City of Yelm Daily Inspection Form 20-Grading Pavng - Grind
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 3/7/07
Day: Wednesday
Time: 11:00 a.m.
Project Name:
Bella Housa Village
Project Number
SUB-05-0058-YL
Project Description:
Subdivision
Contractor's Name:
Don Olson Construction
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Warm, Sunny,. Soil conditions are Dirt and Rock, Dry and firm.
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.)
Don Olson Construction is on grading crushed rock top course for paving. Grind Mt.View and Burnett Rd. Will prep for pave. Contractor to keep road in good condition for vehicle traffic,
will make any necessary repairs or fixes if needed. Contractor will do a complete pave of both Roads.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material)
Contractor Grading Paving Area.
5. Sketch or Paste Pictures Below:
Date
3/7/07
Typed or Printed Name and Title
Steve Harrington
Signature