City of Yelm Daily Inspection Form 8 D.I. storm line and Type 1 C.B.
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 11/13/06
Day: Monday
Time: 11:00 a.m.
Project Name:
Bella Housa Village
Project Number
SUB-05-0058-YL
Project Description:
Subdivision
Contractor's Name:
Don Olson Construction
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Cool, Sunny, Soil conditions are Dirt and Rock
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.)
Contratractor placing Type 1 C.B. # 1, 2 and approximately 23’ of 12” D.I. storm pipe. Type 1 C.B. # 14, 15 and approximately 95’ of 12” D.I. storm pipe. Type
1 C.B. # 17, 21 and approximately 35’ of 12” D.I. storm pipe.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material)
Contractor Placing 12” D.I. storm line and Type 1 C.B.’s
5. Sketch or Paste Pictures Below:
No pictures taken today.
Date
11/13/06
Typed or Printed Name and Title
Steve Harrington
Signature