City of Yelm Daily Inspection Form 4 Storm gallery
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 10/23/06
Day: Monday
Time: 9:30 a.m.
Project Name:
Bella Housa Village
Project Number
SUB-05-0058-YL
Project Description:
Subdivision
Contractor's Name:
Don Olson Construction
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Cool, cloudy, Soil conditions are Dirt and Rock
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.)
Contratractor placing 36” ADS for Infiltration Gallery. Contractor nearly complete with placing 36” storm line for the infiltration unit.
Sections of Infiltratin Gallery was put in place and back filled with washed rock and wrapped in geotextile fabric and backfilled with drain rock.
When completed with this run of 36” storm, the Contractor will place more 60” storm wet vault gallery. This will be from the east end of project at Sta.3+13.89
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material)
Contractor Placed section of 36 “ Infiltration Gallery.
5. Sketch or Paste Pictures Below:
Date
10/23/06
Typed or Printed Name and Title
Steve Harrington
Signature