Loading...
Response to 08-08-07 Comments 001o ° ~I~~LN~ ENGINEERING, INCORPORATED ~wizcd ~euelof~neirf -~r~ariodzn~ferYricec October 12, 2007 Jim Gibson, P.E., Development Review Engineer City of Yelm Community Development Department P.O. Box 479 Yelm, WA 98597 Re: SUB-05-0531-YL Rainier View Estates Redline Response Letter BASELINE Job. No. 04-159 Step Sewer Plan: 1. The plans show that the horizontal separation between the sewer and water utilities are at least a minimum of 10'. 2. Only one gate valve is shown. 3. All fittings have been adjusted to show Slip x Slip with thrust blocking. 4. A note has been added to the plans. 5. Deflection points are used within the forcemain except for areas exceeding 5 degrees. 6. The details have been updated. Water Plan: 7. A note has been added to the plans. 8. A note has been added to the plans. 9. An 8-inch gate valve has been added to the plans. 10. The sewer services for lot 1 and 22 have been relocated. 11. The details have been updated. Misc Comments: 21. It is to our understanding that this issue has been resolved with the planning department and the owner. 22. A new detail of the CBU has been added. 23. Street Channelization adhering to MUTCD standards are now shown on the road plans. 24. A cut-de-sac has been added to the plans. 25. The chain link fence will be replaced with the boarding fence and will correspond with the landscape architect design. 26. A note has been added to the plans. 27. PSE has completed the lighting plan and has added an additional light pole. 28. PSE has completed the lighting plan and has added an additional light pole. Sincerely, J ry W ron, P~ Lantl Planning 8 Use Engineering Surveying 1910-64th Avenue West • Tacoma, WA 96466 (253) 5654491 Fax (253) 5658563 Seatlle (206) 624-1205 "The industry starts here"