04-0175 Walk Thru Request 123008 From: Steve Harrington
Sent: Tuesday, December 30, 2008 3:59 PM
To: Edward Smith; John Ivey; Jim Doty; Kevin Ray; Deonne Hardy; Karen Bennett
Cc: Grant Beck; Gary Carlson; Tim Peterson
Subject: FW: Johns Meadows Subdivision Requested Walk Thru-Inspection for Final Plat
Please find this e-mail to serve as official notice for request to conduct a walk thru and inspection for final plat for the below mentioned project. Please fully read the below
e-mail for the complete explanation. We request all items and comments e-mailed back to Karen and I by next Tuesday January 6, 2009
Thank you,
Steve Harrington
From: Nisha Box
Sent: Tuesday, December 30, 2008 3:24 PM
To: Steve Harrington
Subject: Johns Meadows Subdivision
Steve, please refer to this email when you request another punch list.
Project # SUB-04-0175-YL John’s Meadows Subdivision
Site Address: Located on
Middle Road, across from Willow Glen I & II
This project requested the original punch list in January 2007 and CDD began review of their Final Plat in May 2007.
A second review letter for the Final Plat review was sent to them in September 2007.
We have not heard anything back in regards to the second review until now.
Due to the fact that the applicant waited so long before responding to the 2nd Review letter from the City, we are requiring another walkthrough from all departments.
In the meantime, we will review the revised final plat map as well. The City will not approve the Final Plat if there are remaining items on the punchlist.
Thanks!
Nisha Rohila Box
Assistant Planner
City of Yelm
nishab@ci.yelm.wa.us