Water Construction Final Punchlist 010407Transmittal Letter ???????????????????? From: Edward Smith
Sent: Thursday, January 04, 2007 12:55 PM
To: Tim Peterson
Cc: Deonne Hardy; Jim Gibson; Kevin Ray; Steve Harrington
Subject: Joh's Meadow Public Works Inspection Report , Water Main Inspection and Punch List .doc
John's Meadow Punch list from the water department.
City of Yelm Public Works Department
901 Rhoton Road / P.O. Box 479
Yelm, WA 98597
(360) 458-8406 Fax: (360) 458-8417
Transmittal Letter
To:
Date:
Company:
Re:
City, St Zip
Name:
Items transmitted for:
Review and comment
For your records
As Requested
Other
Public Works Inspection Report
Date: 4/January/2006 ____________ Page _1 . __ of 1___
Location: __John’s Meadow _______________________________ Department: Water_________
Contractor: ________________________________ Les Russell Rep: Ken
1. Lot 1. – Raise meter box to final grade – Ensure all meter boxes are at final grade when landscape are finished.
2. The irrigation meter at the storm pond needs the Double Check Valve Assembly installed and test before the water is left on to the meter and the meter box needs to be
backed filled around.
3. The air release at the end of Greenbrier Court is in the wrong location, needs to be moved to other side of the meter setters as per print.
4. Lots 10 and 11 – Move the meter box back and straighten back of meter setters.
5. The meter setter at lot 31 needs to be raised.
6. The meter setter at lot 32 is installed backwards.
7. The air release at the end of Greenbrier Street is leaking.
8. Lots 12 and 13 – Move the meter box back and straighten back of meter setters
9. The fire hydrant at the end of Greenbrier Street is too high.
10. The fire hydrant at Cochrane and Middle Road is too high.
11. The irrigation meter Middle Road and Cochrane needs the Double Check Valve Assembly installed and test before the water is left on to the meter and the meter box needs
to be backed filled around.
12. Make sure all the Stroz’s fitting screws are tight.
13. Backflow assembly must be tested by a certified backflow tester and a copy of the report sent to the water department for the CCS files.
14. The Bacterial test results have been received and are good.
15. Is the well on the existing house going to be pulled and if so the water department needs a copy of the well being pulled report?
Inspection done by: John I.
Signed: Edward B. Smith
_______________
0.
__________________________________________________
_______________________________________________________________________________________________________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________________________________________________________________
_______________________________________________________________________________________________________________________________________________________________________________________________________
Signed: ______________________
Remarks:
Signed: Jim Gibson
Development Services Engineer