Memorandum
To: SPRC
From: Tami Merriman, Associate Planner
Date: August 29, 2018
Re: 20170254 – Project Review Schedule for ICE Storage Yard Expansion
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
August 29, 2018 – Notice of Application distributed – begin 15 day comment period.
September 12, 2018 – Environmental Review
September 19 & 26 SPRC project review. Department comments/conditions of approval for staff report.