City of Yelm Inspection Form 5 McCammant 4-Plexes
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 3/28/08
Day: Friday
Time: 9:05 a.m.
Project Name:
Trump Plat
Project Number
SPR-05-0540-YL
Project Description:
Subdivision
Contractor's Name:
Bulls Eye Trucking & Excavating / PSE
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Sunny, Cool.
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor has
trenched to roadway at 903 Crystal Springs Rd. this is to tap the water main for the water services to the 4-plexes.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Contractor working on trenching on Crystal Springs Rd. for water main tap for services.
Sketch or Paste Pictures Below:
Date
3/28/08
Typed or Printed Name and Title
Steve Harrington
Signature