From our Department walk thru conducted on Friday November 2, 2007. We discovered there were some issues with various driveways that appeared to be in conflict with utilities and street
trees, we notified you of these conditions and set up a meeting with Bob Holcomb of SCA (Designer), Merle Hom (Owner), John Sailing (Co-Owner), Nisha Box (City of Yelm) and Steve Harrington
(City of Yelm) last week on Wednesday November 7, 2007 at 10:30 a.m. on the Bella Housa project site. We discussed this issue and reviewed the plans on site. All driveways will be
put in per approved plans, any utilities or street trees that are in conflict with the driveways that were approved on the plans, will have to be relocated.
Please build per approved plans, with no deviations.
If you have any questions, please feel free to give me a call at (360) 458-8496.
Sincerely,
Steve Harrington
Civil Engineering Inspector
Community Development Department