City of Yelm Daily Inspection Form 14- Storm C.B.'s Type 1 & 2 Gallery B City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 12/12/06 Day: Tuesday Time: 9:30 a.m.  Project Name: Bella Housa Village Project Number SUB-05-0058-YL  Project Description: Subdivision Contractor's Name: Don Olson Construction  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Cool, Cldy. Soil conditions are Dirt and Rock, wet.  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contratractor placing Storm Gallery “B”. Contractor still utility crossing. Contractor placed drainage per plans on Burnett Rd.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Contractor Placing Storm C.B.and ABS Storm Pipe  5. Sketch or Paste Pictures Below:    Date 12/12/06 Typed or Printed Name and Title Steve Harrington Signature