Response to 08-08-07 Comments 001o ° ~I~~LN~ ENGINEERING, INCORPORATED
~wizcd ~euelof~neirf -~r~ariodzn~ferYricec
October 12, 2007
Jim Gibson, P.E., Development Review Engineer
City of Yelm Community Development Department
P.O. Box 479
Yelm, WA 98597
Re: SUB-05-0531-YL Rainier View Estates Redline Response Letter
BASELINE Job. No. 04-159
Step Sewer Plan:
1. The plans show that the horizontal separation between the sewer and water utilities are at
least a minimum of 10'.
2. Only one gate valve is shown.
3. All fittings have been adjusted to show Slip x Slip with thrust blocking.
4. A note has been added to the plans.
5. Deflection points are used within the forcemain except for areas exceeding 5 degrees.
6. The details have been updated.
Water Plan:
7. A note has been added to the plans.
8. A note has been added to the plans.
9. An 8-inch gate valve has been added to the plans.
10. The sewer services for lot 1 and 22 have been relocated.
11. The details have been updated.
Misc Comments:
21. It is to our understanding that this issue has been resolved with the planning department and
the owner.
22. A new detail of the CBU has been added.
23. Street Channelization adhering to MUTCD standards are now shown on the road plans.
24. A cut-de-sac has been added to the plans.
25. The chain link fence will be replaced with the boarding fence and will correspond with the
landscape architect design.
26. A note has been added to the plans.
27. PSE has completed the lighting plan and has added an additional light pole.
28. PSE has completed the lighting plan and has added an additional light pole.
Sincerely,
J ry W ron, P~