05-0540 Approval letter 112607
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
November 26, 2007
Michael N. Antonoff, P.E.
3316 Deer Island Drive E
Lake Tapps, WA 98391
RE: McCammant Fourplexes – City of Yelm Project No. SPR-05-0540-YL
Approval of Construction Documents
Mr. Antonoff:
The City of Yelm has completed the sixth review of the proposed project. Your application included:
Response to comments from City of Yelm’s previous review
Full Size Plans
We have reviewed the plans for compliance with the City of Yelm Development Guidelines, the DOE Stormwater Manual and general standards of civil engineering practice. The construction
plans are complete and we have attached a billing summary for payment. Upon receiving the required fees the signed plans will be released to the applicant. The applicant will be required
to submit the following approved copies before a preconstruction meeting will be set up.
4 sets of full size construction plans
1 set of 11”x17” construction plans
1 copy of the Stormwater Report
1 CD with the AutoCAD drawings and all xrefs included in a separate directory and PDF’s of the approved signed plans.
If you have any additional questions or comments please do not hesitate to call or contact me at jimg@ci.yelm.wa.us.
Community Development Department
Respectfully,
Jim Gibson P.E.