up"wrth wire nuts These wire nuts need to be replaced
wrtri~heat 1 rink butt connectors
Other Htgh School issues
The Sewer department is still waning to hear about the new tank for bldg 400
2 The 10,000 gallon tank serving bldg s 300 and 500 had ecology blocks located around the
tank hds to prevent vehicles from driving on the hds for the final inspection These
ecology blocks have since been removed and there is now a broken lid at that location It
is the posrt~on of the Yelm Sewer Department that a permanent non-removable barrier
(such as Bollards, Ecology blocks clearly dtd not work) must be placed around the tank
and hds to prevent vehtcles from drwmg on, or parking on the tank or hds (non-traffic
bearing tank and hds) The broken lid must also be replaced and any other consequential
damage repaired
R~dgelme
1 Need heat shrink butt connectors m all `J" boxes
2 Floats are not functioning properly
3 Electrical contractor has an tssue with having more than 2 wires m a splice and there is
not enough terminals m pump control panel for all of the wires needed to do separate
loft
Yelm High School punch list Aug30-2007
splices The bottom line of thts tssue is that tf the electrical contractor cannot connect the
electrical controls for the tank per the Yelm standards then the tank cannot be finalled
4 The Man Holes have not been vacuum tested
5 Ground water test wells have not been installed
As- Built drawm~s for al] STEP mstallaUons need to be supplied to the Sewer Department
2of2
Yelm High School punch list Aug30-2007
Page 1 of 1
Steve Harrington
From Jon Yanasak
Sent Wednesday October 31, 2007 9 O5 AM
To Steve Harrington
Cc Tim Peterson
Subfect Update on Punch list atl~elm High School
Steve,
Here is the latest as of this AM
Please refer to our latest Punch List d5t 8/3/07
TankA&B
Item #1 is not complete
Item #2 has been completed
1500 gal STEP tank for Auto Shop at High School
None of the 4 items on the list have been completed
Other High School Issues
Item #1 (replacement tank for bldg 400) not started
Item #2 (bollards) The broken lid has been replaced but no bollards installed
Jon Yanasak
City of Yelm Sewer Dept Mgr
Po Box 479
Yelm Wa 98597
Phone 360-458-8411
Fax 360-458-8166
lony@ci yelm wa us
10/31 /2007
Page 1 of 1
Steve Harrington
From Rocky Birkland [ebirkland@ycs wednet edu]
Sent Tuesday October 30 2007 11 03 AM
To Steve Harrington
Cc ray@ericksonmcgovern com Chris Hansen
Subtect Yelm High School Punchlist
Steve,
I was informed today that all punchlist items remaining at YHS,
with the exception of the 400 building tank replacement, are
complete and ready for inspection.
Thank You
Erling Birkland
10/31/2007
Page 1 of 1
Jim Gibson
From Steve Harrington
Sent Tuesday October 30, 2007 11 27 AM
To Grant Beck Jim Gibson Gary Carlson Tami Merriman, Nisha Box, Edward Smith John Ivey, Jon
Yanasak, Deonne Hardy Kevin Ray Tim Peterson
Subject FW Yelm High School Punchlist
From Rocky Birkland [mailto ebirkland@ycs wednet edu]
Sent Tuesday, October 30, 2007 11 03 AM
To Steve Harrington
Cc ray@ericksonmcgovern com, Chris Hansen
Subject Yelm High School Punchlist
Steve,
I was Unformed today that all punchllst items remaining at YHS,
with the exception of the 400 building tank replacement, are
complete and ready for inspection
Thank You
Erling B1'rkland
10/31 /2007
Please refer to our latest Punch List dated 8l3I07 \
Tank A 8 B ~~~ _i 1
Item #1 is not complete
Item #2 has been completed
1500 gal STEP tank for Auto Shop at High School
None of the 4 items on the list have been completed
Other High School Issues
Item #1 (replacement tank for bldg 400) not started
Item #2 (bollards) The broken lid has been replaced but no bollards installed
Jon Yanasak
City of Yelm Sewer Dept Mgr
Po Box 479
Yelm Wa 98597
Phone 360-458-8411
Fax 360-458-8166
Tony@ci yelm wa us
02-10-05 06 27AN FROId-BCE Engineers Inc
/r ~-
iI ~~ ENGINEERS, WC
TACOMA SEATTLE OLYMPIA
FAX TRANSMITTAL
February 10, 2005
City of Yelm
105 Yelm Avenue West
Yelm, Wa 98597
Phone 1 (360) 458-8438
Fax 1(360)458-3144
Attention Jrm Gibson /Gary Carlson
Pro(ect Name Yelm Junior High School
Protect # 204-108
From Fred Blanchard
Memo
253 9220846 T-911 P 001/005 F-d01
TACOMA OFFICE
6021 - 12th Street East, Suite 200
Tacoma Washington 98424
Phone (253) 922-0dd6
Fax (253)922-0896
2~r4/oY--
~„ l~ f-~.e~ i~ Ir~~ G~< cl
~t ~~ o4f c.eK ~~ /
T=rb 28 2n c/ S t-.-/o..l//.l h.. 'E
~ ~ r b [.. ~.t,..,
J ~
Please see the pages for the fire hydrant relocation utilizing wall post Indicators and a
wall mounted fire department connection Please calf if you have any more questions
Copy to follow via mails Yes ~ No X
If you do not receive this entire facsimile or have any questions please call
Total number of pages including this sheet 5
_ 02-10-OS 06 27AN FROId-BCE Engineers Inc 253 922D696 T-911 P 002/005 F-d01
~ ~~
~~~ ENGINEERS, INC
TACOMA SEATTLE OLYMPIA
February 10, 2005
Cdy of Yelm
105 Yelm Avenue West
Yelm, Wa 98597
Phone 1(360)458-8438
Fax 1 (360) 458-3144
Attention Jim Gibson
CC Gary Carlson (1-360-458-3144)
CC Mark King (1-360-458-2766}
CC Steve Barber (1-360-570-3136)
Protect Name Yelm Junior Hlgh School
Protect # 204-108
Dear Jim
TACOMA OFFICE
6021 - 12th Street East, Suite 200
Tacoma Washington 90424
Phone (253)922 0446
Fax (253)922 0896
Per past conversations with the Crty of Yelm, the fire protection underground supply
piping is required to contain a yard post Indicator for system shutdown and the fire
department connection is required to be located within 50'-0" of a fire hydrant BCE
Engineers would Tike this opportunity to propose the following modifications to the
above requirements, which have been discussed with both Mark King (City of Yelm Fire
Marshal) and Steve Barber (State of Washington Fire Marshal)
The Yelm Junior Hrgh School protect will include a single underground supply pipe that
will serve a single backflow preventer and a manifold that consists of (4) wet pipe
automatic fire protection sprinkler system risers and (1) dry pipe automatic fire
protection sprinkler system riser By installing a yard mounted post indicating valve, the
fire department looses the ability to isolate each system independently and will only be
allowed to shutdown the entire site We propose to install (5) wall mounted post
indicating valves in lieu of the single yard mounted post indicating valve, allowing the
fire department to have the ability to isolate each system without shutting down the
remaining systems
With the post indicating valves to be placed on the wall, it makes the most sense to also
place the fire department connection on the wall as well However, placing the fire
department connection on the wall puts the nearest fire hydrant lust over 100'-0" away
Page 1
02-10-05 06 27AM FROM-BCE EnQinaers Inc 253 9220696 T-911 P 003/OD5 F-401
If this distance is too great for the City of Yelm to accept, the fire hydrant may be
relocated and placed within the 50'-0" requirement
In sur~tmary, we propose to install (5) wall post indicators in lieu of (1) yard post
indicator and propose to install the fire department connection on the wall of the
budding We would also propose relocating a fire hydrant if the City of Yelm determines
that ~t is necessary to have the hydrant within 50'-0" of the fire department connection
If you have any comments or changes, please let us know within a week Otherwise,
this is the direction in which we will proceed
Please feel free to call if you wish to discuss any of these issues in more depth Thank
you for your time
Sincerely,
J'~ ~lc~.,7,~6tauv~
FRED BLANCHARD F P E
BCE Engineers, Inc
6021 12T Street East Suite #200
Tacoma, Wa 98424
Phone 1 (253) 922-0446
Fax 1(253)922-0896
Aage 2
vTUD~TJt DROP 01=F
RELOCATED LOCATION 5 WALL POST iNOICATING
OF THE FIRE VALVES WITH A WALL
}-fYDRANT TO BE ~ MOUNTED FIRE DEPARTMENT
INSIDE FENCED CONNECTION
~ ENCLdSURE AND
PLACED
~ APPROXIMATELY
50'-D" OF THE WALL
MOUNTED FIRE _
DEPARTMENT - ~
~~~ CONNECTION ~ _ _
~ ~ ~ i
r~ 4'1'~ ORIGINAL
'~ LOCATION
OF FIRE -~
HYDRANT •-
nJUaau~nraaaonzsnm~
~s '
J
S
\ ~~~~ "
~/ t ~-n~LI f8f ~~ari~~ I ~1~T1 NFigUS E1~lTRY
~ ~ VAlVCS MIId A
FlRf OEYARINEM WALL AIDll7ll
CORNEC1N m
ri
1~ s
_
~ ` ~ e
- '
e
2
o
T
i
I
1I(
REIOGIFD lDGll@N CF iHL
71RE HI@fGW7 TO @E IR51@E i
~ -
_ o______ ____.o__ ___b.
~
fB~CEO QIClL611RC AND ~
PLALEO APPRONAWCLV 50'-@"
OF 111E WALL I/.OUNi[0 FlRL
OCpARNCNC CpfdlWISIN ~
I I
1 ~\ ~
\~~/
o ~~
~ ~
1 ~" ~ ~
/ \
e
1
\
/
\ /
~ I
6RlCIN4. IOCMON ~~
aFl nRE ronw.Nr o ~r 3/
i
"_ DDD~DG~~Q~O
~DDDO
~D
OflQ
JWM&A
Jerome W Morrlssette & Associates Inc. P S
1700 Cooper Point Road SW, #B-2, Olympia, WA 98502-1 i 10
(360) 352-9456 • (360) 352-9990
LETTER OF TRANSMITTAL
TO James E Gibson
Development Services Engineer
City of Yelm
105 Yelm Avenue W
Yelm, WA 98597
JOB NO 03157
DATE June 24, 2005
SUBJECT Yelm Community Schools
Yelm Rtdgehne Meddle School
I am enclosin for you the attached Items
COPIES DATE DESCRIPTION
1 June, 2005
1 June, 2005
1 June, 2005
1 June, 2005
1 June, 2005
1 June, 2005
1 June, 2005
1 June, 2005
I June, 2005
PW Eagle Small Diameter Sewer Pipe
Mull Fittings 45° Wye
Muh Fittings 45° Elbow (GxGxG)
Muh Fittings 45° Gasket Cap
Muh Fittings 45° Elbow (GxG)
Muh Fittings 45° Female Adapter
Muh Fittings 45° Cleanout Plug
Iron Pipe Size (IPS)
PVC Scheldue 40 Fittings (Less than 2" only)
As requested, attached are submitted sewer cut sheets for the above referenced protect I have not
received the storwater treatment or catch basins, as soon as I receive them I will submit them to
you Please review and let me know if they are acceptable to the City If you have any questions,
please contact me at (360) 352-9456
Very truly yours,
Jerome W Morriss/e~tte~& Associates Inc, P S
SIGNED {I-~Xre~-'f~G?,Q,~j%C.-`
Robert Tauscher, P E
Cc Mr Erhng &rkland Facdmes Opetanons, Yelm Community Schools, P O Box 476, Yelm, WA 98597
Mr Stan Zielinski Archrtcct Enckson McGovern, 120 131` Street S Tacoma, WA 98444 4804
C \Bob sFdes\03157 Yelm Rtdgehne Middle School\Comespondancc\062405 Transmtt Ydm Submmuls DOC
Gvd / Mumcrpal / Geofechmcal Engmeenng and Planning
PWEa /e S~~ ~TA~P ON
g ~~~ /~~~~ '~~®E Sewer and Drain Products
V Submittal and Data Sheet
April 2005
Small-Diameter Sewer and Drain Plpe 4-Inch -- 15-inch
Solid-Wall Sewer Plpe -ASTM D3034 Gasketed
Mlnlmum Ploe StlHness 46 pal -SDR 35
Nommal Average Approximate Base Minmum Approximate
Pipe Size Outside Diameter Inside Diameter Inside Diameter Wall Thickness Wetght
Ultra-Rib Profile-Walt Sewer Plpe -- ASTM F794, AASHTO M304
Pipe Size Outside Diameter Inside Diameter Inside Diameter Minimum Wall Weight
GENERAL NOTES
Teating PWEagle tests Its sewer pipe for dimensional compliance, Impact resistance, flatternng,
pipe stiffness, end Joint Integrity according to ASTM standards
Lengths All sizes are evadable in 14- and 20-foot lay lengths
SotMS Gaskets meet ASTM F477 Jolms meet ASTM D32t 2
Installetlon PWEagle sewer and storm pipe should be Installed according to PWEagle's /nstallatlon
Guide for PVC Sewer Plpe
P O BOX 10049 EUGENE OREGON 97440 (547)343-0200 FAX (541) 688 9257 MKT W 702A
Mlnlmum Plpe Stillness 115 psi -SDR 26
Nommal Average Approximate Base Minimum Approximate
Pipe Size Outside Diameter Inside Diameter Inside Diameter Wall Thickness Weight
SOLID-WALL NOTES
Ends All sizes have Integral gasketed bells one end Solvent-weld bells are available
in 4- and 6-mch sizes
Lengths All sizes are available in 14- antl 20-foot lay lengths
Materials Pipe compound meets ASTM D1784 cell class 12454 or 12364 i
Certification Underwriters Laboratories, Inc•
PROFILE-WALL NOTES
Ends All sizes have Integral bells one end The Joint is gasketed, with gasket located on the spigot
Materials Pipe compound meets ASTM D1784 cell class 12364
Plpa Daslgn Pipe is a seamless db design meetmg ASTM F784 and AASHTO M304
MULTI FITTINGS -Trench Tough -Short Form Specs
7t~~ut Us What W. eo Mark~tc W~ Servo Inct alfation ~roducls
~~
f
MU4.T1 FITTINGS
EnAteeerae Toupti'
Page 1 of 2
WHATSNEW CONTACT US
Products -Trench Tough -Short Form Specs
~~T
Introduction -Features & Benefits - Engineennp Lav Lengths -Download
Broc ures
Trench Tough SDR35 Gasketed Sewer Flttings ~1
Flttings 4" through 15" shall be molded and comply with ASTM 03034 and ~ A •
F1336 standards Fittings shall be manufactured from a PVC compound having
a minimum cell classification of 12454 per ASTM 1784 Molded wyes, t-wyes
and tees must be a minimum of a SDR26 thickness where the branch connects
to the body of the filing In addition, service branches and bells for 4" and 6'
sizes must have a minimum of a SDR26 wall thickness Materials used for ~~
gaskets must conform to the requirements of ASTM F477 or F913 All fittings
must be manufactured with a locked in black color coded gasket having a
durometer rating of 45 These fittings must be IAPMO approved and be thud-
party certified to CSA B182 1 and/or CSA B182 2 FM
Trench Tough SDR35 8 Fabricated Gasketed Sewer Flttings
All fabrmated fittings up to 48" shall be made from segment of third-party
certified SDR35 pipe that exceeds the requirement of ASTM F679 The fllttngs `~`
shall consist of butt fused or welded pipe and solvent cemented service ~
\
\
branches All 4" through 6" service branches must be a minimum of SDR26 `
`
wall thickness The fittings must wnform to ASTM 03034 F1336 and F679
standards All fittings shall be third-party certified to CSA 8182 1 and/or CSA
8182 2
Trench Tough SDR35 Gasketed Sewer Frttrngs meet these
standards
ASTM 03034 F1336 & F679
CSA 8182 1 &CSA 8182 2
IAPMO file number 1575
~
Trench Tough SDR 26 Heavy Wall Sewer Flttings
All heavy wall SDR26 gasketed sewer fittings shall conform to ASTM 03034
and F1336 and shall be manufactured from a compound having a minimum cell ~
~
~°~,
~ 7
classification of 12454 as prescubed in ASTM 01784 All molded wyes, t-wyes
and tees must ba a minimum of a SDR24 thickness for the body of the filtrng In ~
~/
addition all outlets 4" through 6" service branches hells and bodies must have
a minimum of a SDR24 thickness Materials used for gaskets must conform to
the requirements of ASTM F913 or ASTM F477 All fttngs must have clocked- ~
in gray color coded gasket ~
Trench Tough SDR 26 Heavy Wafl Sewer Frttrngs meet these
~~
~
Standards
ASTM F1336
M 030
AS
T
34
Trench Tough CIOD Sewer Fittings for C900 Plpe
Inteclron-molded 4" to 8" CIOD gasketed sewer tees, couplings, elbows, plugs
and reducers shall conform to AW WA 0007 and be thud-party certhed to CSA
B13712 They shall be UL listed and FM approved All other configurations
must have a minimum DR18 wall thickness DR18 fittings shall be made from a
compound wdh a minimum cell classification of 12454 per ASTM 01784 The
compound must have a mmrmum Hydrostatic Design Basis of 4,000 psi and
must be listed with the Natlbnal Samtapon Foundation
Fabricated CIOD fitlrngs shall be made from segments of DR18 AWWA C900
http //www multtfitUngs com/html/trench/ttspecs htp 6/8/2005
SEE S~"AI~P ~~
~E°VERSE SI®E
SAYING LENGTH
ISSUE DATE OCT 31/00
MULTI FITTINGS SUPERCEDES AUG 01/98
H2
A C
H1
INJECTION MOLDED 45°
H3
D
FITTING WYE (GxGxG)
H2
A C
H1
(M) FABRICATED
TTING (F)
H3
p
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
M = 022
++F @ 032
M = 022
M = 022
M = 022
F @ 032
F @ 032
Notes = Refer to Page G4 for Hub Detail, Type A
# Refer to Page G4-1 for Hub Detail, Type B
@ Refer to Page GS for Hub Detail, Fabricated
~ Available on request
++ FRP Reinforced
SIZE
H1xH2xH3 PART
NUMBER REFERENCE
NUMBER , A
REF C
REF D
REF
4x4x4 63304 481549 10 125 6 125 9 250
6x6x6 63306 481564 14 250 9 000 10 500
6x6x4 63307 481556 11 750 6 500 8 875
8x8x8 63298 481580 18 250 12 000 13 500
8x8x4 63294 481572 12 750 6 500 10 500
8x8x6 63296 481598 15 250 9 000 12 000
lOxI0x10 43308 481510 22 250 15 000 16 750
lOxI0x4 43311 486513 16 625 9 375 12 500
1Ox10x6 43312 466514 16 625 9 375 13 625
1Ox10x8 43313 481518 22 250 15 000 14 625
12x12x12 43309 481512 25 875 17 875 19 625
12x12x4 43319 481524 17 375 9 375 14 500
1~^x12x6 43276 486530 17 375 9 375 15 125
12x12x8 43314 481528 25 875 17 875 16 125
12x12x10 43315 481521 25 875 17 875 17 625
15x15x15 43310 471515 42 000 29 500 26 000
15x15x4 4 320 471554 21 250 12 750 14 875
15x15x6 4315 471556 21 250 12 750 16 500
15x15x8 43316 471558 21 250 12 750 18 750
i5x15x10 43317 471551 34 000 21 500 24 000
15x15x12 43318 471552 40 000 17 500 30 000
PAGE G7
LAYING LENGTH
MULTI FITTINGS
45° ELBOW (GxG)
(1 /8 BEND)
A
H1
INJECTION MOLDED FITTING (M)
M=
M=
M=
M=
M=
M=
M=
F@
F@
F@
F@
F@
H1
ISSUE DATE JAN 26/05
SUPERCEDES OCT31/00
FABRICATED FITTING (F)
SIZE
H1xH2 PART
NUMBER REFERENCE
NUMBER A
REF
4x4 063504 480848 3 000
4x4 LONG 063409 - 3 500
6x6 063506 480863 4375
6x6 LONG 063420 - 5 500
8x8 063507 480889 5 375
10x10 063508 480810 6 250
12x12 043509 480612 7 250
15x15 043515 470815 12 000
18x18 043971 470818 20 000
21x21 043957 460821 22000
24x24 043953 450824 23 000
27x27 043516 440827 25 000
Note = Refer to Page G4 for Hub Detail, Type A
# Refer to Page G4-i for Nub Detail, Type B
@ Refer to Page GS for Hub Detail, Fabricated
"Available on request
++ FRP Reinforced
022
022
022
022
022
022
022
032
032
032
032
032
SEE S~Ai~I~ ~~
REVERSE SIDE
PAGE G18
SEE STAI~f~ ~~
REVERSE Si®E
LAYING LENGTH
ISSUE DATE OCT 31/00
MULTI FIT'I'DJGS SUPERCEDES MAY 01/98
GASKET CAP
i~
INJECTION MELDED FITTING (M) FABRICATED FITTING (F>
M =
M =
M =
M #
M =
F
F
F
F @
++F @
SIZE PART
NUMBER PART
NUMBER A
REF
4 63959 482943 2 375
6 43988 482968 3 375
8 63961 482984 4 625
10 43886 482910 4 875
12 43987 482912 5 250
15 43962 472925 13 000
18 43746 472918 17 500
21 43747 462921 19 500
24 43168 452924 20 500
27 43749 442927 19 000
022
022
022
054
022
032
032
032
032
032
Notes =Refer to Page G4 for Hub Detail, Type A
# Refer to ~hge G4-1 for Hub Detail, Type B
Refer to Page GS for Hub Detail, Fabricated
~ Available on request
++ FRP Reinforced
PAGE G22
LAYING LENGTH
- ISSUE DATE JAN 26(05
MULTI FITTINGS SUPERCEDES OCT31/00
45° ELBOW (GxG)
(118 BEND}
A
H1
H1
INJECTION MOLDED FITTING (M)
M=
M=
M=
M=
M=
M=
M=
F@
F@
F@
F@
F@
FABRICATED FITTING (F)
SIZE
HixH2 PART
NUMBER REFERENCE
NUMBER A
REF
4x4 063504 480848 3 000
4x4lONG 063409 - 3 500
6x6 063506 480863 4375
6x6 LONG 063420 - 5 500
8x8 063507 480889 S 375
10x10 063508 480810 6 250
12x12 043509 480812 7250
15x15 043515 470815 12 000
18x18 043971 470818 20000
21x27 043957 460821 22 000
24x24 043953 450824 23 000
27x27 043516 440827 25 000
022
022
022
022
022
022
022
032
032
032
032
032
SEE 5~~~~/!P ~~I
REVERSE SI®E
Note = Refer to Page G4 for Hub Detail, Type A
# Refer to Page G4-1 for Hub Detail, Type B
@ Refer to Page GS for Hub Detail, Fabncated
"Available on request
++ FRP Reinforced
PAGE G 18
MULTI FITTINGS -Solvent Weld -Short Form Specs
About Us what W~Oo Markets W~ Serve Installation Products
MULTI FITTINGS
Englnaere0 TOUgIt'
Page 1 of 1
WHAT S NEW CONTACT US
Solvent Weld -Short Form Secs
Introduction -Features & Benefits - ~ineering Lav Lengths -Download
Brochures
All SDR35 solvent weld sewer fittings shall comply with ASTM D3034 These
fttings shall be IAPMO approved and thud-party certified to CSA B182 1 and
CSA 8182 2
SbR35 solvent weld sewer fittings meet these standards
ASTM D3034
IAPMO File 2431
CSA B182 1
CSA 6182 2
"Our goal...
to manufacture the toughest flitting possible"
SR•
~~
IA~'l~tt l~
About Us What We Do Markets We Serve Installation Products
MUlll Fa7M63
Gglutryl leM
SEE ST~~ ~~~
RE1/ERSE S9~E
http //www multtfittmgs cont/1ttmUsdr35/sdrspecs htp 6/8/2005
LAYING LENGTH
ISSUE DATE JAN 19/01
MULTI FITTING5 SUPERCEDES MAY 08/98
FEMALE ADAPTER (HxFPT)
N TL
PS OD
SPIG ^T H1 FPT MALE PIPE THREAD
INJECTI^N MOLDED FITTING (M)
M 051
M Q51
M 022
M 022
SEE ~~,~~,~
RE1/ER~E ~~®E
PS SIZE
HixFPT PART
NUMBER REFERENCE
NUMBER N
REF TL
REF OD
SEW - 3, 250 3x3 04p948 282533 0, 125 1 125 -
SEW - 4,215 4X4 040949 282541 0 125 1,300 -
SEW - 6,275 6x6 040952 282560 0,180 1 500 6 625
SEW - 8, 400 8x8 040945 282580 0, 250 0 875 -
PAGE SW31
LAYING LENGTH
1 ~ ISSUE DATE JAN 19/01
1 MULTI FITTINGS SUPERCEDES MAY 08/98
CLEANOUT PLUG (MPT)
INJECTION MOLDED FITTING CM>
M
M
M
M
FABRICATED FITTING CF)
SIZE
MPT PART
NUMBER REFERENCE
NUMBER H
REF Q
REF TL
REF
3 040423 283036 0 875 1 625 0,750
4 040424 283044 1 000 2 000 0 875
6 040926 283066 0 625 1,500 1 250
8 040927 283080 1, 000 2 000 1, 100
10 040928 283010 - - -
12 040929 283012 - - -
SEE ~~:~~1P ~
REVERSE SIDE
022
022
022
022
001
001
PAGE SW33
TT. H
Iron Ptpe Stze (IPS) Plpe For Potable Water Systems
Pipe with Solvent-Weld Infegra) Bells
P R 160 Dsl -SDR 26
Nominal Average Approximate Minimum
Pipe Srze Outside Diameter Inside Diameter Wall Thickness
(inches) (inches) (Inches) (inches) Approximate
Weight
(Ibd100)
1'/a 1 660 1 52 0 064 21
1'h 1 900 1 74 0 073 28
2 2 375 Z 18 0 091 43
2'/Z 2 875 2 63 0 110 64
3 3 500 3 21 0 135 94
4 4 500 413 0 173 150
6 6 625 6 07 D 255 330
8 8 625 7 91 0332 550
Schedule 40
Nominal Average Approximate Minimum
Pipe 5¢e Outside Diameter Inside Diameter Wan Thickness
(inches) Qnches) (inches) (Inches) Approximate
Weight
(Ibsi100)
'h 0 840 0 60 0 109 i 16
3'a 1050 0 80 0 113 22
1 1 315 1 03 0133 32
1'/a 1.660 136 0140 43
1'k 1900 159 0145 52
2 2 375 2 04 0 154 69
2?h 2875 244 0203 170
3 3500 303 021fi 140
4 4 500 3 99 0 237 200
6 6 625 6 02 0 280 360
8 8 625 7 93 0332 550
10 10 750 9 96 0 365 700
12 12 750 11 88 0 406 1010
P R 200 ast -SDR 21
Nominal Average Approximate Minimum
Pfpa Size Outside Oiamefer Inside Diameter Wall Tfsclmess
(Inches) (Inches) (inches) (inches) Approximate
Wergh[
(Ibs/100~
3'e 1 050 0 92 0 060 12
1 1 315 1 18 0.063 17
1'/e 1660 149 0079 26
1'h 1 900 1 70 0 090 33
2 2 375 2 13 0113 53
2'h 2 675 258 0 137 77
3 3 500 314 0 167 110
4 4 500 404 O 214 160
6 6 625 5.94 0 316 400
rSEE S ~~~' ~~
RE~/E~SE S~®E
Pipe with Gasketed Integral Bells
P R 160 Dsl -SDR 26
Nominal Average Approximate Minimum
Pipe Size Oulsitle Diameter Inside Diameter Wa0 Thickness
(inches) (inches) (inches) (Inches) Approximate
Weight
(Iby100)
3 3 500 3 21 0 135 96
4 4 500 4 73 0 173 f 60
6 6 625 6 07 0 255 340
8 8 625 7 91 0332 570
10 10 750 9 B6 0 413 900
72 12750 1170 0490 7250
P R 200 Dsl -SDR 21
Nominal Average Approximate Minimum
Pipe Size Outside Demeter Inside Diameter Wall Thidmass
(inches) (inches) (inches) (nches) Approximate
Weight
(Ih5/Y00)
2 2 375 2 13 0113 52
2Yx 2 875 2 56 0 137 77
3 3 500 3 14 0 167 120
4 4500 404 0214 790
6 6.625 5 94 0 316 410
8 8 625 7 74 0 470 fi90
10 10 750 9 65 0 511 1090
12 12 750 11 45 0 606 1520
Pipe Meterral Pipe compound meets ASTM D 1784 cell class 12454
Prpe Dealgn Pressure rated pipe meets ASTM D 2241 Schedule 40 pipe meets ASTM D 1785 Gaskets meet ASTM F 477
Agency Classified to ANSIMSF Standard 61 for potability Applicable products are tested to the requirements of fhe Uniform
Plumbing CodeT"'
Installation Refer to installation instructions in PWEegle s Instalfahon Gurde Ior PVC Wafer Pipe and on labels supplied on the pipe
Testing PW Eagle subfects as IPS pressure pipe to several ASTM tests, mclutlmg dimensional compliance impact resistance, burst
flahenmg and font mtegnty
Other Sizes PWEegle also makes other sizes and pressure ratings of IPS size pressure pipe Consult PWEegle for details
PWEegle PWPurple Plus'"' Color Coded Pipe for Non-Potable Reclalmed/Reuse Water Systems
PWEegle manufactures a pipe product that Is tinted purple for use in non potable, reclaimed/reuse applications Irt addition to ilia purple wlor
coding, the pnnt on the pipe includes the following warning Caution Reclaimed Water Do Not Dnnk - Peligro Agua Impure No Beber'
Sizes PWPurple PIusTM can be manufactured in any of the diameter and pressure combinations available in our standarcl
potable water piping products
Note Underwnters Labora[ones Inc ° and FM bstmgs are not appltcabfe for these products However, these products
otherwise meet the same AWWA end ASTM specifications as the potable water pipe sizes upon which they are based
General Notes 1 Inside diameters may vary due to allowable manufactunng tolerances
2 Approximate weights ere for esamabn9 purposes only
3 Aft orders are sutrrecf ro hnat acceptance by PWEegle sates management
PYC SCHEDULE 40 FITTINGS
40-2-0604
Performance Engineered & Tested
SPEARS®Schedule40PVCfitting designscombmeyearsof
_£~~,~~+ (~ proven experience with computer generated stress analysts
~1~1\\ "`;,fl to yield the optimum physical structure and performance
\~\`''L0°d " x ° { ~ for each fifhng Material reinforcement is uniformly placed
~~~ ~ art`;{'?x't~ m stress concentration areas for substantially improved
~`~ ~ pressure handling capability Resulting products are
` r' t ,y, h~ ' ; sablected to numerous verification tests to assure the very
~~ ~ ~'~`°~ "~P` bestPVC fittings available
Fu-I 1/4" Through 12" Availability
Spears0° comprehensive tine of PVC fittings offers a variety
of mlecnon molded configuranons m Schedule 40 sizes l/4"
through 12" conforming to ASTM D 2466
Exceptional Chemical & Cm rosion
Resistance
Unlike metal, PVC fittings never rust, scale, or pit, and will
provide many years ofmamtenance-free service and extended
system life
Higher Flow Capacity
Smooth interior walls result in lower pressure loss and higher
volume than conventional metal fittings
Additional Fabricated Configm ations
through 36"
Extra large, hard-to-find, and custom configurations are
fabricated from NSF Certified pipe Fittings are engineered and
tested to provide full pressure handling capabilities according
to Speais'~ specifications
High Temperature Ratings
PVC theimoplashc can handle fluids at servce temperatures
up to 140°F (60°C), allowing a wide range of process
apphcanons, including corrosive fluds
Luwer Installation Costs
Substantially lower material costs than steel alloys or tined
steel, combined with tighter weight and ease of installation,
can reduce mstallanon costs by as much as 60% over
conventional metal systems
Sample Engineering Specifications
All PVC Schedule 40 fittings shall be produced by Spears®
Manufacturing Company from PVC Type I cell classification
12454 conforming to ASTM D 1784 All infection molded
PVCSchedule 40 fittings shall be Certified for potable water
service by NSF International and manufactured in strict
compliance to ASTM D 2466 All fabricated fittings shall be
produced in accordance with Spears General Specifications
for Fabricated Fttings
PVC Valves
SPEARS® PVC Valve products are available for total
system compatibility and uniformity, see SPEARS'
THERMOPLASTIC VALUES PRODUCT GUIDE &
ENGINEERING SPECIFICATIONS (V-4)
Advanced Design Specialty Fittings
Spears wide range of innovative, improved products include
numerous meta]-to-plastic transrnon fittings and tmtons with
Spears' patented special iemforced (SR) plastic threads
PROGRE'SSIVEPRODUCTSFROMSPEARS'a INNDYATION& TECHNOLOGI'
Visit oru web site www spearsmfg coin
PVC Thermoplastic Pipe Temperature Pressure De-Rating
To determine the maximum internal pressure rating at an elevated temperature, simply multiply t)~e ~lpe
pressure rating at 73°F by the percentage specified for the dewed temperature ~ ~ j ~'~
System Operating
Temperature °F (°C) 73
(23) 80
(27) 90
(32) 100
(38} 1 0
( 1
~ (5
(60)
PVC 100% 90% 75% 62°k °"90% 22%
NOTE Valves, Unions and Specialty Products have different elevated temperatur~jgs~3an pipe
PVC Basic Physical Properties
Properties ASTM
Test
Method
PVC
Mechanical Properties, 73°F
Specific Gravity g/cm° D 792 1 41
TensAe Strength pw D 638 7 200
Modulus of ElastlGty psi D 638 440 000
Compressive Strength psi D695 9 000
Flexural Strength psi D 790 13 200
Izod Impact notched ft Ibfin D 256 65
Thermal Properties
Heat Deflection Temperature °F at 66 psi D 648 165
Thermal Conductivity BTU/hr/sq it/°F/m C 177 1 2
C°efhGent of Linear Expanswn In/1nPF D X96 31 X ib$
Flammability
Limiting Oxygen Index % D 2863 43
UL 94 rating 94V 0
Other Properties
Water Absorption % 24 hr D 570 05
Industry Standard Color Whde /Dark Gray,
ASTM Cell Clesslflcatlon D 1784 12454
NSF Potable Water Approved Yes ~
PVC Chemical Resistance
PVC Is generally Inert to most mrneral acids, bases,
salts and pazaffmle hydrocarbon solutions For more
Irifotmahon on PVC chemical resistance refer to
the Chemrcal Resistance of Rrgtd Vinyls Based on
Immersion Test, published by the GEONs' Company
NOT FOR USE WITH
COMPRESSED AIR OR GA5
Spears°r Manufactuung Company DOES NOT
RECOMMEND the use of thermoplastic piping products
for systems to transport or5tore compressed air or gases, or
the testing of thermoplastic piping systems with compressed
air or gases m above and below ground locations The use of
our product m compressed air or gas systems automatically
voids any warranty for such products, and its use against
our rCcommendahon is entirely the responstbilrty and
liability of the installer
WARNING DO NOT USE COMPRESSED
ATR OR GAS TO TEST ANY PVC OR CPVC
THERMOPLASTIC PIPING PRODUCT OR
SYSTEM, AND DO NOT USE DEVICES
PROPELLED BY COMPRESSED AIR OR GAS
TO CLEAR SYSTEMS THESE PRACTICES MAY
RESULT IN EXPLOSIVE FRAGMENTATION
OF SYSTEM PIPING COMPONENTS CAUSING
SERIOUS OR FATAL BODILY INJURY
SPEAR5® MANUFACTURING COMPANY • CORPORATE OFFICE
15853 Olden St ,Sylmar, CA 91342 • PO Box 9203, Sylmar, CA 91392
(818) 364 1611 vnvW spearsmfg coin
PACIFIC SOUTHWEST
15880 Oldwl SI
8yhnar (LOa Mga'es) CA 91312
(818) 3x 1611 (89018621489
fax 181913673014
NORTHWEST
4103 G SL NE Smle 870
Auhum (See9kl WA 98002
(es31939-a43J (8551x17327
Faz (253) 039 7557
ROCKY MOUNTAIN
4880 Florence 8L
Denver CO 80238
(303) 371 9430 IBJO) 777-0154
Fax (303) 3756546
SOUTH CENTRAL
4250 PaVbiDr Suite 300
Caapenne lDelies) TX 76651 2317
Isnl6sutxo (a5o)99t taa7
Fax (972)691-0404
UTAH
1641 S°ulh 705 West
8x11 Lake Gty UT 89154
(801) 972 X59
Fax (8011972-0688
NORTHEAST
580 inluslAal Or Swle 100
LeA¢barry (HaMSWrg) PA 17339-'.FSY
(717) 9386894 (800) 2330275
Fax (71719386547
SOUTHEAST
42~ Nexy9lnl PI Suxe 700
Lavrtencen5e (Atlanta) GA 30019
(678(9651263 (800(6626326
Fax (678)9856892
FLORIDA
9563 ParksauN C°uA
Odand° FL 32837
(407)943 1860 (800)327.6390
Fax (dW)425-3563
w51n
_t
' ~~
r',n( ,`~
MIDWEST
1 GalewaY Cl SuiteA
B°IMgbr°°k (Chmag°) IL 60440
(fi301769 7529 (600(6626330
Fax (630) 759 7515
INTERNATIONAL9ALE3
15653 Olden 5(
Sylm~r(lm Mgeks) Cp 9ix2
(818)7E4 1811 Fex (818169&3774
E+nail exp°rtgs0eaisallg coin
® C°PPIgh12005 6pearx° ManulecWnn9 r:9maam M Rphb Reserved PAnletl In the Unlled dales 9tAmanca 01105 462-0604
JWM&A
Jerome W Mornssetle & Assoaates Inc P S
1700 Cooper Point Road SW #B 2 Olympia WA 98502-1110
(360)352 9456 I FAX (360)352 9990
August 15, 2006
Mr Erhng Btrkland, Director of Facihties
Yelm Community Schools
PO Box 476
Yelm, WA 98597
Re Ftre Flow Test at Yelm Htgh School
August 11, 2006/Sumary of Results
Dear Mr Btrkland
This fire flow test was conducted to evaluate the fire flow capacity of the system with a higher
degree of certainty than is possible with the earlier fire flow tests conducted May 31, 2006 The
fire flow tests conducted May 31, 2006 and the fire flow projection calculations indicated that
the system could provide 1,426 gpm at 20 psi residual pressure at one fire hydrant and could
provide 1,279 gpm at another fire hydrant at 20 psi residual pressure Subsequent to conducting
the fire flow tests, it was discovered that one of the City's reservoirs was out of service Since
the required fire flow is 1,438 gpm with a minimum pressure of 20 psi, the fire flow test and
pro~ecUOn calculations indicated that the system could not provide the required minimum fire
flow Additionally, the fire flow calculation for the earlier fire flow tests required projections of
the fire flow capability of the system since the actual flow from the hydrants during the tests was
less than 1,438 gpm Projecting fire flow capacity introduces some uncertainty into the fire flow
calculation Moreover, a reduced pressure backflow assembly (RPBA) was installed on the 8
inch city line that serves the entire school site, including the city owned fire loop and city owned
fire hydrants As far as fire flow is concerned the RPBA effectively reduces the available water
pressure Thus the installation of the RPBA introduces more uncertainty into trying to project
the fire flow capacity of the system
These current fire flow tests were conducted with the RPBA installed and operational and were
conducted using a discharge somewhat higher than the required minimum fire flow and were
conducted with all of the City's reservoirs in service Thus the certainty of the results for this
fire flow test is considerably higher than using the results of the earlier fire flow test While
discharging more than 1,438 gpm from the fire hydrants, the residual pressure exceeded the
minimum required 20 psi For the conditions that existed during this fire flow test, in particular
water levels in the Public Works Tank at 138 93 fr in the Downtown Tank at 110 76 fr and in
the Baker Hill Tank at 56 85 fr ,the system is capable of exceeding the 1,438 gpm minimum
required flow while maintaining residual pressure exceeding the 20 psi minimum required
residual pressure
Mr Erhng Kirkland, Director of Fac~lrties
August 15, 2006
Page 2 of 2
A reduction m reservoir levels would reduce the fire flow capacity of the system According to
our understanding of the Fire Marshal's requirements for a new building, the water system
serving the fire system should be able maintain fire flow capacity above the minimum required
when the reservoirs are drawn down to the bottom of the allotted fire flow storage Since the
RPBA reduces the pressure m the fire loop, the RPBA makes the fire loop act as though the
reservoirs are drawn down approximately 16 feet lower than the actual reservoir levels In the
immediate future a significant pomon of the 8" fire loop will be replaced with 10 inch ]me This
will have the effect of increasing the fire flow capacity of the loop, but will not change the
pressure drop that occurs across the RPBA
Very truly yours
Jerome W Mornssette & Associates Inc , P S
Doug Eklund, P E
Senior Protect Engineer
Attachments
CC Mr Jim Gibson, PE City of Yelm
Mr Ray Mow, Erickson McGovern
Jerome W Mornssette & Associates Inc , P S
1700 Cooper Point Road SW #B 2 Olympia WA 98502 1110
(360)352-9456 / FAX (360)352-9990
Yelm Htgh School
Ftre Flow Results Report
August 14 2006
By Scott G Severs
Condrtrons
Our office conducted two fire flow tests for the Yelm School District at the Yelm High School on August 11, 2006
between the hours of 10 00 am and 10 30 am in cooperation with the City of Yelm Personnel conducting the flow
testing were Scott Severs Sr Engineering Technician(JWMBA), Doug Eklund Sr Pro)ect Engineer (JWM&A) and
Edward Smith Yelm Water Dept (City of Yelm)
The equipment utilized for the flow testing were two Pollard hydrant diffusers equipped with pilot and pressure
gages Three pressure recorders (Dickson PR 300 electronic recording devices) and one 0-200 psi (Dwyer digital
pressure gage) were used to record static and residual pressures before, during and after fire flow testing See
attached map for gage locations
The well pumps were off and all three City reservoirs were on line
The reservoir levels were recorded prior to each flow test (See Exhibits 2 and 3)
Static pressures were recorded prior to each flow test and residual pressures were recorded during each flow test
(See Exhibits 2 and 3)
There is an 8" reduced pressure backflow assembly installed at the Southeast corner of the school site and all flow
into the site flows through the RPBA, to include the City owned Fire Loop and Hydrants The static pressure drop
across the RPBA is 7 to 8 psi (See Exhibit 4 pressure recorder results graph "Downloaded Data")
Flows were recorded at two hydrants while flowing through two ports simultaneously at the flow locations (See
attached map)
The first flow test had both pilot gages attached to a single hydrant The second flow test had the pilot gages
attached to separate hydrants (See attached map)
One of the pressure recorders was deployed upstream of the RPBA and the other two with the digital pressure
gage were deployed downstream of the RPBA (See attached map for locations)
The first flow test was conducted at 10 04 am (See Exhibit 2) and the second flow test was conducted at 10 18 am
(See Exhibit 3)
Flow Results
The first fire flow test was conducted with both pilot gages attached to a single hydrant located at the North end of
the school sites situated between the Gymnasium and the newly constructed High School Building
The calculated combined flow at 20 psi residual for this flow test is 1782 gpm (See Exhibit No 1)
Civil / Municipal / Geotechnical Engmeenng and Planning
The second flow test was conducted with the pitot gages attached to separate hydrants One was attached to the
same hydrant as the lust test and the other was attached to a hydrant located near the southerly end of the school
site adjacent to the Shop Bwlding
The calculated combined flow at 20 psi residual for this test was 1688 gpm (See Exhibit No 1)
The requued flow for the High School is 1438 gpm or better
Summary
Exhibit No 1 summarizes the flow test results and the flows protected out to 20 psi residual pressure
Exhibit No 2 shows recorded data from the first flow test
Exhibit No 3 shows recorded data from the second flow test
Exhibit No 4 is a graph that shows the recorded pressures before, during and after the testing both upstream of
the RPBA and downstream of the RPBA
Exhibit No 5 is a copy of the Pollard Flow Test Chart Calculator and Hydrant inlet coeffiaents
Exhibit No 6 is a copy of the speafication sheet for the installed RPBA with head loss charts
The pressure drop across the RPBA increased to approximately 14 psi during flow conditions This is a
considerable pressure drop and is cause for some concern with the overall diminished capacity that existed within
the system pnor to the installation of this device The head loss for this device at the flows recorded should be near
10 psi (See Exhibit 6)
The fire flow testing results demonstrate that the looped portion of the system under these conditions will meet the
minimum fire flow regwrement of 1438 gpm The final calculated flow results for the two flow tests under these
conditions, protected out to 20 psi residual pressure are 1782 gpm and 1688 gpm
Flow Test August 2006
Exhibit No 1
Hydrant Flre Flow Tests at the Yelm Hlgh School August 11, 2006
Flow Test No 1 August [1 20061004 am
Reservoir Pumps Hydrant Onfce Onfice Stabc Pltot Residual Static Residual
Level (ft) On/Off Location Dig (in) Coef Pressure Pressure Locebon Pressure Pressure
`R1=138 93 R2=110 76 R3=56 85 OH Northedy Hydrant between New HS 8 Gym 2 5625 1 44 0 17 0 See Below 44 0 24 0
R1=139 52 R2=111 09 R3=57 75 OH Northerly Hydrant between New HS & Gym 2 5625 1 44 0 17 0 See Below 44 0 24 0
Hydrant Target
Flow (Qh) Flow (Or)
807 62 891 18
807 62 891 18
Total Combined Flow 1782 35
Qn = 29 83(C)(d^2)(p"0 5)
Dr = Oh(Hr`0 54/HP 54)
Oh =flow from hydrnt
Hr=drop from static to desired pressure
Hf=drop from static to flowed pressure
Flnw Tnef Nn ~ Aunust 11 2006 70 18 am
Reservort Pumps Hydrant Onfice Onfce Static PROt Residual Static Residual
Level (ft) On/Off Location Dig (in) Coef Pressure Pressure Location Pressure Pressure
R1=139 52 R2=111 09 R3=57 75 Off Between Gym 8 New H S N Side 2 5625 1 44 0 17 5 See Below 44 0 22 0
R7=139 52 R2=111 09 R3=57 75 Off E Side of Shop (W-10) 2 5 1 44 0 18 0 See Below 44 0 22 0
Hydrant Target
Flow (Gh) Flow (Gr)
819 41 858 83
790 99 829 04
Total Combined Flow 1687 87
On = 29 83(C)(d^2)(p^0 5)
Dr = Oh(Hr`0 54/Hr" 54)
Qn =flow from hydrant
Hr =drop from static to desired pressure
Hr=drop from static to flowed pressure
RI=Public Works Tank R2=Downtown Tank R3=Baker Hill Tank
Residual Pressures ware recorded at the following locations
Dwyer 0 200psi Digital Pressure Gage Located on Fue Hydrant
at the SE wrner of the new High School Bwldmg
Dickson PR300 Electronic Pressure Recorders at the following locations
On the RPBA upstream of the check valves SE corner of School Property
Fire Hydrent located approx 200 ft west of the SE property comer
Fire Hydrant located near fhe NE corner of the new HS service yard
8/15/2006
~~
!'Eft '.3 !a- n.~ L
JWM&A
1700 Cooper Pomt Road S W, #B-2, Olympia, WA 98502-1110
(360) 352-9456 • (360) 352-9990
FIRE FLOW FOR: Yelm H~~h School
DATE 1 D TIME 10 , ~~ 4 LOCATION 5 ~(e'TGtJ~! ~~S ~ G s~rv ~/, yG1E.
RESERVOIR LEVEL (FEET)
PUMP (S) OON DOFF
ORIFACE DIAMETER (INCHES) _ ~`~/ia ~ ~/i~,
ORIFACE COEF ~•a
STATIC PRESSURE (PSI) 44
PITOTPRESSURE(PSI) ~~ c7 3o'fFr Pitcsc5
HYDRAULIC MODEL NODE #
FLOW=QH-2983 (C) (d Z)
Where flJ
C = coeffiemt used to descnbe the outlet end of the hydrant, usually~if smooth
d =diameter of hydrant flow port
p = prtot pressure observed
Qy=
TARGET LOCATION _~ ,E t' ~~.cfE,P ~¢ ~/,.tr,~ f~ S /3!,t ACV ~./c~
STATIC PRESSURE (PSI) 4.4
RESIDUAL PRESSURE (PSI) 24- 25 ~sl
PROJECTED FLOW @ 20 PSI
Q DESIRED = Qg (P STATIC- P DESIRED) ~ 54 HYDRANT
(P STATIC - P RESIDUAL) ~ 54 TARGET
Q 20=
FLOW THROUGH~R'd"RP3A YES ONO
STATIC PRESSURE ABOVE PRV (PSI) •~_
STATIC PRESSSURE BELOW PRV (PSI) -~
PRV PRESSURE 5ET @~.4- (PSI)
CALCULATED BY S ~~ ~'E/ZS DATE CALCULA
REMARKS J!ls l~Gcr~LrL(~O~/~S Tit.J~C !~Z = r,~a.~,! :~c:...'~.f ~r,4,lEC
/r~~i~(3~T ,~/d 3 ~~
JWM&A
1700 Cooper Point Road SW, #B-2, Olympia, WA 98502-1110
(360) 352-9456 • (360) 352-9990
FIRE FLOJW FOR• Yelm Hish School
DATE D~Jrr/r/OG TIA~ rb ; 1 S LOCATION YN~ /'~wr¢,~/ N5 ~ ~ Yl~~ ~/ F
RESERVOII2 LEVEL (FEET) Rl ~3~9' RZ No =`
PUMP (S) DON' (OFF
ORIFACE DIAMETER (INCHES) = Za~~,, 2'~z
ORIFACE COEF /.
STATIC PRESSURE (PSI)
PITOT PRESSURE (PST)
HYDRAULIC MODEL NODE
FLOW = QH = 29 83 (C) (dz)
Where
/s~
C = coeffiemt used to describe the outlet end of the hydrant, usually if smooth
d = diameter of hydrant flow port
p =pilot pressure observed
Oy=
TARGET LOCATION ~~ C°r9~'Nr~ o~ .^y<=J N, 5 ~C/~~>iRIG,
STATIC PRESSURE (PSI) 4Y
RESIDUAL PRESSURE (PSI) ~2 - Z.3 Tx 1
PROJECTED FLOW'@ 20 PSI '
Q DESIRED = Qy (P STATIC - P DESIRED) 0 54 HYDRANT
(P STATIC - P RESID UAL) o sa TARGET
Qzo=
FLOW THROUGH-P;~TV I~l'l~ `)(YES
STATIC PRESSURE ABOVE PRV (PSI)~~° i
STATIC PRESSSURE BELOW PRV (PSI}
PRV PRESSURE SET (7a, F///-I- (P
ONO
REMARKS ~2l = ~(/GL/G wo/1/c5 TrFn//L .2y TJou~./tr~cvr! T'.4..!lC
CALCULATED BY S. SE~~t2S DATE CALCULATED /!
~~~,Cf~/TS.f R/D
FLOW TEST CHART CALCULATOR >~[~--art-~a~er(o)QO1111
r
SMOOT
H RADIUS
PAGE 1 of 2
;~-
-
.. u = No Coefflaent for Inlets with Smooth Radlus Edge -
---
0 77 Coefriaent for In lets wdh Raised Square Llp ~ "-
i' ~ ~ 0 88 Coefficient for In lets wdh Sharp Square Edge ~ ~
~' ~ 4 3- 1 i 0 Coeffiaen t for Open End Plpe
d f~~
q
II ~'r SHARP
souARE RAISED
souatE
Chart Values h
ave been
rounded to the nearest 5 GPM
s
as1 1-7n° z° z-tn° 3" 3-tn~ a a-7n s' s'
1 60 110 770 245 330 435 550 680 980
2 BS 7so 2ao 3as a7o s7s 77s ssD 13Bo
3 105 185 290 420 570 740 940 1160 1670
4 125 220 340 490 665 870 7700 1360 1960
5 135 240 380 545 745 960 1220 1520 2190
6 150 260 410 590 BOS 1050 1340 1640 2360
7 160 280 440 ~ 635 860 1140 1440 1760 ~ 2535
8 175 310 480 ~ 690 940 1220 1540 1920 2765
9 180 320 500 720 980 1290 1640 2000 2880
10 190 340 530 765 1040 1360 1730 2120 3050
11 200 355 555 800 1090 1420 1800 2220 3195
12 210 370 580 835 1135 1490 1890 2320 3340
13 220 390 605 870 1185 1550 1960 2420 3485
14 230 405 630 910 1235 1610 2040 2520 3625
15 235 415 650 935 1275 1665 2105 26017 3745
16 240 430 670 965 1315 1720 2180 2680 3860
17 250 440 690 995 1350 1770 2235 2760 3975
18 255 455 710 1020 1390 1830 2310 2840 4090
19 265 465 730 1050 1430 1870 2365 2920 4205
20 270 480 750 1080 1470 1920 2430 3000 4320
22 285 505 790 1140 1550 2020 2550 3160 4550
24 295 525 820 1180 1605 2110 2660 3280 4720
26 370 550 860 1240 1685 2190 2770 3440 4950
28 320 570 ~ 890 1280 1745 2280 2880 3560 5725
30 _ 330 590 920 1325 1805 2350 2980 3680 5295
32 340 610 950 1370 1860 2430 3080 3800 5470
34 355 625 980 1410 1920 2510 3170 3920 5640
36 365 645 1010 1455 1980 2580 3260 4040 5815
38 375 fi65 1040 1500 2040 2650 3350 4160 5990
40 380 680 1060 1525 2075 2720 3440 4240 6105
42 395 700 1090 1570 2135 2780 3520 4360 6275
44 400 710 1710 1600 2775 2850 3610 4440 6390
46 410 730 7140 1640 2235 2920 3690 4560 6565
48 420 740 1760 1670 2275 2980 3770 4640 6680
50 430 760 1190 1715 2330 3040 3860 4760 6850
52 435 775 1210 1740 2370 3100 3940 4840 6965
54 445 785 1230 7770 2410 3160 4010 4920 7080
56 450 800 1250 1800 2500 3220 4080 5000 7200
58 460 820 1280 1845 2510 3280 4160 5120 7370
Toll Free 800-437-1146 • Fax 516-746-0852 • www pollardwater com • Email tnfo@pollardwater com
FE~C®®
BACKFLOW PREVENTION
REDUCED PRESSURE ASSEMBLY
Charactenstics
Physical Properties
Size of Mainline
Max Working Pressure
Hydrostatic Test Press
Temperature Range
End Connections
Materials
Main Valve Body
Coating
Shut Off Valves
Trim
Elastomer Discs
Spring
Clamp
Application
Health Hazard
Model 860 Flow Curves
2'!z' 3, 4 , 6', 8", 10'
175 PSI (1200 KPa)
350 PSI (2400 KPa)
32° F to 140° F (0° C to 60° C)
Flanged ANSI B16 1
Class 125
Ductile iron
Grade 65 45-12
Fusion epoxy coated
internal and external
AW WA C550-90
OS & Y resilient wedge
gate valves
AW WA C509
Bronze
Alloy C83600
EPDM
Stainless steel
AWWA C606 (10 Only)
U S Patent No 4 989,635
Agency Compliance
ANSI/AWWA (C511 89) - 2 r, lo'
ASSE (Std 1013) - 2'/: ~ 0
CAN/CSA (864 4) 2'r: e•
UL Listed - 2v: &'
FM Approved - z'r, s
Approved by the Foundation far Cross Connection
Control and Hydraulic Research at the University of
Southern California - 2 /:" e
2'/:" and 3
zo
n. 15
N
g 2'~ 3„
J
a 10
m
m
5
80 160 240 320 400 GPM
4' and 6
_ zo
N
a
N 16
N
J 6
~ 10
d
6
400 800 1200 1600 2000 GPM
8" and 10"
20
m 10' T
~u
N
N
J 8"
.° t (]
N
Y
Z
6
MODEL 8601NSTALLATION
1000 2000 3000 4000 5000 GPM
MODEL 860 REDUCED PRESSURE ASSEMBLY
.~
HYpRANi FLOW TEST
LOCATION 1ST FLOW LEST g FlREMAIN
AND 2ND FLOW TEST
7~ ~a°.v ~~ ~i ` 1 8" FlRETIAI
.c c ,..... OIGI iAL PRi
e.~
333 ~ ' ~
. la
rc
~ HYDRANT FLOW LEST
- -~ 1O LOCATION 2ND FLOW TE$i
/ ~
SCALE 1 =100 FEET /
IIIIIIIIIIr
"" I H +f H F+ I-Fm I~f~T~
0 50 100 200 Q I ~ ~ I I I I I I I I I I I I I I I L/ 8 F7REA/gIN
B,........~ I I V I I I I I I I I I I I I I I 1 1 I I
GE ~yl`~ W IJlI Il1L I11LI Llll
PR 300 PRESSURE
RECORDER YH$ NORTH
(SEE EXHIBIT 4)
a
A
i
Z
LOCA PON
JI
0~~
PR 300 PRESSURE RECORDER
YH$\ EE EXHIBIT 4)
8° FlREMAIN
i~
I
~ \~
~ \
I
I r
I
I
m
I
A
n I
z
~ B RPBA
PR J00 PRESSURE RECORDE
tti5 RPBA (SEE EXHIBIT 4)
~ pl.iE 6Y PP REN d15 ~~~~~~~~pp p~
^rr~~®'~Gnl Mumnpal Geotechmcal Englneenng and Planning
~
FIRE FLOW MAP
drt
~ YELM SCHOOL DISTRICT FOR AUGUST 11 FLOW TESTS
Jerome W Mornssette & Assoaates Inc , P S ..
VDDCm
er%FOatlSW NR2 Ol
W
9B3@1110
4
fi F3W 35E 999
h
p
ympm
a
P
360 I539
5
D $HT 1 OF
C'aty of Yelm
Community Development Department
105 Yelm Avenue West
P O Box 479
Yelm, WA 98597
October 5, 2006
Erling Birkland
PO Box 476
Yelm, WA 98597
RE Yelm Hrgh School Reclaimed Water Revrew No 1
City of Yelm Protect No SPR-03-8362-YL
Dear Mr Birkland
The following comments are from the review of the reclaimed water plans submitted on Wednesday
September 27, 2006 The intent of the submittal was to relocate the reclaimed water main to a distance
greater than 10' from the potable water main We have the following comments based on the review of
these plans
A User Agreement must be executed with the City of Yelm before the connection to the reclaimed
water main at the property line can be made Please contact Stephanie Ray at (360) 458-8414 to
arrange for the agreement
A detailed water balance needs to be submitted to the City of Yelm for review and approval
User protections, notifications andlor warning signs need to be installed per the City of Yelm
regwrements These are not shown on the plans A sufficient number of Reclamation Identification
Signs must be placed and provide for the site to inform site users that reclaimed water is being used
to conserve the potable water and warn against consuming any type of non-potable water
The reclaimed water notes need to call out the specific "purple" color The regwred color is Pantone
512 or Pantone 522
Reclaimed Water note no 1 should be City of Yelm not City of Yelm's Water District
Please note that all ID tags and all other informational and warning signs must be approved by the
City of Yelm and all regulatory agencies Please contact the City of Yelm for further information
The reclaimed water sleeves need to be 20' m length This length should be split evenly acrossed
the main line that is being protected
The construction plans are being approved for installation only The above comments still need to be
_addressed and need to be adhered to during the installaion of the reclaimed water system
If you have any questions or concerns please do not hesitate to call or contact me by email at
IimbCa~a velm wa us
Respectfully
Community Development Department
Jim Gibson
Development Review Engineer
(360) 458-3835
(360) 458-3144 FAX
www et yelm wa as
JWM&A
Jerome W Mornssette &Assoctates lnc . P S
1700 Cooper Point Road SW, #B-2, Olympia, WA 98502-1110
(360) 352-9456 a (360) 352-9990
FAX TRANSMISSION SHEET
TO. James E Gibson, P E
Development Services Engineer
City of Yelm
105 Yehn Avenue W
Yelm, WA 98597
JOB NO 03143
DATE August 11, 2006
SUBJECT Yelm High School
CCD 73 -Revised Fine and Domestic Lines
I am enclosing for you the attached items
COPIES DATE DESCRIPTION
1 August, 2006 CCD #73 mylaz
4 August, 2006 CCD #73 paper copies
1 August, 2006 CCD #73 11 x 17 copy
I am submitting copies of the revised domestic and fire Imes, as requested, for the Yelm High
site If you have any questtons, please contact me at (360) 352-9456
Very truly yours,
Jerome W Mornssette 8 Assoctates Inc , P S
SIGNED 1 ~~P~d-~T ',~~
Robert Tauscher, P E
Protect Engineer
C Mr ErLng Bvkland, Facdmes Operations Yelm Community Schools, PO Box 476 Yelm, WA 98597
Mr Ray Mow , Enckson McGovern, 120 131" Street S ,Tacoma, WA 98444-4804
C \Bob\03143 Yelm High School Srte Improvement\Correspondence\081106 Transmit Yelm DOC
Crvd * Muntctpat * Geotechntcal Engmeenrtg and Planning
,o ~~,~ City Of Yelm
;' ~ PO Box 479
Yelm, Washington 98597
(360) 458-3144
Date ~ `' - ? ~, ~~ ~%
~Vew ~r Hook Up s ~ 0 4
i
BuildmgPerm~t ~ I ; n, ~ ~ a---r~ ,~ w, r ~•~ r-
Name YrI~,, (~,~,.,~,„,~ S~ ~.~, Is Tap#_
.*
Address ~ ~ ~ ~ ~ q ~ G- Account #
Phone # 5 ~ c - ~} ~ r - (, I < <`~
Site Address
Fees Paid ~I ~ c '~ ~ ~~ Receipt #
Public Works Approval
r~,~-,tiit~~~
g icta pp val2- 4 , ~ ~ ~ `~_.
./
i
Book #
Lot #
COMPLETED DATE
SIGNATURE
READING
~, ••~~ CrtyOfYelm `~` "`""`~~~
® PO Box 479 New ~'titPr Hook Up s ~ o s
Yelm, Washington 98597
(360)458-3144 nle-. ~ n r,.. ~..~~pf~~i' ,. ~~I.~.-, 1, ,.~1
Date f t> z ~ - ~ ~ C^ Buffdmg Permit I ~' -~iz1 C ~T, c '~' ~-~ ~T~-~'
,~~oc-E<iti,t
Name Y . I ~" C ~ ,,, .., ~. ~, ~ ~ y S . L, ~ ~ r Tap#
Address P ` '3 ~ X 4 ~ ~.- Account
Phone # ~ ~ ~ q ~ 'r ' ~ 12 f ~ Book #
Site Address `~ '= `~ ~ ~~ ~ I I K ~ , ~ ~ ~ - Lot #_
Fees Paid I Receipt #
Public Works Approval COMPLETED DATE
,c ~<<c2
Bu~ldtngAfficia}-Appreva ,<..,~o~ £ ~~_~~~~-r---` SIGNATURE
READING
~~
P~II YELM COMMUNITY SCHOOLS REVOLVING FUND
P O BOX 476
VELM WA 98597
~4fd~
~„
I ~,k~,
~; ~~~1~
~/ www vanNrabank com
venture Telap~oneBankingl-6004511765
i x w x\`~ (360)923 5332 <
~~ IUIt
it f
x:12$1076711:1 26 10 309 10~i'
~_ i _ a ~ _ _ i _ .~ _- ~
~~~ ~
~~
~ ~~
2391 ~
98 76]/1251 I
i
„~~~
2391
I $ 2, 6CL `~' i~d
~ ,, ~-- "'
inn~
wl
,w ~l y
-- - ___ __ _ III
I~
c -x _
<•
`4
~j~~~l & ASSOCIATES, INC
GEOTECHNICAL ENGINEERING . CNVIRONM ENT4L ENGINCERING
CONSTIiU CTION TCSTING R INSPCCTION
August 17, 2006 KA No 066-04202
'`~~` Permit No BLD-04-0130-YL
(~f BLD-04-0]32
" ~,,, '~
Mr Erhng Btrkland - F ;~ `~
YELM COMMUNITY SCtIOGLS ~~
404 Yelm Avenue West
Yehn, WA 93597-0476
RE Special Ltspechous
Yclm Fhgh School
Yehn Wasluneton
Dear Mr Blrkland,
Li accordance r+Jth your request and authonzatton, our firm perfomted special inspections for the above-
referenced project The mspecttons were perfomTed by our inspectors from August 11 through August
15, 2006 Copies of our inspector's field reports are attached
Unless otherwise indicated, the civil actlvrtles noted on the attached daily field renort~ were m
accordance w rth the approved project plans and spectfications, and the 2003 In[emahonal Bwldmg Code
A euarantee dia[the contractor has necessanly constructed the structure m full accord with the plans and
specifications is neither attended nor implied
If you have any questions or if we can be of further assistance, please do not hesitate [o contact our
office
Respectfully submitted
KRAZAN & ASSOC TES, INC
~-
Edward A Smith
Project Manager
Pacific Northwest Region
CAS\rd
CC 7CLM GDhIMUNII} $CHOOIS ATTN EItLING BIRhL4ND (PDC)CaIRLLANU(FU1 CS i~LDNLI LDU
PU INAM CDLLINS SC OIT ASSOCIAI LS INC AT1N JAC6 PINMRU
PDTNAh1 COLLINS SCOTT A$S0C14TES INC ATIN DOUG GGDDRIN (PUI)UGOOU&IN n~PCSAINC CUM1I
ERIC ISON MCGOVCRN ACRD DAVID BCRTUSA IA
BERSCHAUCR PHILLIPS CONSTRUCTION COb1PANY
1CROAIEW MORRISSI IILR ASSOCIA7 C5 ATTN BOU TADSC IIER
Cir1 OFIELSi A1TN GAR\ GARLbON
Offices Ser~mg The Western United States
I X01 - IS°' Street NW Swte IOG .Auburn Waslnngton 13002 • (253) 939 25W • Eae (253) 939 ?SSG
`1 ~~17a11 & Associates, Inc FIELD REPORT NO ~~24L
CcOI[_H ii c..t F for s=aiur' E i iFCi m, - [ u-~i i i r_
Gnrou~u~n TE nn~rir~L Pf~nr
DATE \~ ~-(~ CONTRACTOR ~-_ _ \\ - t li ,
PROJECT # `-'r I, -~+ Y ~ 1, JURISDICTION l ~ I
PROJECT ~ '~ r; r _ PERMIT # ~ - ~ ~", , ? ~~, - 1~
LOCATION /" + } . t
V t INSPECTOR ~ , ~ .-\ ~
KRAZAN PROJECT MANAGER ~ WEATHER ~ ~j TEMP ( r,
~_ ~ ``
\y 1 ~ ~ r ~
\~
c_r ~ v i v ~~
1 r~ ~ ti
,\
~
___ . ~
r
Equipment/Asset Number(s)
To the best of my knowledge the abovc~WAJS /WAS NOT performed m accordance wdh the approved plcns specifications and regulatory regwrements
Supennfendeni/Representahve
Technrclan ~ r r
~r y
~ r lam` \ `~,'~~
Servif~g the Weste~ri U~arted States
~~
_y~,..3 V u COMPACTION
~'~Z~ & Associates, Inc REPORT NO ! ~~,;!
GEOTECHNICAL ENGINEERING ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING AND INSPECTION
DATE -~ i t - L° 4
CONTRACTOR
PROJECT# >~...1 ~ •" i ~ PERMIT NO -~ s_~ ~_'
PROJECT ~' - I ut __~ _ _ INSPECTOR f' . ~ ~ ~~ -
LOCATION _1 `. t_ " ~'--~ ~_.-_
JURISDICTION ~ `
KRAZANPROJECT MANAGER t L. ~ _ WEATHER ~_ `_. _ '
^ WASHINGTON DENSOME7ER ^ SANDCONE ~ NUCLEAR TEST ^ OTHER
L_OCATfON_MAP
- J ~ (~' _,
T U
^ Paved Areas (circle one) Sub / Agg /Asphalt
Budding Pad (s)
^ Other "~ ~ ^ ', _ ~` ~
~
_
^ I
Trenches (circle one) Sewer /Water /Storm Dram / Utly
I ~
~ Curve Unrfied Solis Classdication Max Dry
Density Opt
Moisture
I
i
I I
I
I I I
Test Elevation Location(Comments) Curve Mode 8
Depth Density Moist
% Percent
Compaction Required
~ ~ ~~`` _i ,.. ~.~1~_-_,r r ~'I l~" lit' ~`~i. ~ riL"v ~ ~`~-~.
~
~~ ~ -t
I~cx, 1`°
~
~
~~ _
f t l i d I _
i ~
'~ ~ ~ ~ ~ i- tl >,) ~ r -
- ~ ~ ~ - ~ t ~ ~ ~ ~ ` `~ ~ ~/
I ~ ~
I I -_ ~
~ ~ ~
~ -
' ~
--
-- -
MapLocabon ICuraeTes4Method`~-...•~,i ~ { TMslest~sgdoessotprec45dett}e~ssshnACgthatthesaAOShoSSrnxasp'r~a'1~mag424cASer~edby4u43se
consiruc6on actrvnles or rainfall events The compaction tests were performed at the approximate
Attached I D lial D y Avg Std ~ ~ locations and elevations shown and indicate relative compaction at those locations Horizontal and
Count Densities vertical limds of the compacted area were determined by others Ourhrm does not guarantee earthwork
i Daily Avg Std
I Count moisture i ~ ; t or paving construction nor does our work relieve the con Vactor s resoonsibiliry to conform to the
~ approvetl protect plans and specifications
To the best of my knowledge the above(~NA WAS NOT performed m accordance with the approved plans speu6cahons and regulatory requirements
Superintendent/Representative ~ Techmaani(~1 ~ ~ ~~ ~~t
~ w ti~
i
215 West Dokota Ave Clovis CA 93612 (559! 348 2200 4221 Bnckell $t Onrono CA 91T 1 (909) 974 4400
2205 Coy Ave Bakersfield CA 93307 (661) 837 9200 1501 1 S $f NW Suik 106 Avburn WA 98002 (253) 939 2500
1025 Lone Polm Ave #2E Modesro CA 95351 f209J 572 2200 20714 Srote Hwy 305 NE Svrte 3C Poulsbo WA 98370 (360/ 59B 2726
545 Parron St San lose CA 951 12 !408) 271 2200 19501 144 Ave NE #F 300 Woodinville WA 98072 (425) 485 5519
5808 Price Ave 81dq 1016 McClellon CA 95652 !9161 564 2200
-~ _~
~~~c`~1 & Associates, Inc
FIELD REPORT NO '' ~ ~ ~ 2
G[CirCN diGL LnGn uEwr i E u _„r r ir.. Fr, ai,[~.u _
G. i~rrnilr nr,c Arn lr ~~ i_~
DATE ~ /~/-~C
PROJECT ~~.+,~ /~~~ >r~~~~
i
LOCATION %/,n i ~/~~
KRAZAN PROJECT MANAGER cA5
CONTRACTOR ~ /mar ~r~G„ r~/' ~~/i~<
JURISDICTION ~` ~ r r, /,,.,
PERMIT # ~- </_~ ~'~ , L
INSPECTOR ,(~,~ ~J~,,,,~
WEATHER ~LI~Ai,r TEMP %>'~L
/~ / / ~/
EgwpmenUAsset Number(s)
To the best of my knowledge the a'aov WAS dA5 NOT performed in accordance wirh fhe approved pions s eaficahons anc reaulotorv regwremenfs
i
Superintendent/Representative Techniaon /' /
Sen~tng the Western United Stntes
J, = FIELD REPORT NO ~ 5 % ~;
~~e~~~ & Associates, Inc
G[o~e~iluicF~ Erlcin~~air C is ~r lr i i_i F iii unu~
Cci nun~~n fE Ur,~ rl Iri n~-ii~ri
DATE - l r ' ~. ~ CONTRACTOR ~ ,-"- ~ .- I
PROJECT# -_ _~ - -~~" ~ JURISDICTION l ',~
PROJECT 1~ ~ "^ '~ ~ - PERMIT# `~. ~ ~ l - ~ ~ ,
LOCATION + ~ 1 ~ J~ ~ -` P ~ INSPECTOR ~~` ',. ~ ~~
KRAZAN PROJECT MANAGER t ' `" WEATHER ~=\~ J~1\ TEMP 'v ~„`
y
i_ ~
EqurpmenURsset Number(s)
To the best of my knowledge the abov ~/wAS AS NOT performed in acccrdarce wdh the approved plan= specficahons and regulatory requirements
1
Supenntendent/Representative Technlaan ~ I `~\r~ \
4 ` l
i
11
Senrmg t17e Western United States
r V Y Y ~ V~/
Jerome W Morrissette & Associates Inc P S
1700 Cooper Point Road SW #B 2 Olympia WA 98502-1110
(360)352 9456 / FAX (360)352-9990
August 23, 2006
Mr Jtm Gibson, PE
Development Review Engineer
Crty of Yelm
PO Box 479
Yelm, WA 98597
R
FcFitr
~~~~`~~r,II ~0
Re Ridgehne Junior Htgh School/STEP tank
Installatton/Flotatton/revtstons for tank
location
Dear Mr Gtbson
This letter and its attachment are intended to address the installation of the STEP Tank
installation at Rtdgehne Middle School and to obtain Ctty of Yelm approval
As you know a specific plan and detail was developed for installation of the tank and the plan,
detatl, and calculations were submitted to you for review and obtained Ctty of Yelm approval
The plan, detatl, and calculations addressed flotation and conformance the tank manufacturer's
mstallatton requirements The plan and detatl called for tank installation m a parking lot island
with a 4 Inch thick concrete slab above the tank The tnstallatton in the parking lot tsland was
rntended to increase the total depth of cover over the tank and the 4 inch thick concrete slab was
rntended to add weight to the tank cover materials The design of the 4 inch concrete slab and
the parking lot tsland provided for extending the slab at least 1 foot beyond the overall length
and overall width of the tank m accord with the manufacturer's recommendations A copy of
this Ctty of Yelm approved plan and detail were provided to the Contractor
Although the Contractor managed to install the tank in accord with the manufacturer's
recommendations for excavation, dewatenng, and materials, the installed location did not
conform to the plans and details This problem became apparent when the Contractor attempted
construct formwork for the tsland and discovered that one of the pump risers would have been
located m a curb ramp m the tsland At this point the Contractor shifted the island curb northerly
and shifted a curb tine opposite the tsland northerly to obtain adequate tank cover while
maintaining pavement width The concrete curbs were constructed in these locations and the
area around the tsland was paved We mvesrigated the situation and found the installation
would have had two problems First, the relocated curb would not have allowed construction of
the concrete slab to extend 1 foot beyond the overall length and width of the tank Second, the
concrete curb was constructed low so that the tank would have several inches less cover than the
plan and detail called for Without correction, the tank flotation calculations would be mvahd
Mr Jim Gibson, PE
August 23, 2006
Page 3 of 3
surface of the portion outside the curb must meet the finished surface of the pavement
The as-built location of the STEP line END OF LINE CLEANOUT it too close to the end of the
monolithic slab and will result m asphalt pavement farlure unless the cleanout is relocated
Further, with the as-built location of the cleanout the monohth~c slab is at nsk should
maintenance of the cleanout valve or other cleanout maintenance be requued We recommend
that the pipe launch port and valve be moved as shown on the plans and details
Given the short timeline to accomplish this work and the adverse impact to the School D~stnct if
the construction does not comply with our revised detarls, we recommend that a Jerome W
Momssette & Associates inspector be present at all times dunng construction of the concrete
slab
We are very eager to obtain City of Yelm approval Should you have any questions or
comments, please do not hesitate to contact me
Very truly yours
Jerome W Momssette & Associates Inc , P S
Doug Ek~Pttrrnd, P E
Senior Protect Engineer
Attachments
Cc Mr Erhng Brrkland, Yelm Community Schools
'~ JWM~A
Jerome W Morrisseffe & Associates Inc P S
1700 Cooper Point Road SW #B 2 Olympia WA 98502 1110
(360)352 9456 / FAX (360)352 9990
August 23, 2006
Mr Jim Gibson, PE
Development Review Engineer
Crty of Yelm
PO Box 479
Yelm, WA 98597
R
qp 2~~~~FO
1pp6
Re Ridgelme Junior High School/STEP tank
Installation/Flotation/revisions for tank
location
Dear Mr Gibson
This letter and its attachment are intended to address the installation of the STEP Tank
installation at Ridgehne Middle School and to obtain Crty of Yelm approval
As you know a specific plan and detail was developed for installation of the tank and the plan,
detail, and calculations ware submitted to you for review and obtained Crty of Yelm approval
The plan, detail, and calculations addressed flotation and conformance the tank manufacturer's
installation requirements The plan and detail called for tank installation m a parking lot island
with a 4 inch thick concrete slab above the tank The installation in the parking lot island was
intended to increase the total depth of cover over the tank and the 4 inch thick concrete slab was
intended to add weight to the tank cover mater:als The design of the 4 inch concrete slab and
the parking lot island provided for extending the slab at least 1 foot beyond the overall length
and overall width of the tank m accord with the manufacturer's recommendations A copy of
this Crty of Yelm approved plan and detail were provided to the Contractor
Although the Contractor managed to install the tank in accord with the manufacturer's
recommendations for excavation, dewatermg, and materials, the installed location did not
conform to the plans and details This problem became apparent when the Contractor attempted
construct formwork for the island and discovered that one of the pump risers would have been
located m a curb ramp m the island At this point the Contractor shifted the island curb northerly
and shifted a curb line opposite the island northerly to obtain adequate tank cover while
maintaining pavement width The concrete curbs were constructed m these locations and the
area around the island was paved We investigated the situation and found the installation
would have had two problems First, the relocated curb would not have allowed construction of
the concrete slab to extend 1 foot beyond the overall length and width of the tank Second, the
concrete curb was constructed low so that the tank would have several inches less cover than the
plan and detail called for Without correction, the tank flotation calculations would be invalid
Mr Jim Grbson, PE
August 23, 2006
Page 3 of 3
surface of the portron outsrde the curb must meet the finished surface of the pavement
The as-built locatron of the STEP line END OF LINE CLEANOUT rt too close to the end of the
monolithic slab and will result m asphalt pavement failure unless the cleanout rs relocated
Further, wrth the as-built location of the cleanout the monolithic slab rs at nsk should
maintenance of the cleanout valve or other cleanout maintenance be required We recommend
that the pipe launch port and valve be moved as shown on the plans and details
Gwen the short ttmelme to accomplish this work and the adverse impact to the School District rf
the construcrion does not comply with our revised details, we recommend that a Jerome W
Momssette &Assocrates inspector be present at all trines during constructron of the concrete
slab
We aze very eager to obtain Crty of Yelm approval Should you have any questions or
comments, please do not hesitate to contact me
'" Very truly yours
Jerome W MomsseQtte~& Assocrates Inc , P S
~C2c.5~~~'Yfi~---'~.
Doug Ek d, P E
Senior Protect Engineer
Attachments
Cc Mr Erhng Brrkiand, Yeim Community Schools
~~4~`"E~ City of Yelm
~~~~~
Community Development Department
]05 Yelm Avenue West
P O Box 479
Yelm, WA 98597
August 23, 2006
Erling `Rocky' Birkland, Facilities Director
Yelm Community Schools
P O Box 476
Yelm, WA 98597
Rocky
In anticipation of the start of school on September 5, 2006, the Community
Development Department met with you this morning to review outstanding issues
related to the use of the new and remodeled High School buildings and the new
Ridgeline Junior High School
Dunng the course of the meeting, we addressed the larger issues surrounding the
protects and the timing of implementation of required improvements, including those
regwred for issuance of a Temporary Certificate of Occupancy and then final Certificate
of Occupancy for each site
Yelm High School
In order to issue temporary Certificates of Occupancy for Buildings 100/200, the
following must be accomplished
/ The temporary parking plan that was discussed at the meeting between the
District and the City on August 11, 2006, should be approved, in writing
/ The Public Works Department needs to inspect and final the water and sewer
infrastructure The City Engineer has requested a final punch list from Public
Works for both water and sewer and will provide the punch list to the Distnct as
soon as it is available
To issue final Certificates of Occupancy for the buildings at the High School site, the
following must be accomplished
/ All conditions of the land use approval and Mitigated DNS must have been met
Ridgehne Junior High
The District proposes to open the school year using only the 100 to 600 wings, except
the 300 wing, and not the 200 wing (Gym faality) In order to issue Temporary
Certificate of Occupancy, the following items must be addressed
/ A copy of the approval to occupy from the State Fire Marshal must be provided to
the Building Official
(360) 458 3835
(360) 458 3]49 FAX
wmtu m yelm wo us
/ A copy of the approval by the Thurston County Health Department must be
provided to the Building Official
/ The 100 to 6000 wings, except the 200/300 wings, must be given final approval
by the Building Official There does not appear to be any mafor outstanding
issues relating to budding codes at this time
/ The Public Works Department needs to inspect and final the water and sewer
infrastructure The City Engineer has requested a final punch list from Public
Works for both water and sewer and will provide the punch list to the District as
soon as it is available
/ As of today, there are a number of trip hazards on the site where landscaped
areas have not been graded to the top of adtacent sidewalks or walkways
/ The concrete cover over the STEP tank was not installed as designed A
revision must be submitted to the City Engineer for approval and installed
pursuant to the revised approval
/ The temporary Certificate of Occupancy may be issued even if the commons
area and kitchen within the 300 wing are not complete, provided that access to
this area is controlled and an access control plan is submitted to the Building
Official, that a modified exiting plan is submitted to the Building Official, and the
fire suppression and alarm system covers 100% of the building
The following items are required before issuance of final certificate of occupancy for the
any building at the School site
/ All conditions of the land use approval and Mitigated DNS must have been met
/ The off-site transportation system improvements required by the Mitigated DNS
on SR 507 must be installed and approved no later than July 31, 2007
/ It appears that the parking lot was not striped pursuant to the approved plans and
contains more compact spaces than allowed
/ Landscaping must be installed pursuant to the approved landscaping plans
Otherlssues
You requested that the District be allowed to connect the irrigation system at Ridgeline
to a fire hydrant to irrigate two fields and landscaping until the site is connected to
Reclaimed Water This request is approved subtect to the following conditions
/ All potable water is metered and paid for by the District at potable water rates
/ An approved backflow prevention device with up to date certification be installed
and maintained between the hydrant and the connection to the irrggation system
at all times
/ The area surrounding the temporary hydrant connection be secured in a manner
approved, in writing, by the Public Works Department
August 23 2006 Page 2 of 3
/ The connection is not authorized after September 26, 2006, unless extended, in
writing, by the Community Development Department
As soon the reclaimed water system is charged at the Htgh School, you may schedule
the dye test through Kevin Ray at the Public Works Department Upon successful
completion of the dye test and certification of the cross connection control program on
the site, but before beneficial use of reclaimed water on the property, Stephanie Ray will
provide a reclatmed water users agreement for the Districts execution I spoke with
Kevin Ray after our meeting this morning and he stands ready to conduct the dye tests
upon your request
The City is holding proceeds from an assigned savings from Hawks Landing for use by
the District in construction of improvements on SR 507 At the point that construction
plans are approved by the Washington State Department of Transportation and a
contract for the construction has been executed by the District, the Ctty will release the
funds to the Distract A letter requesting release of funds to the Community
Development Department at the time the contract is executed will serve as a the
mechanism for the City to process a warrant
During the meeting you indicated that buses would be entering Rtdgeline from 107"'
Street, using Mill Road and the intersection of Mdl Road and SR 507 After the meeting,
you telephoned to let me know that you had followed on this issue with the Districts
Transportation Office and that no buses would be making a left hand turn from SR 507
onto Mill Road As you know, the reason that the Mitigated DNS did not require any
improvements to Mdl Road was because the District had indicated that no buses would
be using this intersection This was noted in both the MDNS and the land use approval
issued for Rtdgeline Junior High Thank you for quickly addressing this concern
If you have any questions regarding the above information, please don't hesitate to
contact me at the Community Development Department
Sincerer ~ _
t of Communty Development
c Shelly Badger, City Administrator
Tim Petersen, Public Works Director
Stephanie Ray, Protect Manager
August 23 2006 Page 3 of 3
Ridgeline Middle School Punch List
25/August/2006
1 There is a sewer lid on the water valve box at carter street entrance
2 The valve box for the fire hydrant at station 5+82 89 needs to be
vacuumed out
3 The fire hydrant at station 3+00 OO looks like it may be too low when
the landscaping is done
4 Ensure fire hydrant that is near the domestic water meter is at proper
height when landscaping is complete
5 The valve box at station 7+17 OS needs to be vacuumed out
6 There are no bollard install around the fire hydrant at station 13+12 45
as the prints shows
7 There are no bollard install around the air release as the prints shows
8 The air release needs to be raised to final grade of the landscape
9 The irrigation system needs to be removed from the fire hydrant at
station 9+06 69
10 The fire hydrant at Mill Pond Middle School m back by the play
ground needs the ground to be butlt up around the hydrant and the fence m
front of rt to be moved behind the fire hydrant DANGER THIS HYDRANT
C-ty of Yelm Water Department
COiJLD BE DANGEROUS This hydrant is not accessible to fire
department in this state
11 Mill Pond School now REQUIRES a Reduced Pressure Backflow
Assembly now that rt has Reclaimed water on this property
12 The Reduced Pressure Backflow Assembly hot box at Ridgeline
School needs power to tt
City of Yelm Water Department
J - '~
~~-c~
Yelm High School Punch List
25/August/2006
1 Need to put chains on the fire hydrants two and a half ports caps at the
entrance of the ball fields
2 Need to put chains on the fire hydrants two and a half ports caps at the
entrance of the Gym
3 Need to put chains on the fire hydrants two and a half ports caps at the bus
and car entrance of the Yelm High School
4 The fire hydrant at inter circle needs to be raised to finished grad of
the landscape
5 Two gate valves need to be place m concrete, see details on prints
A One is at the fire hydrant at the entrance for the busses and cars
B Two is at the inter circle
6 I have not seen to BACTERIC TEST RESULTS for the ten inch fire
They should know Friday the twenty fifth
7 The new fire hydrant on the ten main does not have the Stroz's fitting
on yet I do know they have
8 The ten inch fire main is not turned on yet
ti
n
~t
~~~~
~ _ ,
`~~- .,
5747E OF 1145HINGTON
DEPART~1ENT OF HEALTH
OFFICE OF C1'\ IhONMF'~'T4L HEaLTH 4N~) tiAFCTI
Ia00 LVc c( Fuurfh Ai cnuc $w!c -003
Spud ua IYaifunrtrm )V2f14 ]GIG
Apnl 14, 2006
Ms Stephanie Ray, Project Manager
City of Yelm
PO Box 479
Yelm, Washington 98597
Dear Ms Ray
RE City of Yelm, Thurston County, Construction Documents for Reclaimed «'ater
Imgauon at Ridgelme Middle School, DOH Project R06-006
Construction drawings for the Ridgehne Middle School imgation protect were received
m our office on Apnl 10, 2006 An initial review of these construction documents has
been completed, and the following comments and concerns have been identif ed
1 Engmeenng Report An engmeenng report is required per the Watef Reclnnuufon
and Reuse Standards, Section I, Amcle 8 1 c(5) either as a stand alone report or
by reference to a previously approved engmeenng report The report must
address at a minim the following issues
a A detailed water balance and imgation plan
b Reclaimed water system hydraulics, including water demands pipe sizing
system pressures and hydraulic transient condmons that will likely affect
the system
c Cross connection control and backflow prevention considerations
d The identification of the specific area to be serviced by this system
expansion
e Use area and user protections, notifications, and /or warning signs
2 Construction Specifications Construction specifications need to be provided
3 Sheet CO 0 The sheet submitted appears to be draft A final version of this sheet
is necessary for final approval
4 Sheet 3 7 RW
a Please descnbe the intent behind the 305 If- 1"diameter reclaimed i+ater
line e~.tension at the northwest portion of the site especially the potential
for reclaimed water use m the adjacent residential lots to the north of the
r+
n
6J
Ms Stephanie Ray, City of Yelm
Apnl 14 2006
Page 2 of 3
srie and potential for hose-to-hose cross connection between the reclaimed
water ]me an potable pipelines at the Rtdgehne Middle School Site
b The potable water line e>,tending around the Elementary School changes
from `water' to `fire', which is a nonpotable use To do so, some sort of
isolation or backflow prevention from the fire line system with the potable
systems Is necessary
c Construction Notes
i [ 1 ] & [5] -Note that Watet Reclmnahon and Reuse Stanclmds
define acceptable shades for color coding of reclatmed water
pipelines and facilities The `purple color' shall be the shade
Pantone 512 or 522 or a shade acceptable to the Departments of
Ecology and Health
u [4] -Please provide Project Manual Volumes 1 and 2
d Reclamation Identification Signs Note that this srte must be provided
with a sufficient number signs to inform users of the use of reclatmed
water at the srte It is suggested that the signs inform site users that
'reclaimed water is being used to conserve the potable water supply and
wain against consuming any type ofnon-potable water
Sheet 3 8RW
a Note that all references to "recyc]ed water" m the drawings and for
imgation system labels must be changed to "reclaimed water' Recycled
water is a regulatory term used m California, and is generally taken to
mean water that is recaptured and reused within an industnal process for
mtemal water conservation, which is not subject to water reclamation and
reuse regmrements
b Please descnbe means to assure that the buned hose bib is not subject to
intrusion by ground water or subject to uncontrolled discharge or leaking
that could result in flooding or runoff The concern is that the hose bib is
normally out of site, and either of these situations could possibly result m
a violation of the terms of the reclaimed water permit held by the Gty
c The specification for `purple color' must be consistent the specifications
as notea above
Sheet L3 0 Please provide the basis of design for the reclaimed water booster
station and Identify at a minimum the rated flow capacity and head and motor
horsepower and efficiency
Sheet L3 3
a Note I Note that the potable and reclatmed water system purveyor m this
area is the City of Yelm, not a water distnct ]n addition, note that the
regulatory requirements are Imposed through city ordinances, and not any
rules or regulations, which are normally administered by state or federal
agencies
b Note 2 Please also address separation between reclaimed water pipes and
sanitary sewers
c Note 4 Please provide approval of or concurrence with these construction
documents from the water system purveyor's cross connection program
'~ Ms Stephanie Ray, City of Yelm
Apnl 14, ?006
Page 3 of 3
d Note 6 The imgat~on system operation must be consistent +vith the
~mgaUon plan required per Comment #1, above
e Notes 8 and 10 Please assure that the color codes are consistent wrih
specifications noted previously
f Note ] 0 Please note that the ID tags and all other informational and
warning signs on the site need to be approved by both regu]atory agencies
Please feel free to contact meat (509) 456-2466 or via email at cram, rilev cc doh wa ;ov ~f
you have any questions regarding this concerns
Srncerely,
,1~1't~
Craig L eye, PVE
Office of Environmental Health ~C Safety
Water Reclamation & Reuse
cc Thurston County Health Department
Jerome Momssette ~C. Associates, Olympia
Glenn P~entz, WA Dept ofEcology, SWRO, Lacey
Caty of Yelnz
IO.i Yetm Avenue West
P O Box 479
Yelm Washington 9897
(360) 458-3244
February 13, ?006
Craig L Rtlcy, P E
\Vater Reclamation R Reuse Sectron
Oftice of Envrronmcntal 8.. Health Satety
Washington State Department of Health
1500 \Vest 4°i Avenue, Suite 403
Spokane, \VA 99204
RE Ctty of Yehn -- R1V \Vater to Ridgclinc School
Dear Craig
Regatdme the connection of the new Rrdgelme Ahddle School to the city's rcclamred
water system, the Cny has detennuxd that the installation of the RPIIA s will be installed
on the sen ice lines of the school dtstnct and not on the fire loop As a result, the fire flow
pressures will not be reduced Cross connection control requirements are still being met
and the Cdy s potable eater service to the school bwidmg remains protected
This decision ~sas made m concurrence wrih Tun Peterson, Public \Vorhs Director and
Key m Ray, Cross Connection Control Specrahst
Sincerely,
i~ f/~7
Stephanie Ray
Protect Manager
Cc Tom Skdhngs, Skilhngs/Connolly
Jun Gibson, Ctty ofYelm
Tnn Peterson, Crt} ofYelm
Kcvm Ray, City ofYelm
Tire City of Yehn rs an Equat Opportunity Provider
7
,~
WEISMAN
DESIGN GROUPY
April 25, 2006
Mr Stan Zielinski
Erickson McGovern Architects
120 131st Street South
Tacoma, WA 98444-4804
Re Department of Health Review Comments
Ridgehne Junior High Reclaimed Water
Yelm, Washington
Dear Stan,
REC~IVcQ
MqY 1 ~ 1000
LANDSCAPE
ARCHITECTURE
I am m receipt of a letter from Craig L Riley, P E of the Office of Environmental Health and Safety This letter was
originally sent to Stephanie Ray at the Gty of Yelm and has been forwarded [o us as~i[ contains review comments
specifically relating to [he landscape sheets Our responses to the comments on [he landscape sheets are as follows
la _ Adetailed irrigation plan has atready been submitted, revised plans aze enclosed
The basis for the design of the booster pump was the pressure and flow mformauon provided to us by
Skdlmgs/Connolly, as well as design of the water extension provided by JWMA Based on that mfoimatton and the
agreed upon flow rate a[ Ridgelme Junior Htgh of 100 gpm, and 54 psi static pressure, we determined that pressure
loss to the pump of 21 4 psi and a pump outlet pressure requirement of 66 I psi Thts results in a required boost at
_[he pump of 33 5 psi Attached is [he specification for the pump indicating flow rate, maximum boost and power
requirements
7a Note # 1 indicating the water purveyor has been corrected as requested
76 Note #2 has been modified to also address separation between reclaimed water pipes and sanitary sewers
7c Note #4 has been modified to require the contractor to obtain approvals of the installation from the City
7d System operation run times indicated m note #6 are consistent with the designed plan as submitted
7e Notes 8 and 10 have been modified to indicate requirement for the correct color coding of purple pipe
7f Note 10 has been modified to indicate the requirement for approval of aII~ID tags and warning signs by both
regulatory agencies
Enclosed are pump specifications as well as plans reflecting the modifications described herein If you have any questions
or comments on the above, or require additional information from us, please feel free to give me a call
Sincerely,
Dave Andrews, ASLA
WEISMAN DESIGN GROUP, INC , P S
DA/Jma
Cc Mr Bob Tausher. Morrisette & Associates
WEISMAN DESIGN CROUP INC, PS 2329 EAST MADISON STREET, SFATRE, WASHINGTON 98112 5416 PHONE 206 3221732 FAX 206 3221799 WWW WDGINC COM
FloBoy Pumping System Proposal
Date 4/3/2006
Quotation - 1614
Customer Name
Project Name Ridgelme JHS
FloBoy Fixed Speed Booster Pumping System, Model FBSBF4SH5D46R3AC rated for 100 GPM at 40 PSI Boost Minimum
suction pressure to be 30 PSI Discharge pressure to be 70 PSI Motor is 5 HP 3600 RPM Full voltage horizontal NEMA faced
ODP Pumps shall have stainless steel casing stainless steel enclosed impeller and mechanical seal A schedule 40 full-flow
bypass line with check valve will be provided Electrical power shall be 460 volts, 3 phase, 60 Hertz
Standard Construction wdl include
• Marine grade aluminum enclosure
• Lockable access cover
• Enclosed ventilation fan
e Electrical fusible disconnect
• 3 m flanged suction and discharge connections wdh zinc plated piping
• 3 in epoxy-coated pressure control valve with pressure reduang pilot and backcheck
• 2 5/8 in silicone filled pressure gauges with isolation valve
• Factory run testing using actual suction pressure, discharge pressure and flow conditions
• U L listed NEMA 12 control/ starter panel
• Suction pressure gauge
• Programmable "Smart Relay" industrial grade controller with operator intertace
• Power Monitor -Under/ Overload Under/ Overvoltage Protection
• On/ Off /Auto selector switches
• Low/ High discharge pressure shutdown and alarm
• Solid State overload/ single phase/ phase imbalance/ low voltage protection
• 5 HP across the line NEMA starter
• 24 volt AC relay for starting and stopping
e 3 in station discharge isolation valve with individual pump suction & discharge isolation valves
• Full Flow Bypass System
• 1 CD -FloBoy operation & maintenance manual
• 1 Printed copy of the FloBoy operator ~ maintenance manual
0 1 year limited warranty
JWMBA
Jerome W Morrissette & Associates Inc. P S _
1700 Cooper Point Road SW, #B-2, Olympia, WA 98502 1110
(360) 352-9456 • (360) 352 4990
LETTER OF TRANSiWITTA~
TO Mr hm Gibson, P E
Community Development Engineer
City of Yelm
105 Yelm Avenue W
P O Box 479
Yelm, Washington 98597
JOB NO 03157
DATE May 17, 2006
SUBJECT Yelm Ridgehne Middle School
Reclaim Water Design DOH Protect R06-006
Revised Plans
I am enclosing for you the attached items
~~
~e~ F
~ COPIES DATE DESCRIPTION
Apnl, 2006 Revised Civil Sheet CO ORW C3 7RW and
C3 8RW L3 0 through L3 7
April 5, 2005 Project Manual Volume 1 and 2
DOH comments and concerns from the Apnl 14, 2006 letter to Gty of Yelm aze fisted below
with my responses provided in italics, directly below each item
Engmeermg Report An engmeenng report is required per the Water Reclamation and
Reuse Standards, Section 1, Article 8 I c{5) either as a stand alone report or by reference
to a previously approved engmeenng report The report must address at a minim the
following issues
a A detailed water balance and imgaUon plar» 2 s ~< <~a~7
A detared rrrrgatron plan has already been subrfl:tted, revrsed plans are enclosed
b Reclaimed water system hydraulics, including water demands, pipe sizing, system
pressures and hydraulic transient conditions that will likely affect the system
Response provrded by the Crty of Yelm ?
c Cross connection control and backflow prevention considerations
Crvd / Munrapal / Gaotechnical Engmeermg and Planning
An RPBP devrce has been rnstalled downstream of the domestic water meters on the
Rrdgehne Middle School A RPBP devrce wdl also be mstahed downstream of the
domestic water meter ~... --.~o Marti Potiz Nail ~l~ Sc l
d The identification of the specific azea to be servtced by flits system expansion
The specrfc area serviced is the Yelm School Drstrrcl property only Thrs includes the
Mill Pond Elementary School and Ridgeline Meddle School
e Use area and user protections, notifications, and /or warning signs
Use area, user protection and warning rrgns will be rnstalled as required
0~2 Construction Specifications Construction specifications need to be prowdGd. r~d-r P Iah S
Constructions Specifications included on the plans
Sheet CO 0 The sheet submitted appears to be draft A final version of this sheet is ~ (a,2s
p~ necessary for final approval s
Sheet CO 0 submitted has been revised to CO ORW
Sheet 3 7 RW
a Please describe the intent behind the 305 if - 1" diameter reclaimed water tine ~
extension at the northwest portion of the site, especially the potential for reclaimed A i ~ ~C~
water use m the adjacent residential lots to the north of the site and potential for hose- //
~~ to-hose cross connection between the reclaimed water Ime an potable pipelines at the
~Z' Ridgehne Middle School Site
~t~ ~ od The 305 lfof I-inch lane is for a hose bib the City has requested to perform r
\ ~J maintenance of the STEP tank A required 6-inch air gap was included on the
~ hose bib detail with the locking cover for Crty use only
b The potable water Lne extending azound the Elementary School changes from 'water'
to 'fire', which is a non potable use To do so, some sort of isolation or backflow
prevention from the fire line system with the potable systems is necessary
The tine m question is an existing watermain loop which is labeled water and fire
The tine looping around the school rs the watermain tine to the fire hydrants and
potable water to the school wish backflow prevention
c Construction Notes
i [1] & [5] -Note that Water Reclamation and Reuse Standards define
~ acceptable shades for color coding of reclaimed water pipelines and
facilities The 'purple color' shall be the shade Pantone 512 or 522 or a
shade acceptable to the Departments of Ecology and Health
911 purple callouts have been revised to reyurre the Pantone 512 or
522 or a shade acceptable to the Departments of Ecolog}~ and Health
s~ a [4] -Please provide Project Manual Volumes 1 and 2
b Copies of Volume I and 2 are included ivrr~lhrs submittal
d Reclamation Identification Signs Note that this site must be provided wrth a
sufficient number signs to inform users of the use of reclaimed water at the site It is
suggested that the signs mforni site users that 'reclaimed water is being used to
~a[Qa
i5f.~a
t''' ~ e•-
s,+e z a~.~
~t~r``
Crvd / Municipal / Geotechmcal Engmeenng and Planning
2
conserve the potable water supply and warn against consuming any type of non-
potable water z•~ d S r p a s a.-r ~l ~t p l u c,r d ~,. l 4// to n~~c>~
Identification tags n Jude an the trrtgatton plans /
5 Sheet 3 8RW
a Note that all references to "recycled water" m the drawings and for
e~V imgation system labels must be changed to "reclaimed water" Recycled water is a
regulatory term used m California, and is generally taken to
mean water that is recaptured and reused within an mdustnal process for
internal water conservatwn, which is not subject to water reclamation and reuse
requirements
Reference to recycle water has been revised to reclAim
Please descnbe means to assure that the 'boned hose bib is not subject to
intrusion by ground water or subject to uncontrolled dischazge or leaking that could
result m flooding or runoff The concern is that the hose bib is normally out of sne,
and either of these snuahons could possibly result m a violarion of the terms of the
reclaimed water permit held by the City
A required 6-inch air gap was included on the hale bib detail with the locking
cover for Crty use only ~ ,.~ ~ ~{~ ~~,~,~ ! 2 <~ M,L 9ct~ z~~ ~,,~,,,~
c The specification for 'purple color' must be consistent the specifieanons as noted
~~L above
All purple callouts hare been revised to require the Pantone ~ 12 or .i22 or a
shade acceptable to the Departments of Ecology and Health
6 Sheet L3 0 Please provide the basis of design for the reclaimed water booster station and
idenrfy at a minimum the rated flow capacity and head and motor horsepower and
~\V efficiency
The basis for the design of the booster pump was the pressure and flow information
provided to us by Skrllrngs/Connolly, as well as design of the water extension
provided by JWMA Based on that rnformahon and the agreed upon flow rate at
Rrdgelrne Junior Hrgh of 100 gpm, and 54 psi static pressure, we deter mined that
pressure loss to the pump or21 A psi and a pump outlet pressure reyurrement of
66 1 psi Thrs results zn a required boost at the pump of 33 S psi Attached is the
speczficauon for the pump indreahng flow rate, maximum boost, and power
requirements
7 Sheet L3 3
~~~ a Note 1 Note that the potable and reclaimed water system purveyor in this area is the
City of Yelm, not a water distract In addition, note that the regulatory requirements
are imposed through city ordinances, and not any rules or regulations, which are
normally administered by state or federal agencies
Note #1 rnd~cating the water purveyor has been corrected as requested
Gvd / Munrcrpat / Geotechrncel Engrneenng and Planning
3
b Note 2 Please also address separation between reclaimed water pipes and sanitar}
sewers
Note #1 has been modified to also address separation beta een reclaimed water
pipes and sanitary sewers
Note 4 Please provide approval of or concurrence with these construction
documents from the water system purveyor's cross connection program
Note #a has been mod~fred to reyurre the contractor to obtain approvals of the
installation (ram t,_~h~ r~*,=.
it ~~ r ~ays e 4 L cG~-e"e -
Note 6 The imgaUOn system operation must be consistent with the imgation plan
regmred per Comment #], above
System operation run times indicated rn note #6 are consistent with the designed,
plan as submdted
e Notes 8 and ] 0 Please assure that the color codes are consistent with specifications
noted previously
~ ~~- Notes 8 and 10 have been modified to rnduate requirement jor the correct color
coding of purple pipe
Note 10 Please note that the ID tags and all other informational and warning signs on
the site need [o be approved by both regulatory agencies
Note 10 has been modified to rndreare the requirement for approval of a!1 ID tags
and warning signs by both regulatory agencies
Enclosed are pump specifications as well as plans reflecting the modifications descnbed herein
If you have any questions, please contact me at (360) 352-9456
Very truly yours,
Jerome W Mornssette & Associates Inc , P S
SIGNED
Robert Tauscher, P E
Project Engineer
Cc Mr Citing Bvkland Facthucn Operations Yelm Community Schools P O Box 476 Yelm WA 98597
Mr Stan Gehnsl.i Archnec~ Enc}son McGoi~rn 120 131" Street S racoma. WA 98444 4804
C lnob\03157 Yelm Ridgehne Middle SchoollCorrespondance\OSI70G Transmit Gry Rermons to UGH Reclaim Letter DCK
Crod / Municipal / Georechmcal Engmeenttg end Planning
JWMBA
Jerome W Morrissette & Assoaates Inc . P S
1700 Cooper Point Road SW, t1B-2, Olympia, WA 98502-1110
(360) 352-9456 • (360) 352-9990
LETTER OF TRANSMITTAL
TO Mr Jiiri Gibson, P E
Commumty Development Engineer
City of Yelm
105 Yelm Avenue W
P O Box 479
Yelm, Washington 98597
JOB NO 03157
DATE• May 17, 2006
SUBJECT• Yelm Rrdgelme Middle School
Reclaun Water Design, DOH Protect R06-006
Revised Plans
I am enclosing for you the attached items
AYI F~VFQ
1006
DATE DESCRIP~TpIO~N
Apni, 2006 Revi~-s d Civil Sheet CO ORW, C3 7RW and
C3 8RW L3 0 through L3 7
Apn15, 2005 Protect Manual Volume 1 and 2
DOH comments and concerns from the Apnl 14, 2006 letter to City of Yelm are fisted below
with my responses provided in italics, directly below each item
Engmeenng Report An engineenng report is regmred per the Water Reclamation and
Reuse Standards, Section I, Article 81 c(5) either as a stand alone report or by reference
to a previously approved engmeenng report The report must address at a mimm the
following issues
a A detazled water balance and imgation plan
A detailed irrigation plan has already been submitted, revised plans are enclosed
b Reclauned water system hydraulics, including water demands, pipe sizuig, system
pressures and hydraulic transient conditions that will likely affect the system
Response provided by the City of Yelm
c Cross connection control and backflow prevention considerarions
Crvd / MunMrpal / Geotechnical Engmeenng end Planrnng
1
An RPBP device has been Installed downstream of the domestic water meters on the
R:dgeltne Middle School A RPBP device will also be installed downstream of the
domestic water meter
d The identification of the specific area to be sernced by this system expansion
The specific area serviced is the Yelm School Dtstrrct property only Thrs tncludes the
Mtdl Pond Elementary School and Rrdgelrne M:ddde School
e Use area and user protections, notifications, and /or waiving signs
Use area, user protection and warning signs will be installed as required
2 Construction Specifications Construction specifications need to be pmvided
Constructions Spec fcations Included on the plans
3 Sheet CO 0 The sheet submitted appears to be draft A final version of this sheet is
necessary for final approval
Sheet CO 0 submitted has been revised to CO ORW
4 Sheet 3 7 RW
a Please describe the intent behind the 305 If - 1 "diameter recleaned water tine
extension at the northwest portion of the srte, especially the potential for recleaned
water use in the adjacent residential lots to the north of the site and potential for hose-
to-hose cross connection between the reclaimed water tine an potable pipelines at the
Ridgelme Middle School Srte
The 3051E of I -rnch lrne is for a hose bib the City has requested to perform r
maintenance of the STEP tank A required 6-rnch err gap was included on the
hose bib detail with the locking cover for City use only
b The potable water line extending azound the Elementary School changes from 'water'
to 'fire', which is a non potable use To do so, some sort of isolation or backflow
prevention from the fire Ime system with the potable systems is necessary
The ltne to questton rs an exrsting watermarn loop whrch rs labeled water and fire
The lane looping around the school rs the watermarn line to the frre hydrants and
potable water to the school with backflow prevention.
c Construction Notes
i [1 ] & [5] Note that Water Reclamation and Reuse Standazds define
acceptable shades for color coding of recleaned water pipelines and
facilities The 'purple color' shall be the shade Pantone 512 or 522 or a
shade acceptable to the Departments of Ecology and Health
All purple caldouts have been revised to require the Pantone 512 or
522 or a shade acceptable to the Departments of Ecology and Health
u [4] -Please provide Protect Manual Volumes 1 and 2
Copses of Volume 1 and 2 are included with this submittal
d Reclamation Identification Signs Note that this site must be provided with a
sufficient number signs to inform users of the use of recleaned water at the site It is
suggested that the signs inform srte users that reclaimed water is being used to
Crvd / Mumdpal / Geotechmcal Engineering and Plartnmg
2
conserve the potable water supply and warn against consuming any type of non-
potable water
Identification tags include on the trr:gat:on plans
5 Sheet 3 8RW
a Note that all references to "recycled water" m the drawings and for
imgation system labels must be changed to "reclaimed water" Recycled water is a
regulatory term used in California, and is generally taken to
mean water that is recaptured and reused wrthiri an industrial process for
internal water conservation, wtuch is not subject to water reclamation and reuse
requirements
Reference to recycle water has been revised to reclaim
b Please describe means to assure that the'buned hose bib is not subject to
intrusion by ground water or subject to uncontrolled discharge or leaking that could
result m flooding or runoff The concern is that the hose bib is normally out of site,
and either of these situations could possibly result in a violation of the teens of the
recleaned water permit held by the Crty
A required 6-tech err gap was included on the hose bib detail with the locking
cover for Crty use only
The specification for 'purple color' must be consistent the specificatrons as noted
above
All purple callouts have been revised to require the Pantone 512 or 522 ar a
shade acceptable to the Departments of Ecology and Health
Sheet L3 0 Please provide the basis of design for the recleaned water booster station and
identrfy at a minimum the rated flow capacity and head and motor horsepower and
efficiency
The basis for the design of the booster pump was the pressure and flow information
provided to us by Skrllings/Connolly, as well as design of the water extension
provided by JWMA Based on that information acrd the agreed upon flow rate at
Rrdgeltne Junior Htgh of I DO gpm, and 54 psi static pressure, we determined that
pressure loss to the pump of 214 psi and a pump outlet pressure requirement of
661 psi Thrs results to a required boost at the pump of 33 5 psi Attached :s the
specification for the pump indicating flow rate, maximum boost, and power
requtrements
7 Sheet L3 3
a Note 1 Note that the potable and recleaned water system purveyor m this area is the
Crty of Yelm, not a water district In addition, note that the regulatory requirements
are imposed through mty ordinances, and not any rules or regulations, which are
normally administered by state or federal agencies
Note #1 indicating the water purveyor has been corrected as requested
Av~l J Municipal / Geotechmcal Engineering and Plemm~g
3
b Note 2 Please also address separation between reclaimed water pipes and samtary
sewers
Note #Z has been modified to also address separation between reclaimed water
pipes and sanitary sewers
Note 4 Please provide approval of or concurrence with these construction
documents from the water system purveyor's cross connection program
Note #4 has been modified to regu:re the contractor to obtain approvals ofthe
installation from the Ctty
d Note 6 The imgahon system operation must be consistent with the imgahon plan
required per Comment #1, above
System operation run times indicated to note #6 are consistent with the deszgned
plan as submitted
e Notes 8 and 10 Please assure that the color codes are consistent with specifications
noted previously
Notes 8 and 10 have been modtfzed to indicate requirement for the correct color
codtng of purple pipe
f Note 10 Please note that the ID tags and all other informational and wainmg signs on
the site need to be approved by both regulatory agencies
Note IO has been modified to indicate the requirement for approval of all ID tags
and warntng stgns by both regulatory agencies
Enclosed are pump specifications as well as plans reflecting the modifications descnbed herein
If you have any questions, please contact me at (360) 352-9456
Very truly yours,
Jerome W Mornssette & Associates Inc , P S
SIGNED
Robert auscher, P E
Project Engineer
Cc Mr Erlmg Bvkland, Facilities Operations, Yelm Community Schools, P O Box 476, Yetm WA 98597
Mr Stan Zielinski Architect, Encksou McGovern, 120 13ti` Street S, Tacoma, WA 98444.4804
C \Bob\03157 Yelm Ridgelme Middle School\Conespondance\051706 Transmd City Revisions to DOH Reclean Letter DOC
Crvd / Munrclpal / Geotechnical Engmeenng and Planning
4
~~
:~ ~rT~ =,
SraTF of tvasttlrvcion
DEPARTh1ENT OF HEALTH
OFFICE OF CV\ II:ONNF\L1L HEALTH a\f1 ~~FFTI
Ii00 tM1 cc1 Rrurlh 4i cnuc Cutlc 403
Spud vu IYnehmf;ton 9x104 7(rG
Apn114,2006
b4s Stephanie Ray, Project Manager
City of Yelm
PO Box 479
Yelm, Washington 98597
Dear Ms Ray
RE Gty of Yelm, Thurston County, Construction Documents for Reclaimed Water
Imgation at Ridgelme Middle School, DOH Project R06-006
Construction drawings for the Ridgehne Middle School imgation project were received
m our office on April ] 0, 2006 An initial review of these construction documents has
been completed, and the following comments and concerns have been identified
Engineering Report An engineering report is requtred per the Water Reclamanori
and Reuse Standal ds, Section 1, Article 8 1 c(5) either as a stand alone report or
by reference to a previously approved engineering report The report must
address at a minim the following issues
a A detailed water balance and imgation plan
b Reclaimed water system hydraulics, including water demands pipe sizing
system pressures and hydraulic transient conditions that will likely affect
the system
c Cross connection control and backflow prevention considerations
d The identification of the specific area to be serviced by this system
e>`pansion
e Use area and user protections, notifications, and /or wammg signs
2 Construction Specifications Construction specifications need to be provided
3 Sheet CO 0 The sheet submitted appears to be draft A final version of this sheet
is necessary for final approval
4 Sheet 3 7 RW
a Please describe the intent behind the 305 lf- 1"diameter reclaimed water
]me extension at the northwest portion of the site, especially the potential
for reclaimed water use m the adjacent residential lots to the north of the
~' Rd
~~ Ms Stephanie Ray, City of Yelm
` Apnl 14 2006
Paee 2 of 3
site and potential for hose-to-hose cross connection between the reclaimed
water hne an potable pipelines at the Rtdgehne Middle School Site
b The potable water hne extending around the Elementary School changes
from `water' to `fire', which is a nonpotable use To do so, some sort of
isolation or backflow prevention from the fire line system with the potable
systems is necessary
c Construction Notes
t []] R, [5] -Note that Water Reclmnanon and Reuse Standards
define acceptable shades for color coding of reclatmed water
pipelines and facilities The `purple color' shall be the shade
Pantone 512 or 522 or a shade acceptable to the Departments of
Ecology and Health
u [4] -Please provide Protect Manual Volumes 1 and 2
d Reclamation Identification Signs Note that this site must be provided
with a sufficient number signs to inform users of the use of reclaimed
water at the site It is suggested that the signs inform site users that
Yeclaimed water is being used to conserve the potable water supply and
warn against consuming any type ofnon-potable water
5 Sheet 3 8RW
a Note that all references to `recycled water" m the drawings and for
imgation system labels must be changed to "reclaimed water" Recycled
water is a regulatory term used m Cahfomia, and is generally taken to
mean water that is recaptured and reused within an industnal process for
internal water conservation, which is not sublect to water reclamation and
reuse regmrements
b Please descnbe means to assure that the buned hose bib is not sublect to
intrusion by ground water or sublect to uncontrolled discharge or leaking
that could result in flooding or runoff The concern is that the hose bib is
normally out of site, and either of these situations could possrbly result m
a vrolation of the terms of the reclaimed water permit held by the City
c The specification for `purple color' must be consistent the specifications
as notea above
6 Sheet L3 0 Please provide the bans of design for the reclatmed water booster
station and identify at a minimum the rated flow capacity and head and motor
horsepower and effiaency
7 Sheet L3 3
a Note 1 Note that the potable and reclaimed water system purveyor in this
area is the City of Yelm, not a water dtstnct In addition, note that the
regulatory requirements are imposed through city ordinances, and not any
rules or regulations, which are normally administered by state or federal
agencies
b Note 2 Please also address separation between reclaimed water pipes and
sanitary sewers
c Note 4 Please provide approval of or concurrence with these construction
documents from the water system purveyor's cross connection program
-~ Ms Stephanie Ray, Ctty of Yelm
Apn114,2006
Page 3 of 3
d Note 6 The imgation system operation must be consistent wnh the
imgation plan regmred per Comment #1, above
e Notes 8 and 10 Please assure that the color codes are consistent with
specifications noted previously
f Note ] 0 Please note that the ID tags and all other informational and
warning signs on the site need to be approved by both regulatory agencies
Please feel free to contact meat (509) 456-2466 or via email at crat,~ nlev ce doh wa _~ov if
you have any questions regarding this concerns
Sincerelyr,
i ~
Craig Leh ey, P E
Office of Environmental Health & Safety
Water Reclamation & Reuse
cc Thurston County Health Department
Jerome Momssette & Associates, Olympia
Glenn Pientz, WA Dept of Ecology, SWRO, Lacey
• 22-141 50 SHEETS
(_PAO 22 142 100 SnEET9
22 744 200 SHEETS
,r ~
u
~' a
~~
~~
~'
E STATg
~S~'nt>~In ~.n
`~
o
y m
s = z
~'~' o=
`~
~~ I899 oy
~
STATE OF WASHINGTON
DEPARTMENT OF HEALTH
OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY
1500 West Fourth Avenue, Smte 403
Spokane, Washington 99204-1656
Apnl 14, 2006
Ms Stephanie Ray, Protect Manager
Crty of Yelm
PO Box 479
Yelm, Washington 98597
Dear Ms Ray
RE Crty of Yelm, Thurston County, Constmctlon Documents for Reclaimed Water
Imgatlon at Ridgelme Middle School, DOH~Prolect R06-006
Construction drawings for the Ridgelme Middle School imgation protect were received
m our office on :Apnl 10, 2006 An initial review of these construction documents has
been completed, and the following comments and concerns have been identified
Engmeenng Report An engmeenng report is requued per the Water Reclamation
and Reuse Standards, Section I, Artrcle 8 1 c(5) either as a stand alone report or
by reference to a previously approved engineenng report The report must
address at a minim the following issues
a A detailed water balance and imgation plan
b Reclaimed water system hydraulics, including water demands, pipe sizing,
system pressures and hydraulic transient conditions that will likely affect
the system
c Cross connection control and backflow prevention considerations
d The identification of the specific area to be serviced by this system
expansion
e Use area and user protections, notifications, and /or wammg signs
2 Constmctlon Specifications Construction specifications need to be provided
3 Sheet CO 0 The sheet submitted appears to be draft A final version of this sheet
is riecessary for final approval '- ~ '
4 'Sheet 3 7 RW '
a Please descnbe the intent behind the 305 lf- 1"diameter reclaimed water
tine extension at the northwest portion of the site, especially the potential
for reclaimed water use m the adjacent residential lots to the north of the
~~
Ms Stephanie Ray, City of Yelm
Apnl 14, 2006
Page 2 of 3
site and potential for hose-to-hose cross connection between the reclaimed
water line an potable pipelines at the Ridgelme Middle School Site
b The potable water line extending around the Elementary School changes
from `water' to `fire', which is a nonpotable use To do so, some sort of
isolation or backflow prevention from the fire ]me system with the potable
systems is necessary
c Construction Notes
~ [1] & [5] -Note that Water Reclamatzon and Reuse Standards
define acceptable shades for color coding of reclaimed water
pipelines and facilities The `purple color' shall be the shade
Pantone 512 or 522 or a shade acceptable to the Departments of
Ecology and Health
u [4] -Please provide Project Manual Volumes 1 and 2
d Reclamation Identification Signs Note that this site must be provided
with a sufficient number signs to inform users of the use ofreclaimed
water at the site It is suggested that the signs mfonn site users that
'reclaimed water is being used to conserve the potable water supply and
warn against consuming any type ofnon-potable water
Sheet 3 8RW
a Note that all references to "recycled water" in the drawings and for
imgation system labels must be changed to "reclaimed water" Recycled
water is a regulatory term used m California, and is generally taken to
mean water that is recaptured and reused within an industnal process for
internal water conservation, which is not subject to water reclamation and
reuse requirements
b Please descnbe means to assure that the buned hose bib is not subject to
intrusion by ground water or subject to uncontrolled discharge or leaking
that could result in flooding or runoff The concern is that the hose bib is
normally out of site, and either of these situations could possibly result to
a violation of the terms of the reclaimed water permit held by the City
c The specification for `purple color' must be consistent the specifications
as noted above
Sheet L3 0 Please provide the basis of design for the reclaimed water booster
station and identify at a minimum the rated flow capacity and head and motor
horsepower and efficiency
Sheet L3 3
a Note 1 Note that the potable and reclaimed water system purveyor in this
area is the City of Yelm, not a water distnct In addition, note that the
regulatory requirements are imposed through city ordinances, and not any
rules or regulations, which are normally administered by state or federal
agencies
b Note 2 Please also address separation between reclaimed water pipes and
sanitary sewers
c Note 4 Please provide approval of or concurrence with these construction
documents from the water system purveyor's cross connection program
Ms Stephame Ray, City of Yelm
Apnl 14, 2006
Page 3 of 3
d Note 6 The imgahon system operation must be consistent with the
~mgation plan required per Comment #1, above
e Notes 8 and 10 Please assure that the color codes are consistent with
spec~ficahons noted previously
f Note 10 Please note that the ID tags and all other mformat~onal and
warning signs on the site need to be approved by both regulatory agencies
Please feel free to contact meat (509) 456-2466 or via emarl at cra~x nley ~+,doh wa gov if
you have any questrons regarding this concerns
Sincerely,
Craig L ey, P E
Office of Environmental Health & Safety
Water Reclamation & Reuse
cc Thurston County Health Department
Jerome Momssette & Associates, Olympia
Glenn Pientz, WA Dept of Ecology, SWRO, Lacey
Rif STAtE O
c` y v
c ~ Y
y~ ~<
Y
H~ /NP9 wC
STATE OF WASHINGTON
DEPARTMENT OF HEALTH
OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY
1500 West fourth Avenue, Swte 403
Spokane, Washington 99204-1656
Apnl 14, 2006
Ms Stephame Ray, Protect Manager
City of Yehn
PO Box 479
Yelm, Washington 98597
Deaz Ms Ray
RE City of Yelm, Thurston County, Construction Documents for Reclaimed Water
Imgation at Ridgeline Middle School, DOH Prol ect R06-006
Construction drawings for the Ridgelme Middle School imgation protect were received
in our office on Apnl 10, 2006 An initial review of these construction documents has
been completed, and the following comments and concerns have been identified
1 Engineenng Report An engmeenng report is required per the Water Reclamation
and Reuse Standards, Section I, Article 8 1 c(5) either as a stand alone report or
by reference to a previously approved engmeenng report The report must
address at a minim the following issues
a A detailed water balance and imgation plan
b Reclaimed water system hydraulics, including water demands, pipe sizing,
system pressures and hydraulic transient condmons that will likely affect
the system
c Cross connection control and backflow prevention considerations
d The identification of the specific area to be sernced by this system
expansion
e Use azea and user protections, notifications, and /or warning signs
dit 2 Construction Specifications Construction specifications need to be provided ,_ . kart
ot~ 3 Sheet CO 0 The sheet submitted appears to be draft A final version of this sheet
is necessary for final approval
4 Sheet 3 7 RW
a Please descnbe the intent behind the 305 lf- 1"diameter reclaimed water
line extension at the northwest portion of the site, especially the potential
for reclaimed water use in the adjacent residential lots to the north of the
~~
Ms Stephanie Ray, City of Yelm
Apnl 14, 2006
Page 2 of 3
site and potential for hose-to-hose cross connection between the reclaimed
water tine an potable pipelines at the Ridgelme Middle School Srte
b The potable water tine extending around the Elementary School changes
from `water' to `fire', which is a nonpotable use To do so, some sort of
isolation or backflow prevention from the fire tine system with the potable
systems is necessary
c Construction Notes
i [1] & [5] -Note that Water Reclamation and Reuse Standards
define acceptable shades for color coding of reclaimed water
pipelines and facilities The `purple color' shall be the shade
Pantone 512 or 522 or a shade acceptable to the Departments of
Ecology and Health
ii [4] -Please provide Protect Manual Volumes 1 and 2
d Reclamation Identification Signs Note that this site must be provided
with a sufficient number signs to inform users of the use of reclaimed
water at the site It is suggested that the signs inform site users that
'reclaimed water is being used to conserve the potable water supply and
wain against consuming any type ofnon-potable water
5 Sheet 3 8RW
a Note that all references to "recycled water" in the drawings and for
imgation system labels must be changed to "reclairried water" Recycled
water is a regulatory term used m California, and is generally taken to
mean water that is recaptured and reused within an industnal process for
mtemal water conservation, which is not subtect to water reclamation and
reuse requirements
b Please descnbe means to assure that the buned hose bib is not subtect to
intrusion by ground water or subtect to uncontrolled discharge or leaking
that could result m flooding or runoff The concern is that the hose bib is
normally out of site, and either of these situations could possibly result m
a violation of the teens of the reclaimed water permit held by the City
c The specification for `purple color' must be consistent the specifications
as noted above
6 Sheet L3 0 Please provide the basis of design for the reclaimed water booster
station and identify at a minimum the rated flow capacity and head and motor
horsepower and efficiency
7 Sheet L3 3
a Note 1 Note that the potable and reclaimed water system purveyor in this
area is the City of Yelm, not a water distnct In addition, note that the
regulatory requirements aze imposed through city ordinances, and not any
rules or regulations, which are normally administered by state or federal
agencies
b Note 2 Please also address separation between reclaimed water pipes and
samtary sewers
c Note 4 Please provide approval of or concurrence with these construction
documents from the water system purveyor's cross connection program
i,
.~
Ms Stephanie Ray, City of Yehn
Apnl 14, 2006
Page 3 of 3
d Note 6 The imgahon system operation must be consistent wrth the
~mgation plan required per Comment #1, above
e Notes 8 and 10 Please assure that the color codes are consistent with
specifications noted previously
f Note 10 Please note that the ID tags and all other mformat~onal and
wammg signs on the site need to be approved by both regulatory agencies
Please feel free to contact meat (509) 456-2466 or via email at cra~Q nlev~cJdoh wa eov if
you have any questions regarding this concerns
Sincerely,
Craig L y, P E
Office ofEnvrronmental Health & Safety
Water Reclamation & Reuse
cc Thurston County Health Department
Jerome Momssette & Associates, Olympia
Glenn P~entz, WA Dept of Ecology, SWRO, Lacey
RaE sTnrF of
0 6 £
a _ z
ms 2
~Hi 1889 CpY
STATE OF WASHINGTON
DEPARTMENT OF HEALTH
OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY
1500 West Fourth Avenue, Surte 403
Spokane, Washington 99204-1656
Apnl 14, 2006
Stephanie Ray
C[ty of Yelm
PO Box 479
Yelm, WA 98597
Dear Ms Ray
Subject C[ty of Yelm (Recla[med Imgatlon Water at R[dgehne Meddle School)-
, ,. ~ „_ Protect R06-006
The documents for the above project were received [n th[s office Apnl 10, 2006, and are now [n
- L -
the review process RCW 43 208 020 authonzes fees for sernces for the review of engmeenng
plans, reports, and construct[on documents A fee w[ll be charged for the review and approval of
your engmeenng documents You will receive an invoice for payment upon completion of
review and approval of the documents Payment is due at that hme The fee is based on the hme
required to complete the review at a flat hourly rate which is can-ently $50 00 per hour, but is
subject to change
This project has been assigned a unique DOH Protect # (as shown above which you will use
on future correspondence or submittals pertaining to this project
This letter serves as official notice that if you commence constnachon withou[ all required
approvals under Chapter 246-271 WAC, you and any person assisting you maybe subject to a
penalty of up to five thousand dollars per service connection and you may be required to expose
system components for DOH inspection at your expense The Department is under no obhgahon
to accept or approve any component installed or constructed pnor to approval
Sincerely, _
,r r ._.
_ ,f% ,_"
raig-L Riley, P E . ,._ _.; ` _
Water Reclamation & Reuse Program
Environmental Health Division
,C Cr I .'- If'~ 'ti,' ~' - ~L~J .1
cc Thurston County Public Health and Social Services Dept
.'°' iw0
Page 1 of 3
Jtm Grbson
2~usE~P~i b~
From Stephanie Ray
Sent Friday, March 10, 2006 11 28 AM
To Jlm Gibson
Subject FW Minutes 9/26 meeting
FYI
SCI has sent them a set of plans for the RW line pro)ect I am not sure why they would need this
From Tom Sklllings [mailto tskillings@skillings com]
Sent Thursday, March 09, 2006 1 45 PM
To Stephanie Ray
Subject RE Minutes 9/26 meeting
Steph, Is It okay to send the plan set directly to theme If so, we will send a PDF Thanks, T
Skillmgs-Connolly, Inc
Thomas E Sklllings, P E
President
Office (360) 491-3399
Direct (360) 455-3131
www sklllings com
This email (and or documents accompanying it) may contain confidential information belonging to a sender, which is protected by
the consultant-client privilege The information is intended only for the use of the individual or entity named above If you are not
the intended recipient, you are hereby notified that any disclosure, copying, distribution, or the taking of any action in reliance on
the contents of this information is strictly prohibited If you received this email in error, please notify the sender immediately and
delete the documents from your computer
From Stan Zielinski [mailto Stan@erlcksonmcgovern com]
Sent Thursday, March 09, 2006 1 21 PM
To Tom Sklllings
Cc Stephanie Ray, dove@wdgmc com, Rocky Blrkland, Ray Mow, John Erickson, Bob, Jerry Morrissette,
scoff@~wmorrlssette com
Subject RE Minutes 9/26 meeting
We need to co-ordinate the connection between the city's reclaimed water Ilne planned point of connection at Mlll
Road and our 2" meter point of connection which WDG has located along the North Property line @ the NE
corner of the RMS parking lot
Please forward to WDG, EMA and JWMA, the aty's design on Mill Road so that JWMA can complete the design
for that connection
I'm unaware of any plans for a new HS or JHS for YCSD
That s a question for YCSD Rocky or Alan Burke
Thank you,
3/10/2006
Page 2 of 3
Stan Zielinski, EMA
From Tom Skillings [mallto tskillings@sklllings com]
Sent Thursday, March 09, 2006 12 29 PM
To Stan Zielinski
Cc 'Stephanie Ray', dave@wdginc com, 'Rocky Birkland', Ray Mow, John Erickson
Subject RE Minutes 9/26 meeting
Have you gotten everything you need for the Irrigation design at the schools
Also, on another sub]ect, does the Yelm School District have long range pro)ections when a
new high school or middle school will need to come on line based on population of the areas If
you have any such forward looking pro)ectlons it would be helpful In reclaimed water system
planning Any information would be helpful Thanks, Tom
Skillmgs-Connolly, Inc
Thomas E sklllings, P E
President
Office (360) 491-3399
Direct (360) 455-3131
www sklllings com
This email (and or documentr accompanying it) may contain confdentlal Information belonging to a sender, which is protected by
the Consultant client privilege The Information is intended only for the use of the individual or entity named above If you are not
[he intended recipient, you are hereby notified that any disclosure, copying, distribution, or [he taking of any action in reliance on
the contents of this information is strictly prohibited If you received this email In error, please notify the sender immediately and
delete the documents from your computer
From Stan Zielinski (mallto Stan@ericksonmcgovern com]
Sent Monday, February 27, 2006 5 38 AM
To tskillings@sklllings com
Cc Stephanie Ray, dave@wdginc coin, Rocky Birkland, ray@ericksonmcgovern coin, John Erickson
Subject: RE Minutes 9/26 meeting
Tom,
Just to follow up on our conversation on Tuesday with Dave Andrews, at Ridgeline MS (formerly known as YJHS),
it's been 6 months since we started planning on using reclaimed water Now we are now behind the eight ball to
the point where the unresolved irrigation issues could potentially cause a delay in construction
You received the latest round of information you requested from Dave Andrews (see attached) on Thursday
2/23/06
I asked if he got a timeline from you of when we could expect information back from you so we can make
necessary ad/ustments to our irrigation design In time to get it priced, approved, ordered and installed prior to
school starting in another 6 months
Can we get a timeline on when we can have a decision on the irrigation system
Also, please give us a status of the City's irrigation design for bringing the reclaimed water up MIII Road to the NE
corner of MIII Pond sites This could also prove to be a critical path item if it is not on schedule to be installed by
April
3/10/2006
Page 3 of 3
Thanks
Stan Zielinski
From Stephanie Ray [matlto stephanier@ci yelm wa us] "
Sent Friday, September 30, 2005 8 21 AM
To bob@~wmonssette com, dave@wdginc com, Grant Beck, ~img@a yelm wa us, Rocky Birkland,
Stan@EricksonMcGovern com, Tim Peterson
Subject Minutes 9/26 meeting
FYI
3/10/2006
Jim Gibson
Page 1 of 3
~L~-t..SEr RLDCT~
From Stephanle Ray
Sent Friday, March 10, 2006 11 27 AM
To Jlm Gibson
Subject FW Residual pressure at Irrigation Flow rates at Rldgellne and Hlgh School
Jlm,
FYI -
This information had also been provided to Erlckson McGovern prior to February 27tn
Steph
From Tom Sklllings [mallto tskillings@skillings com]
Sent. Monday, February 27, 2006 5 29 PM
To Tom Skilhngs', 'Stan Zlehnskl'
Cc Stephanie Ray, dove@wdglnc com, 'Rocky Birkland', ray@erlcksonmcgovern com, 'John Erlckson'
Subbed RE Resldual pressure at Irrigation Flow rates at Rldgellne and High School
Let me try again, some of the sent Items came back to me T
Sklllings-Connolly, Inc
Thomas E Sklllings, P E
President
Office (360) 491-3399
Direct (360) 455-3131
www skiliinos com
This email (and or documentr accompanying it) may contain confidential information belonging to a sender, which is protected by
the consultant-client privilege The Information is intended only for the use of the individual or en[rty named above If you are not
the intended recipient, you are hereby notified that any disclosure, copying, distribution, or the taking of any action in reliance on
the contents of this information is strictly prohibRed [f you received this email In error, please notify the sender immediately and
delete the documents from your computer
From Tom Sklllings [mallto tsklllings@skillings com]
Sent Monday, February 27, 2006 5 26 PM
To 'Stan Zlehnskl'
Cc 'Stephanle Ray', 'dove@wdglnc com', 'Rocky Blrkland', 'ray@erlcksonmcgovern com', 'John Erlckson'
Subject RE Resldual pressure at Irrigation Fiow rates at Rldgellne and Hlgh School
Good afternoon Stan
We have analyzed the Irngatlon demands you have requested for the school district These
numbers were discussed at meeting at the Clty of Yelm's Public Work's conference room At
that meeting you were informed that the city could provide water to the new middle school at a
minimum pressure In the 67 - 70 psi range at 62 gpm, the flow you Indicated for the school
We have analyzed the revised flow demands you have requested and have verified the
pressures you can anticipate at Rldgellne to still be In the 67 - 70 psi range You should
anticipate a range of 80 - 85 psI at the high school at 160 gpm
3/10/2006
Page 2 of 3
~~
As Indicated at the meeting, the more significant Issue is the duration of your watering cycle
In order to manage the total volume of water produced during the peak month, the City will
have to regulate the total watering cycle of each of Its users Therefore, some of the schools
anticipated 13-hour watering days will have to be restricted to perhaps 10 hours per day at 160
gpm This will become less of an Issue as time goes by because more reclaimed water will be
produced as the system expands The reclaimed water user agreement that you will execute
with the City will define the flow and volume of water that will be available to each site The
limiting factor is the storage tank The city will manage the system use based on the
residual storage volume in the tank Over time, as total system flow demands increase, the
residual pressure can be expected to decline at Ridgeline to the 60 - 65 psi range Additional
pump(s) would then be required at the reclaimed water pump station
Therefore, if I understand the information you need for des+gn+ng the trrtgatton system is how
much residual pressure can be expected at the design flow rate Is there something more that
you needy Please give me a call if you have any questions or need additional information
I will follow this up with a written report with specifics of the calculations But hopefully this will
address your immediate needs Please let me know if you need more
Tom
Skillings-Connolly, Inc
Thomas E Sklllings, P E
President
Office (360) 491-3399
Direct (360) 455-3131
www sk/Ilmgs com
This email (and or documents accompanying it) may contain confidential mformatwn befongmg to a sender, which is protected by
the consultant client prrvllege The information Is Intended only for the use of the individual or entity named above If you are not
the intended reciDlent, you are hereby notified that any disclosure, copying, distribution, or the taking of any action in reliance on
the contents of this information is strictly prohibited If you received this email in error, please notify the sender immediately and
delete the documents from your computer
From Stan Zielinski [mallto Stan@erlcksonmcgovern com]
Sent• Monday, February 27, 2006 5 38 AM
To tskillings@skillings com
Cc Stephanie Ray, dave@wdglnc com, Rocky Birkland, ray@ericksonmcgovern com, John Erickson
Sub~ect• RE Minutes 9/26 meeting
Tom,
Just to follow up on our conversation on Tuesday with Dave Andrews, at Ridgeline MS (formerly known as YJHS),
it's been 6 months since we started planning on using reclaimed water Now we are now behind the eight ball to
the point where the unresolved irrigation issues could potentially cause a delay In construction
You received the latest round of information you requested from Dave Andrews (see attached) on Thursday
2/23/06
I asked if he got a timeline from you of when we could expect information back from you so we can make
3/10/2006
~, ~
r
Page 3 of 3
necessary adjustments to our irrigation design in time to get it priced approved, ordered and installed prior to
school starting in another 6 months
Can we get a timeline on when we can have a decision on the irrigation system
Also, please give us a status of the City's irrigation design for bringing the reclaimed water up Mtll Road to the NE
corner of Mill Pond sites This could also prove to be a critical path item if it is not on schedule to be installed by
April
Thanks,
Stan Zielinski
From Stephanie Ray [madto stephanier@ci yelm wa us]
Sent Friday, September 30, 2005 8 21 AM
To bob@jwmorissette com, dave@wdginc com, Grant Beck, ~img@ci yelm wa us, Rocky Birkland,
Stan@EricksonMcGovern com, Tim Peterson
Subject Minutes 9/26 meeting
FYI
3/10/2006
Page 1 of 3
I~ct.3 E~7z[ r~ ~.~'
Jim Gibson
From Stephanie Ray
Sent Friday, March 10, 2006 11 29 AM
To Jim Gibson
Subtect FW Ridgeline Irrigation system
FYI
Steph
From Tom Skillings [mailto tskillings@skillings com]
Sent Tuesday, October 25, 2005 3 24 PM
To 'stan', Stephanie Ray
Cc 'Bob', 'Rocky Birkland', 'Dave Andrews', scoff@Iwmorrissette com, Amanda Heye
Subject RE Ridgeline Irrigation system
Bob, Stan
We have finished our analysis of the calculated pressure anticipated at the elementary school
property line Here is a summary for your information
What we know or assumed
. The elevation at the property line as provided by Bob T is 357
. The reclaimed water pump station, minimum water elevation is 329 0
. The pump station consist of two tockey pumps and two line-shaft turbines
. The line shaft turbines are equipped with variable frequency drives that ad]ust speed to
maintain a downstream pressure of 90 -105 psi Due to the lag time for reaction to ramp
up to speed, there is a delay of up to 120 seconds when the line pressure can drop to 65
psi, but only for a short period
. We modeled the system as if the supply was producing a constant head of 85 psi
. We assumed there were other concurrent uses on the system amounting to 100 gpm in
the subject 4" pipe and 200 gpm for other uses off of the 12" line
. The school's irrigation system would have a flow that did not exceed 40 gpm *~`
Conclusions
. The residual pressure at the right of way Ime off of MIII Road, elevation 357 will be
approximately 68 psi It can fall as low as 59 psi for short periods of time, but should
come back up to 65 - 70 psi as the pump motors ramp up their speed
***Caution
. When the City of Yelm negotiates the reclaimed water User's Agreement, the
allowable flow will be limited to a set value I do not have the exact allowable
gallons per minute that the school will be permitted to use on this site I have
assumed 40 gpm for calculation purposes It may be lower
. If you decide to install a booster pump station, you should also consider a flow
control valve in the system I can not tell you today what the set point on the valve
will be until the Reclaimed Water User's Agreement is finalized
I hope this helps you get started with your onsite design, it should be pretty close
3/10/2006
Page 2 of 3
If you have any questions, please glue me a call
Skdlmgs-Connolly, Inc
Thomas E Skillings, P E
President
Office (360) 491-3399
Direct (360) 455-3131
www skdhngs com
This email (and or documents accompanying it) may contain confidential information belonging to a sender, which is protected by
the consultant client privilege The information is intended only for the use of the individual or entity named above If you are not
the intended recipient, you are hereby notified that any disclosure, copying, distribution, or the taking of any action in reliance on
the contents of this information is strictly prohibited [f you received this email in error, please notify the sender immediately and
delete the documents from your computer
From Stan [mailto stan@ericksonmcgovern com]
Sent Monday, October 24, 2005 3 56 PM
To Tom Skdlmgs
Cc 'Bob', 'Rocky Birkland', 'Dave Andrews', scoff@Jwmorrissette com
Subject FW Ridgeline Irrigation system
Toms
Any word on the protected operating water pressure of the reclaimed water system at Mlll Pond Intermediate
School/Ridgeline Middle School site
It costs the school district more each day we don't have the reclaimed system designed since the water system is
being constructed at Ridgeline as we speak
Thanks,
Stan
From Bob [mailto bob@Jwmorrissette com]
Sent. Monday, October 24, 2005 3 52 PM
To. stan, 'Dave Andrews', scoff@Jwmorrissette com
Cc 'Rocky Birkland'
Subject RE Ridgeline Irrigation system
Stan,
We are waiting on response from Tom Skillings, with the protected operating pressure of the reclaim water
system We need to know what the system pressure will be to determine if it meets Dave Andrews design
requirements Rocky found in the northeast corner of Mill Pond School site, the irrigation line is 2-inches and we
should be able to back feed into the system If you have any questions please let me know
Thanks Bob
Robert E Tauscher P E
Jerome W Momssette & Associates Inc , P S
1700 Cooper Point Rd S W #B-2
Olympia, WA 98502-1 1 1 0
Phone360-352-9456
Fax360-352-9990
Ce11360-481-4145
bob@Jwmomssette coin
3/10/2006
Page 3 of 3
-----Original Message-----
From Stan [mailto Stan@ericksonmcgovern com]
Sent Monday, October 24, 2005 3 23 PM
To 'Dave Andrews', Scott@~wmorrissette com
Cc 'Bob', 'Rocky Birkland'
Subbed RE Ridgeline Irrigation system
l meant to ask Bob today at the meeting but forgot 4uhat's the status of the ceclatimed ~atetlustigahon
redesign
From Dave Andrews [mailto dave@wdginc com]
Sent Monday, October 24, 2005 1 34 PM
To Scott@Iwmorrissette com
Cc. Stan@encksonmcgovern com
Subbed Ridgeline Irrigation system
Scott,
We have looked at the pressure loss for the irrigation design at Ridgeline As currently designed, we need
85 psi static pressure going in to the meter We can do some re-design with different heads and oversized
mainline pipe and get that number down to 70 psi ,but no lower
Let me know if you need anythrng else
Thanks
Dave Andrews, ASLA
Prtnc~pal
WEISMAN DESIGN GROUP INC , P S
2329 East Madison Street ~ Seattle, WA 98112
PHONE 206 322 1732 I FAX 206 322 1799
http I/www wdginc com
dave@wdginc com
3/10/2006
dy
s
t I
I
I
~ I
N 591161 25
1
I E nIJ09}a9
SCCCOR
~
n
~ SipNE YON b
n
I
I 7
J II ~
`J
- - -~
19 ]0
2• 25
S~
7CA. L7 1wr I/ n N I c dt JCL JV IwY IA n K ( t wM i W ~
I ~ I
LCNO4IRE RORER iA B I 2 ~
I
N 59165)69 1
PARCEL NO 22730220600 1
=
W
E ug9vt 92 I I 1- U
I
1A 1• i pt I ~ Q
BEONNING Of vROJECr
I O J F
SEE NO1E I
~ !Z
aEYOVE EnSnNG 0.uG AND MauST BLOtx I I ,
COnNECi IO Eil$nNp / l;
r7
• PK (tEQA1ED W1 fER PAIN r
INSTALL y2 1 I
-_
-• If t/a BEND (YJ) ~
~ ~
~ i
`
- _ _ _ _ _ _ _
_ _ __ _ -__ _ - _ _ _ _ N? J
--
' I
I T, u
~`
o Ex Ei 901]236 W ~' - 9u 56
- °
~ --
- i
X n
RI
-~~9v .: i-~M'-~
-~+{~~_
Fj ~ Jr ~ --9T~ ...
w.~_~iW
} _ cx EP
G f ~~ ~vT ~ 1:- . _
~'3
-x ~~--+Z i
i
~ ` ~
I
SE- NOIE
N 59165] 23
E 11139]1 29
FIRE D1$TRIDT /2
PARCEL NO 2v25n 0600
709 MILL RD SE
~~ 1, N I
I II I I
W I
~z~ , ~ ~.
../ I Q I
N 591626.1] f II I 1
E It12925 95
STA 10.25x0 5 Rr I ~ ~ F-
In ALL ~ I
I-• n 1p REVD (Ya)k ~' O 1
AP 12x0 R'
I
I I
I 30 10 1
1 1
1 1
nrE CONniACifR SNALL BE rULLT RESVON9BlE ECR 1NE LOCAnLN
ANO PROTCnp. CE ALL Ex15nNO UnUTES I I
iFE CONiRAC OR 9NAL, VERY" ALL ViKltt lOCAnONS PRICK ip 1
CP.S'RUC nON B+ CALLING ME UNpERDRODND CCALE IiNE AT
1-600-•2x-5555 I I
• YInIMUY S x6 Naas vR10R ra AN° °xUVLnOH I I
LNE =CNiNACipR Mll AL50 BE RESPCN9BL EpR Y4Ni4NING
ALL LOUT YMKS ONCE n.E unLIBES NAVE BEEN LOCATED
N 5913•7 03
_ u1397L5
SiA tb06 12
C Ini ~,
-n5r Z BRASS
SUaEACE Ya
n 59UJ1 u
E m29i0 a
T-~~
J ISr ]-~0
dALS Cf BEAIBNG
J60 501. `n ZONE
PF? nES t0
ibuR5i0N COUntt
NIfJI PREC 90N NEi'ACVIK
N 591626
E ulI9T5 35
Su 10.15 .O 5 Ri I =
M ALl W
I-• 11 1/. RENO (uJ)
V
2
a - a
o
V V
I
V ~ ~
xx
q u ~ ExISnNG~
HX' UAOE
_~
- < _______
______ T
__
!1 1 • • 9i
1 BECJNNINL Ji PRO.ECi
~n5nnc-+ SEE nOiE 1
REMOVE Ex15nN0 n.RUSi BL001
RER~D CONNECT i0 JISnNG
VAiER YNN • PK REQAYCD W11FA VNn
INSrLLL
I-a 11 I/l BEND (YJ)
I-a wn: VALVE (VJ)
10+00 II+00
50
1 1
12+00
Ix
CEV IEa
LE
13+00 14i
GATE RE`ASCNS m.nACr Na
E SK/
DE4GNE0 By A NEYE 11 20(15 N01 DATE !~
I
EN tEPED BY T 31EKER 11 2005 ~
CNECNEO By .
PRO) ENC1R T SKILLINOS it 2005
I .•
I L• 5018 Lacey ei
9
OVOOi 1i_.D1 cet 2.uE6 lO50 ]i Ila n wta os. wYe (360) d97 03
r
_~°~Y
STATE OF M1NASHINGTON'
DEP,ARTt`1ENT OF HEALTH
OFFICE OF ENl'IRONhtENTAL HEALTH A\n SAFFT\
T500 IM1'ett Fourth A~enuc Sutlc 303
Spo6anc IYa~hmeton `1920-i IGSG
Apn114,2006
Ms Stephanie Ray, Protect M.inager
Crty of Yelm
PO Box 479
Yelm, Washington 98597
Dear Ms Ray
l2e~i~ ~„
~"- Z3 - o(p
RE Crty of Yelm, Thurston County, Construction Documents for Reclaimed Water
Imgahon at Rrdgeline Middle School, DOH Project R06-006
Construction drawings for the Ridgehne Middle School imgatton project were received
m our office on Apnl ] 0, 2006 An initial review of these construction documents has
been completed, and the following comments and concerns have been identified
Engmeenng Report An engmeenng report is required per the Wnler Reclcunnnon
and Reuse Srnnrlatds, Section I, Article 8 1 c(5) either as a stand alone report or
by reference to a previously approved engineering report The report must
address at a minim the following issues
a A detailed water balance and imgatron plan
b Reclaimed water system hydraulics, including water demands pipe sizing
system pressures and hydraulic transient conditions that writ likely affect
the system
c Cross connection control and backflow prevention considerations
d The identification of the specific area to be serviced by this system
expansion
e Use area and user protections, notifications, and /or warning signs
Construction Speaficatrons Construction specifications need to be provided
Sheet CO 0 The sheet submitted appears to be draft A final version of this sheet
is necessary for final approval
Sheet 3 7 RW
Please descnbe the intent behind the 305 lf- 1"diameter reclaimed water
line extension at the northwest portion of the site, especially the potential
for reclaimed water use m the adjacent residential lots to the north of the
~'
td
Ms Stephanie Ray, Gty of Yelm
.~ Apnl 14, 2006
Page 2 of 3
site and potential for hose-[o-hose cross connection between the reclaimed
water line an potable pipelines at the Ridgeime Middle School Srte
b The potable water line e>,tendmg around the Elementary School changes
from `water' to `fire', which is a nonpotable use To do so, some sori of
isolation or backflow prevention from the fire line system wrih the potable
systems is necessary
c Construction Notes
i [1] & [5] -Note that Wnter Reclamnnon rnitl Reuse Stunrlurds
define acceptable shades for color coding of reclaimed water
pipelines and facilmes The `purple color' shall be the shade
Pantone 512 or 522 or a shade acceptable to the Departments of
Ecology and Health
ii [4] -Please provide Project Manual Volumes 1 and 2
d Reclamation Identification Signs Note that this site must be provided
with a sufficient number signs to inform users of the use of reclaimed
water at the site It is suggested that the signs inform site users that
'reclaimed water is being used to conserve the potable water supply and
wain against consuming any type ofnon-potable water
Sheet 3 8RW
a Note that all references to "recycled water" in the drawings and for
imgation system labels must be changed to "reclaimed water" Recycled
water is a regulatory term used m California, and is generally taken to
mean water that is recaptured and reused within an mdustnal process for
internal water conservation, which is not subject to water reclamation and
reuse requirements
b Please descnbe means to assure that the buned hose bib is not subject to
intrusion by ground water or subject to uncontrolled discharge or leaking
that could result in flooding or runoff The concern is that the hose bib is
normally out of site, and either of these situations could possibly result in
a violation of the terms of the reclaimed water permit held by the City
c The specification for `purple color' must be consistent the specifications
as notea above
6 Sheet L3 0 Please provide the basis of design for the reclaimed water booster
station and identify at a minimum the rated flow capacity and head and motor
horsepower and efficiency
7 Sheet L3 3
a Note 1 Note that the potable and reclaimed water system purveyor in this
area is the City of Yelm, not a water distnct In addition, note that the
regulatory requirements are imposed through city ordinances, and not any
rules or regulations, which are normally administered by state or federal
agencies
b Note 2 Please also address separation behveen reclaimed water pipes and
sanitary sewers
c Note 4 Please provide approval of or concurrence with these construction
documents from the water system purveyor's cross connection program
Ms Stephanie Ray, Crty of Yelm
~ - Apnl 14, ?006
Page 3 of 3
d Note 6 The imgation system operation must be consistent with the
tirr~gattion plan requrred per Comment #1, above
e Notes 8 and 10 Please assure that the color codes are consistent with
spec~ficahons noted previously
f Note 10 Please note that the ID tags and all other informational and
wammg signs on the site need to be approved by both regulatory agencies
Please feel free to contact meat (509) 456-?466 or via email at cra~~ nley~doh wa vov ~f
you have any questions regarding ih~s concerns
Sincerely, ----~
t
Crarg L rtiey, P E
Office of Environmental Health & Safety
Water Reclamation & Reuse
cc Thurston County Health Department
Jerome Momssette & Associates, Olympia
Glenn P~entz, WA Dept ofEcology, SWRO, Lacey
R
,yq 2~F~VFO
Jerome W Mornssette & Associates Inc.. P S
1700 Cooper Point Road SW, #B-2, Olympia, WA 98502-1110
(360) 352-9456 • (360) 352-9990
May 19, 2006
Mr Jtm Gibson, P E
City of Yehn, Commumty Development Engineer
105 Yelm Avenue W
P O Box 479
Yelm, Washington 98597
Re Rtdgehne Middle School, Reclaun Water Plan Approval Impacts
Dear Mr Gtbson,
As stated m a letter to the Ctty of Yelm dated April 28, 2006, the Ridgehne School reclaim water
plan approval is impacting the construction schedule Since there has been no response to that
letter, the school district has to direct the contractor to proceed to install the on site tmgahon
system
The School District submitted plans to the Ctty, DOH and DOE on April 7, 2006, received
comments from DOE April 13, 2006, and received comments from DOH on April 15, 2006 I
sent a letter to the City on April 28, 2006, stating the concern the School District has m receiving
the Certtficate of Occupancy tf the School cotmechon to the reclaim water system is not
complete On May 12, 2006, you directed the revised tmgahon and reclaim connection plans be
submitted to the Ctty of Yelm for review pnor to routing to DOH and DOE, which I submitted
on May 17, 2006 The process to coordinate with the City and the City Consultant, the time to
tmtially review the plans by the Crty, DOH and DOE, and addrtonal projected rime needed to
review the revised plans by the Ctty, pnor to rerouting to DOH has forced the installation of the
tmgahon system to the critical path for the project
In order for the contractor to complete all site work required to open school as scheduled, the
School District will direct the Contractor to install the irngation system as designed on the
revised plans submitted May 15, 2006 If for any reason the connection to the reclaim water
system is not completed at the time a Certificate of Occupancy is requested, a temporary
connection can me made to provide water to the tmgahon system Thts can be provided if the
Crty requires a functtomng imgatwn system pnor to issuing a Certtficate of Occupancy
Please contact me~f~or ~any~questions o • require additional information, at (360) 352-9456
K-m'Ot~1- V~~
SIGNED
Robert Tauscher, P E
Protect Engineer
C Mr Erring Birkland, Facilities Operehons, Yelm Community Schools, PO Box 476, Yelm, WA 98597
Mr Stan Zielinski, Architect, Erickson McGovern, 120 131' Street S ,Tacoma, WA 98444-4804
C \Bob\03157 Yelm Ridgehne Middle SchoollComespondance\051906 Letter to Ctry Recla,m Approval Delay doc
JWM&A
Jerome W Mornssette & Associates Inc , P S
1700 Cooper Point Road SW, #B-2, Olympia, WA 98502-1 110
(360) 352-9456 • (360 52-9990
Apnl 28, 2006 ~C'~.
~q` ~`
Mr Jtm Gibson, P E ~2? ~~
Community Development Engineer
City of Yelm
105 Yelm Avenue W
P O Box 479
Yelm, Washington 98597
Re Ridgehne Middle School
Reclaim Water Plan Approval Impacts
Deaz Mr Gtbson,
The Ridgeline School reclaim water plan approval is impacting the construction schedule which
impacts obtaining the certificate of occupancy
I submitted, for the School Distnct, on Apnl 7, 2006, the design for the reclazm water extension
for the site and the revised imgation plans for the Ridgehne Middle School to the City, DOE and
DOH On Apnl 13, 2006, we received comments from Glen Piertz, DOE, only requinng an
engineer certification and updated Sheet CO 0 to accept the plans, but will not issue approval
pnor to DOH approval On Apnl 15, 2006 we received a comment letter from DOH, requinng an
Engmeenng Report and a few small items On Apnl 21, 2006, you stated m a phone
conversation you had called DOH and requested clazification of the report requirements
The requirement to connect to the reclaim water system was made (the fall of 2005) after the
civil and building plans were approved There were several meetings with the City reclazm water
system consultant (September 2005, December 2005 and January 2006) to determine system
capacity and school distnct needs
The school is scheduled to be open in August of this yeaz This schedule dictates the contractor
must proceed at this Ume, to install the imgation system (pnor to City and DOH approval) m
order to meet the school opening deadline The connection from the City reclaim watennam m
Mill Road to the site imgation system will be installed after it is approved by the City and DOH
It appears the installation of the line from the City main and the imgation system will not be
completed pnor to the need of the certificate of occupancy to open the school as scheduled
The school distnct appreciates the cooperation and effort the City has provided working towards
meeting the required connection Due the late additwn of the requirement to connect to the
reclaim water system, and the need of the school distnct to open school m August, I am
requesting the issning of the cemficate of occupancy not be held up if reclaim water connection
is not completed
Crvr! • Munrcrpa! • Geotechnrca! Engraeenng and planning
-9990
Should you have any questions or require addrttonal mformahon, please contact me at (360) 352-
9456
SIGNED _~~urt '!~~~~~'"'
Robert Tauscher, P E
Project Engineer
C Mr Erhng Birkland, Factlrttes Operations, Yelm Community Schools, PO Box 476, Yelm, WA 98597
Mr Stan Zielinski, Architect, Enckson McGovern, 120 131' Street S ,Tacoma, WA 98444-4804
C \Bob\03157 Yelm Rtdgehne Middle School\Correspondance\042806 Letter to City Reclaim Approval Delay doc
Crvrl r Munrcrpal • Geotechnrcal Engrneermg and Plannrng
Jerome W Mornssette & Associates Inc P S
1700 Cooper Point Road SW #B-2 Olympia WA 98502 1110
(360)352 9456 / FAX (360)352-9990
LETTER OF TRANSMITTAL
TO Ctty of Yelm Job No 03157
105 Yelm Ave W Date 07 Apn12006
Yelm, WA 98597 Attention Mr Jtm Gibson P E
SUBJECT Reclaimed Intgatton Water at Rtdgehne Middle School (Changes from domestic supply to
reclaimed water supply
I am sending you attached the following items
COPIES DATE DESCRIPTION
8 07 Aprt12006 Added Civil Sheets C3 7RW & C3 8RW
8 07 Apn12006 Changed Landscape Archttects Plans L3 0 through L3 7
Jtm,
Please find enclosed for the City's review the changes to connect the tntgatton system to the C1ty's
reclaim water supply I will also be sending the plans to D O H and D O E Thank you for getting the
contact names for these agencies to me
Feel free to contact m~e tf there are an/y~questtons or tf addtttonal information is required
SIGNED i%//'~ //~~%2'~G~i,~
cott evers
Sr Engineering Technician
cc Erhng Btrkland (Yelm School District)
Stan Ztehnskt (Erickson McGovern Archttects)
~P~;~~ved
qpH - 7 cuu6
Cwd / Mumcrpal / Geotechnrcal Engineering and P/ann~ng
Yage 1 of 1
Josh Mtller
From Stan Zielinski [stan@ericksonmcgovern com]
Sent Tuesday, May 23, 2006 3 21 PM
To tosh@lodymillerconstruction com
Cc Rocky Birkland Gndy Butterworth
Subtect FW Ridgefine Middle School -RFI-23
From Bob Tauscher [maiito bob@Jwmornssette com]
Sent Tuesday, May 23, 2006 6 29 AM
To Stan Zielinski
Cc 'Rocky Birkland', Dcug Eklund, Scott Severs, Jerry Morrissette
Subject Ridgeline Middle School -RFI-23
Stan,
The following is a paragraph by paragraph response to RFI #23 received May 17, 2006, from Roland Gorgas Wood & Sons to
Josh Miller Jody Miller Const
¶ 1 - No assurance was provided of the groundwater conditions moreover the subcontractor has provided verbal statements to
the effect that they understood groundwater was expected I do not recommend acceptance of any additional costs or claims
¶ 2 -All work shall be pertormed in accordance with tank manufacturers recommendations
¶ 3 -All work shall be performed in accordance with tank manufacturer's recommendations
¶ 4 -Bedding and backfill shall be crushed stone in accordance with the tank manufacturer's recommendations and shall be
installed in accordance with the manufacturer's recommendations Pea gravel is not acceptable Submit sieve analysis for crushed
stone to demonstrate conformance with the tank manufacturer's recommendations The proposal to use split backfill is not
acceptable All work shall be in conformance with the manufacturer's recommendations
The changes to the STEP tank location and the direction to use crushed backfill instead of pea gravel was issued to the contractor
on February 1, 2006 The contractor responded on April 10, 2006 with price for this item as follows
Backfill change - $5,000
I recommend you direct the contractor to install the STEP tank utilizing the manufacturers specified crushed backfill (I have been
told by Miles and Holroyd they can blend any specified crushed material) at their quoted cost of $5,000 Using crushed backfill,
there is no need for a geotextile fabric The contractor shall install the tank per the manufacturer's recommendations using
crushed backfill as we have instructed and per the price the contractor provided
If you have any questions, please contact me
Thanks Bob
Robert E Tauscher P E
Jerome W Morrissette & Associates Inc P S
1700 Cooper Point Rd SW #B-2
Olympia WA 98502-1110
'hone 360-352-9456
=ax 360-352-9990
well 360-481-4145
fob@lwmaeny com or
~o_b_@~wmornssette com
>/23/2006
uo{15(LUUb 15 51 tAX 253 5Si 81ST Eric4.son EScGocern ~ 3odc Miller @]OD2JDD5
MAY-15-2006 MON 04'05 PM FAX NO 2535361074 P, 01
J
M PO Box 44628
C Jody Mdier Gonierucbon lnc Tacoma WA 98444
Commrmai Induetnal Reatdarrbal 253-537.6116
NUMBER OF PAGES INCLUDING COVER 3
Oate May 15, 2006
Time: 4 09 PM
To Stan FAX 253-531-9197
Enekson McGovern Phone 253-531-0206
From• Josh Miller FAX. (253) 536-107A
Project Manager Phone. (253) 537-6116
Cell• (253) 405-3305
EMail. ~ (cfiJodvm~llerconstruclron rr~rn
Subject
Stan,
STEP Tank RFI
Here Is the RFI for Wood 8t 5on
Thanks,
Josh Miller
Business Hnum - 9,00 a m to 5 00 p m
STATEMENT OF CONFInENTIALITY
The dowmenp included w11h tfus fatSlmlla trarrsmitfal page eontatn mforin>lhan from Jndy Maser ConsWdlon Inc which rs
con0den9el anNor privileged andlor draempt fiom dlsdosure under eppllrahle laws Thls mformebon is Intended to be for the use of
the eddress9e6 named on Ihis transmittal page If you are not the adtlfessao, nose that any drsdosure capying disblbWOn of use of
the wntents of thw fared Informa0on 15 prohlbltod If you have raCBrved this facsimile m ertdr please nobly us by telapnone
Immetl181e1y so that N6 can arran0e for the rdfnaval of lho onglnal docvmetds at no cost to you
092 DQC Page 1 0l 2
05/15!2006 MON 15 13 [TxlRf NO 7318)
u5/15/LUUU 15 51 YAA L58 5J1 8199
MRY-15-2006 MON 04'05 PM
J
M
c
Erickson McGovern JodS Miller SOU 9!005
FAX NO 2535361074 P, 02
REQUEST FOR INFOi~MATION
JMC RFI # 23
Subcontractor RFI #
pro)ect Rtdge.
Item sTTP
Ref Dwg /Spec 02000
Per the dtscuss~on we had on 5/10/06 T have attached Wood & Son's mstallaUon letter Please
advise on acceptable fabnc matenal and structural baclcfill
Reply req'd by A5AP
Originated by Roland Flrm Woad & Son Date 5/15/06
5ubrrlmed by Jody Miller Conskuchon Date 5/15/06
ABCH>rI'1.Cr/IHIN6INEEB $E9PON6E
Dwg's Attached
Response By
D~att[butlan Sal
cc ct
023 DOC OSH S/06
pate
Pape 1 oft
05/15/2006 MON 15 13 [TX/R9L NO 95291
ooi i.oi[uuu i5 51 rna d5J 531 9197 Erickson McGovern ~ Jodc Miller l~]004(005
riAY-75-2oDB 11oN 04,05 PIi FAX NO 2535361x74 P, 03
Wood & Son Contractors
15040123'd AVE S E
Yehn, WA 98597-9252
To Jody Miller Canstruchan
Attn Josh Miller
Re Ridge fine School STEP tank
Josh,
Asper our discussion at Uie Wednesday meeting on 5-10-06, this outlines our lnstallanan
proposal l must reiterate that Wood and Son does not have confidence to this tnstallahon due
to lack of ancbonng m a }nglt water table azea, and assumes no responsibillry for any damage
if the tank floats, shifts, fists, buckles, deforms, or moves an any way from the onguial
placement Also, extra costs associated with tins installason are not incidental to the ongmal
contract These costs will be tracked and payment will be expected
Wood sad Son wtll perform the fallowing procedure to install the STEP tattle
Exesvate for rani, and dewatentig pits The desibnated tank azea sha116e dug appxoxunately
to proper grade, and the dewareruig pits wAI be dug down below that m areas to be
determined at the time of excavation to maxrmize pumping capability Excavation spoils are
to be stockpiled in an onsite area designated by Yehn Coittmumry Schoo]s
Dewater the excavation. The pump sumps will be installed below the lowest point of tank
excavation Pumps, generators, and disposal pipes or hoses will be placed to such a way as to
not Mader Seal grading, bedding placement, crane locasan, or tank uiatalletion The water is
to be pumped to an approved designated area (stortti-water pond) and dtspersed over a rrp-rap
spillway as to trap silt and tnirnmize erosion. The water level is to be lowered enough and
maintained as such that final gradtug of the excavation and placement of bedding can be
achieved At this time inspections can be performed by the Cily of Yelru
Install STEP tank. After approval by the Ctty of Yeltu, the tank can be lowered in the
excavation and placement ofpea gravel bedding can proceed Deflection measurements are
to be taken as rrgmred Eor the Xerxes warranty As the beddtg is placed, potable water is to
be pumped into the tank for ballast Pea gravel bedding shall be placed to an elevation to be
de[enrinied by the engineer and covered with a layer of Geotexsle fabnc The matena)
selected For final baoldill is also to be determined by the engmoer
As soon as tha requested niformadon is provided by YCS and the eneineer, we can schedule
this mstallaUon
Thank you
Roland Gorgas
Wood and Son Excavation and Utilises
05/15/2006 MON 15 13 (TX/RX NO 7329]
23034 file 23
YELM COMMUNITY SCHOOLS
RIDGELINE MIDDLE SCHOOL
CONSTRUCTION MEETING MINUTES
Date Wednesday, May 17, 2006
Time 9 00 A.M
Location On Slte
Weather Cool and Sunny
PERSONS PRESENT
General Contractor
Clvd Engineer
Architect
ITEMS DISCUSSED
Protect Schedule 5/17/06
Bwldmp
• Roofing proceeding
• Ready to paint In all wings
• Masonry veneer proceeding @ gym
• Ready to start sheathing roofing at locker
rooms
• Footing poured at service yard
• Relates being installed
• Transformer set
Josh Miller & Jody Mlller
& Craig Sorenson
Bob Tauscher
Stan Zielinski
Jody Mlller Construction
Jerome W Mornssette & Assoaates
Enckson McGovern
Cost Issues Loa Reviewed
Cost Issues were discussed
Site Issues
Site Work
• Behind schedule
• Joint trench complete -covered
• Setting grades at service yard
• Subgrade on east side to grade
• Should start grading parking lot soon
• Alternate 3 of ball fields
• Fencing being installed
• Bus loop subbase will start next week
• Chiller Is set
1/17106 Water Is rising on lower end of the site causing some Flooding Neighbors are also experiencing
Flooding off site JWMA well Investigate and determine whether or not our site is contributing to the
problem
4/26/06 Analysis should be done the end of this week Level pool analysis Hopefully by end
of next week will have a decision
5/3/06 By end of this week
5I10/O6 Analysis complete -waiting on decision from owner
SH7I06 No dvectron
2/6/06 Ownerwants to revise Irrigation system to delete sprinkler heads around the site everywhere except
lawn areas and athletic fields and Install quick connect couplers so that no planting areas are more
than 75' from any hose connection
$riCr(S'nn McGot ern PLLC X 1'30)4 RidgeGne Middle Schoo(UdmmlContrrucnon Meeting MmureslMeenng Mrm¢es I/5 /7 06-rtdgelme npd
Rldgellne Middle School
Construction Meeting Minutes
May 17, 2006 Page 2
3/15/06
3115/06
3/15/06
2/21/06 Still need to get a decision from Clty of Yelm on Irngatlon supply of reclaimed water
Dave has heard nothing Beginning to reach the critical point where we really need
Skillings/Conoly to make a determination
3/1/06 Dave has information and Is working on a redesign of the irrigation system
3/15/06 WDG has revised the irrigation drawings Meeting today with City of Yelm to go over
Irngatlon issues
3/22/06 Should have by next week
4/12/06 DOE, DOH 8 City of Yelm are reviewing reclaimed irrigation design
4119/06 DOE has approved It No word from DOH or City of Yelm
4/26/06 JWMA Is waiting on City comments DOH wants city to supply an analysis of the
water system
5/3106 PR 24 costs of $6 604 45 for converting the irrigation system to purple pipe have been
approved, however, JMC needs to submit credit amount for Irrigation pump change in
order for the costs to be Incorporated Into a change order Bob has written a letter to
the city telling them that we well direct the contractor to proceed with on-site reclaimed
water irregatron system down stream from the pump
5/10/06 Clty vnll address Monday According to JIm Gibson, Bob will respond to D O H
5/17106 No response Bob submitted Irrigation comments to City of Yetm this morning
We need to direct JMC to proceed now In order to stay on schedule
JMC needs to submit added costs incurred to date for septic tank excavation and handling
4/5/06 Working on pricing PR 20
4112/06 $10,000 price submitted for PR 20 JWMA requested backup
JMC needs to come up with 2 different options for installing septic tank with costs assoaated with
each option
4110/06
4126/06
Drop dead date for installing septic tank prior to paving
Drop dead date for installing septic tank after all the rest of the parking lot Is
complete
PR #21 prices Issued $32 000 for Option 1
$36,501 for Option 2
Owner and GC disagree on what dewatering is included In the contract
Owner and JWMA need to decide what costs they agree are the owner's
re5ponsiblllty and what portions are Included In the contract
Wood 8 Sons will monitor water table, monthly, with a port pipe monitoring well and put 2" PVC
slotted pipe JWMA well get pipe to JMC In a couple of weeks
3/22!06 Hal Parks will do it through the School District
Encksan McGovern PLLG XII3(Hd R~dgelme Middle SchoolWdmmlConstruchon Meeting MmuteslMeenrtg Mmures OS 1706ndgelme vpd
R/dgellne Middle School
C.OlIStrUCtlOn Meehng Minutes
May 17, 2006 Page 3
3129/06 Well dug Dry 17' deep -schedule for next week What to do with materials
Stockpile it
4/19/06 Well still has water in it up 4 75' from bottom of tank excavation level
346 Bottom of Pond 344 75 water level
4126/06 Needs to be done EMA needs to give JMC a response to PR #21
415/06 Grade 357 0' 340 0'to bottom of septic tank hole Water is at 344 0' Needs to drop 4'to set tank
without dewatering
4/19/06 According to the spec dewatering is included JMC disagrees with this interpretation
5/10106 Water has not dropped
5/17/06 Water is around 3'-3" deep at bottom of excavation or 343 3'
5/3/06 Where to put excavated material from hole
5110/O6 Rocky will answer
5/3/06 Compacting crushed stone against fiberglass
5/10/06 Not allowed by Xerxes
5/3/06 What are City of Yelm requirements for backfillT Wood 8 Sons will ask
New Items
5117/06 8 fixtures at back of kitchen
Semi recessed - no soffit Change to wall mounted Ask Mike or Mark
5/17106 Conflict at back mezzanine at kitchen (5) 6" pipes at supply ducts serving Aux Gym and
commons above partition Need to move (5) 6" pipes up to allow duct to get into chase at
13'-6" Ask Mark
5117106 Criticalltems
Reclaimed water line between Mill Road, irrigation pump and phone line Fence
Frontage improvements will be negotiated between City and the School District
Meeting adjourned at 10 30
The next construction meeting will be held on Wednesday, May 24, 2006 at 9 00 A M at the/obs/te
The above minutes, as compiled by Erickson McGovern shall be considered to be correct as stated unless revisions
are received wdhin five (5) working days
END OF CONSTRUCTION MEETING MINUTES
Encksan McGovern PLLC X 113034 Rrdgelme Middle ScM1oollAdmmlCoruo-uaron Meenng MmuresLNeenng Mrmues US l7 O6ndge6ne Nyd
Rfdgel~ne Middle School
Construction Meeting Minutes
May 17, 2006 Page 4
Enekson McGovern PLLC X 123034 Ridge/me Middle SehaoflAdmmlConstnshon Meeting MmuteslMeenng Minutes OS II O6 ndgehne ~ipd
JWM&A
Jerome W Mornssette &Assoctates Inc . P S
1700 Cooper Point Road SW, #B-2, Olympia, WA 98502-1110
(360) 352-9456 • (360) 352-9990
LETTER OF TRANSMITTAL
TO James E Gibson
Development Services Engineer
C~ City of Yelm
105 Yelm Avenue W
Yelm, WA 98597 RF~Ei
VF
JOB NO. 03157 ~R2 p?0p~ ~
DATE Mazch 19, 2007
SUBJECT: Yelm Community Schools
Yelm Ridgelme Middle School
Revised Storm Drainage for Sport Fields
I am enclosing for you the attached Items
COPIES DATE DESCRIPTION
4 Mazch, 2007 Sport Field Storm Drainage Revised Plans
1 Crvil Plan Review Apphcahon
Attached are the revised Civil Improvement Plans for the Storm Drainage on the sports field
This was emailed to you on 3/6/07 and 6/26/06, but I can not find any comments Please review
this at your eazliest convenience The school distnct Is attempting to complete the work this
summer
If you have any questions, please contact me at (360) 352-9456
Very truly yours,
Jerome W Mornssette 8 Assoctates Inc , P S
SIGNED a;cc~
Robert Tauscher, P E
Cc Mr Erhng Btrkland Facthhes Operations, Yelm Community Schools, P O Box 476, Yelm, WA 98597
Mr Stan Ztehnsky Architect, Enckson McGovern, 120 131° Street S ,Tacoma, WA 98444-0804
C \Bob\03157 Yelm Ridgelme Middle School\Corzespondance\031907 Transmit Yelm Alt 4 SD Revaton DOC
Crvtl * Municipal • Geotechnical Engmeenng and Planning
RFC~rvEo
Comm>tuuty Development
Department
City of Yelm
P.O. Box 479
Yelm, WA 98597
MAR 2 0 2007
OFFICIAL USE ONLY
Date Received.
Received By:
IVIL PLAN REVIEW APPLICATION USE BLACK INK ONLY
er YE4d1 Sc ~-Fe eL D It T.e~ vt PROPERTY LOCATION
ddress PC 4~fj 47L
~ty & Slate !/
p Phone 3L0~/S'pb/2Y North ~ East West sde of
~ ST
7
~
Ir~n~me) Cam
-
pphcant YELw1 Scuy.~D~sTa~rr ~~
~~
//
~~,,
Between (road name) \l'7~r~-~~ S T
d (road name) ~ ~ 7 t~ ~ P S~
ddress D ~e c~7>G
rty and state Y ~ L w~ WA'
p ~LYS'R~J Phone ~je~/S8b12!? Property Address /D /. D 5 (~9/LrE..Q S T -~F
Secuon ~ ~ Townstup / ~' I Range '
dress ('I6o C~DG~2 `IyT SLV j~
~
tty & State ~ ~ /~10! /~ hIA
p ~L95>oi Phone 3L03r~9tfSY t rr /
Assessors Parcel No ~ ~ ~ ~r-J' ~~ • 0(J
UA1nMAlZY OF REQUEST' 1LS type of u~
~' ` Ul ~ 'OR OFFYCIAL USE ONLY
Yre DLslxict i+M+++~-.++•nffi Yes
Po
~- A Z C 'Le F7oav Required ®m
p'1.C
0 of proposed dwelling amts Q!
vnensons ofproperty later connection estimate
ewez connection estimate
-++ffi required
~~]] -- ((// Tw
oral sgft of ste~~,~~~N~
~'
3 Sgptof-way regmred
r
_
otal sq.R in buildings.
~ondiny required
oral sq ft in paved and covered surfaces (mdude buildings,
treeLS sdewallcs, and pazlang lots)
~ n^ eons
A cursory check of the plans against the attached plan checklist will be made by the Development
Engineer If the plans meet the minimum checklist xenuuements as to content, they will be routed to the
appropriate City staff and the plan review process will begin If minmium checklist tequuements ale not
met, plans will be retained to submitting engineer
R \Commumty Development\Forms @Procedures\QvilPlanReview\CrvdPianApp doc
8/01