City of Yelm Inspection Form Jonhs Meadow 5 Paving City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 10/16/06 Day: Tuesday Time: 8:20 a.m.  Project Name: Johns Meadow / Griffin Subdivision Project Number SUB-04-0175-YL  Project Description: Subdivision Contractor's Name: Les Russell Construction / Lakeside Industries  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Suny, warm, clear. Road conditions are crushed rock top course, good compaction.  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor has compacted crushed top course rock. Lakeside is on site placing tack and paving inside of plat roadways. There were no signs of standing water or wet areas around curbs or catch basins. Barry or Lakeside said it is o.k. to pave, they will guarantee it. There is one area of roadway at Sta. A12+00 to A 11+58.12 on Road “A” that has a slight belly in it and is running flat. It appears that Lakeside may haved had a problem when they crowned it. Contractor is aware of the problem and has made Lakeside aware of the problem. Lakeside will fix it. Picture below with white truck, is the where the roadway is flator bellied and needs fixed.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Paving is complete expect for frontage  5. Sketch or Paste Pictures Below:    Date 10/16/06 Typed or Printed Name and Title Steve Harrington Signature