FW Updated Ridgeline Punch ListIPM.Note
FW: Updated Ridgeline Punch List
FW:
Steve Harrington
Jim Gibson
Steve Harrington
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=GIBSON
Updated Ridgeline Punch List
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
Jim Gibson
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=GIBSON
Steve Harrington
Updated Ridgeline Punch List
For your Ridgeline list.
Jim Gibson P.E.
City of Yelm, Development Review Engineer
PO Box 479 Yelm,WA. 98597
Ph. 360.458.8438 Fx. 360.458.3144
<mailto:jimg@ci.yelm.wa.us> jimg@ci.yelm.wa.us
_____
From: Jon Yanasak
Sent: Wednesday, November 21, 2007 9:09 AM
To: Jim Gibson
Cc: Tim Peterson
Subject: Updated Ridgeline Punch List
Jim/Tim,
This is our latest updated punch list for Ridgeline. Roland (Wood & Son) is stopping by my office today to pick up a copy to deliver to Jody Miller Const.
However, it might be prudent if CDD also sent a copy to the School Dist.
Thanks,
Jon Yanasak
City of Yelm Sewer Dept. Mgr
Po Box 479
Yelm Wa 98597
Phone 360-458-8411
Fax 360-458-8166
jony@ci.yelm.wa.us
<DC90029353CCCD468AA2A2858FFCD8F54F330D@server1.ci.yelm.wa.us>
FW%3A Updated Ridgeline Punch List.EML
Jim Gibson
Jim Gibson
11.0
Ridgeline School updated Punchlist November 21, 2007
Ridgeline School updated Punchlist November 21, 2007
Steve Harrington
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=Steveh
steveh@ci.yelm.wa.us
steveh
458-8423
Community Development
Steve Harrington
Steve Harrington
steveh
Ridgeline School updated Punchlist November 21, 2007.doc
CITY OF YELM SEWER DEPARTMENT
November 21, 2007
Re: Updated Punch list Ridgeline School
The #1 pump was operating 7 days per week and 24 hours per day and now has 6975 hours of operation. This pump and motor must be replaced.
All “2 wire” splices must be connected with ‘Heat shrink’ Butt Connectors. All multi-wire connections (more than 2 wires) must be connected with water proof wire nuts.
Some of the existing ‘Heat Shrink’ butt connectors are punctured and must be replaced.
There are currently 4 ‘on-off’ floats operating 3 pumps. This is not wired correctly and must be re-wired.