City of Yelm Daily Inspection Form 6 infiltration gallery
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 10/26/06
Day: Thursday
Time: 3:00 p.m.
Project Name:
Bella Housa Village
Project Number
SUB-05-0058-YL
Project Description:
Subdivision
Contractor's Name:
Don Olson Construction
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Cool, cloudy, Soil conditions are Dirt and Rock
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.)
Contratractor placing 36” infiltration gallery section. Placing rock base and washed rock around 36” perf pipe and warapping with filter fabric. Backfill with
washed rock 1’ over and backfill above that with native.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material)
Contractor Placing section of 36 “ infiltration gallery.
5. Sketch or Paste Pictures Below:
Date
10/26/06
Typed or Printed Name and Title
Steve Harrington
Signature