City of Yelm Daily Inspection Form 11- 60in. Dia. Storm Gallery& Storm Lines
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 11/20/06
Day: Monday
Time: 3:00 p.m.
Project Name:
Bella Housa Village
Project Number
SUB-05-0058-YL
Project Description:
Subdivision
Contractor's Name:
Don Olson Construction
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Cool, Sunny, Soil conditions are Dirt and Rock, wet.
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.)
Contratractor placing 60” Diameter Storm Gallery and C.B.’s # 12, 13 and 14 and approximately 110’ of 12” Ductile Iron storm pipe.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material)
Contractor Placing 60” Storm Gallery B and C.B. D.I. Storm Pipe
5. Sketch or Paste Pictures Below:
Date
11/20/06
Typed or Printed Name and Title
Steve Harrington
Signature