City of Yelm Daily Inspection Form 13- Storm C.B.'s Type 1 & 2 and ABS Storm Lines
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 11/27/06
Day: Monday
Time: 11:30 a.m.
Project Name:
Bella Housa Village
Project Number
SUB-05-0058-YL
Project Description:
Subdivision
Contractor's Name:
Don Olson Construction
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Cool, Cldy. Soil conditions are Dirt and Rock, wet.
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.)
Contratractor placing Storm C.B.’s Type 1 & Type 2 and approximately 122’ of 12” ABS storm pipe.
Contractor still placing waterline within property.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material)
Contractor Placing Storm C.B.and ABS Storm Pipe
5. Sketch or Paste Pictures Below:
Date
11/27/06
Typed or Printed Name and Title
Steve Harrington
Signature