CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 10/02/06
Day: Friday
Time: 8:10 a.m.
Project Name:
Johns Meadow / Griffin Subdivision
Project Number
SUB-04-0175-YL
Project Description:
Subdivision
Contractor's Name:
Les Russell Construction
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Suny, warm, clear. Soil conditions are rocky, dry and dusty
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.)
Contractor has subgrade ready to be inspected the compaction and uniformity for subgrade is good. The grade and compaction is o.k. (Pass). Road way graded and good ballast material
added. Grade of road is uniform and up to proper grade.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Ballast is nice and uniform, Good compaction. Passed Proof Roll with full water tanker truck.
5. Sketch or Paste Pictures Below:
Date
10/02/06
Typed or Printed Name and Title
Steve Harrington
Signature