05-0540 Preliminary Review Ltr 073008
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
July 30, 2008
Bryan McCammant
10305 Canyon Road
Puyallup, WA 98373
RE: McCammant 4-Plexes – SPR-05-0540-YL
Incomplete Civil Engineering Submittal
Mr. McCammant:
Please see below for punchlist items that were noted during preliminary project walk-thru. This is a comprehensive list that includes all departments from within the City.
Water Department:
Has Fire Hydrant Lock been paid for?
Gate valve housings in planter strip need to be raised to final grade and a concrete pad around them.
Fire Hydrant needs Stortz Adapter and raised to final grade.
Fire Sprinkler system Double Check Valve Assembly needs to be tested and results sent to City of Yelm Water Dept.
Ensure all meter boxes are at final grade when all landscaping is complete.
Sewer:
Bldg “A”
Green riser lids need to be installed on all risers.
A 3rd neutral wire needs to be installed between the house breaker panel and the pump Control Panel.
The Pump Control Panel has a broken mount on the Motor Starter and must be replaced.
A surge arrester needs to be installed in the Pump Control Panel per our spec.
The float wiring needs to be corrected so each float does what it is designed to do.
The wires in the “J” box within the vault have multiple cuts in the insulation. Connections need to be re-done.
The Side Sewer “Clean-Outs” have been buried and must be found and brought up to grade.
Bldg “B”
Green riser lids need to be installed on all risers.
A 3rd neutral wire needs to be installed between the house breaker panel and the pump Control Panel.
A surge arrester needs to be installed in the Pump Control Panel per our spec.
The Side Sewer “Clean-Outs” have been buried and must be found and brought up to grade.
The wires in the “J” box within the vault have multiple cuts in the insulation. Connections need to be re-done.
The float wiring needs to be corrected so each float does what it is designed to do.
Engineering:
Handicap parking stall needs a handicap van accessible parking sign put in place.
Bring up grade behind sidewalks and handicap ramps.
Roadway center line striping appears to need a little touch up for visibility.
The area around meter boxes must be brought up to sidewalk grade.
Landscaping:
The two maple trees located along the frontage of Crystal Springs are required to be planted per the City of Yelm Street Tree Planting Detail per the approved landscape plans.
If you have any questions or would like to have a meeting on site to discuss these comments please contact Steve Harrington at (360) 458-8423 or email at steveh@ci.yelm.wa.us.
Community Development Department
Respectfully,
Steve Harrington
Engineering / Civil Inspector