05-0531 Water Review No 2 072707 From: Edward Smith
Sent: Friday, July 27, 2007 9:31 AM
To: Tim Peterson
Cc: Steve Harrington; Kevin Ray; Jim Gibson; Deonne Hardy
Subject: Rainier View Estates Plan Review #4 Public Works.doc
Rainier View Estates review Water dept
???????? City of Yelm Public Works Department
901 Rhoton Road
P.O. Box 479
Yelm, WA 98597
(360) 458-8406 Fax: (360) 458-8417
Public Works Inspection Report
Date: 27/July/2007 Page
1
of
1
Location: Rainier View Estates # 2 Department: Water
Contractor: Rep:
1. The developer is responsible for the cost of the fire hydrant locks and the City of Yelm Water Department will order and install them. The project will not be final
until the City of Yelm has received the payment in full for the fire hydrant locks.
2. The well must be decommissioned PER DOH and DOE regulations and a copy of the report sent to the City of Yelm Water Department.
3. At station 6 + 84.5 the blow off at the end of the main will need the same size gate valve on the main. Need to add a eight inch gate valve.
4. Why can’t the sewer services for lots 1 and 22 be moved to the north side of the lots?
Reviewed by: Edward Smith
Signed by: Edward Smith