City of Yelm Daily Inspection Form 16- Roadway Ballast-Curb & Gutter City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 12/26/06 Day: Tuesday Time: 2:45 p.m.  Project Name: Bella Housa Village Project Number SUB-05-0058-YL  Project Description: Subdivision Contractor's Name: Don Olson Construction  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Cool, Cldy, Heavy Rain. Soil conditions are Dirt and Rock, wet.  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor exxing dry utility trench. Contractor placed and compacted rock for curbing base. Placing Ballast for roadway. Iwill call Victor Breen (Foreman) to remind him to call for inspections.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Contractor Placing balast for road.  5. Sketch or Paste Pictures Below:     Date 12/27/06 Typed or Printed Name and Title Steve Harrington Signature